Bid 2027-04 sadie heights flood improvement project phase 2
Closed State & local contract opportunity Posted
- Solicitation number
- PE-66243-NONST-2027-000000092
- State
- Georgia
- Responses due
Opportunity facts
- NIGP codes
- UNSPSC codes
- 81141501 Materials testing
- 70131502 Soil conservation or protection services
- 81141510 Quality control and quality assurance audit and verification services
- 70171803 Flood protection or control services
- 81141502 Materials synthesis
- 81141503 Materials or product inspection
- 81141505 Production standards development
- 81141511 Quality control and quality assurance consultancy services
- 70171800 Drainage services
- 81141504 Equipment test calibration or repair
- Point of contact
-
- Dan Davis ddavis@intse.com (678) 552-2106
Opportunity details come from ssl.doas.state.ga.us. Updated .
About this opportunity
The City of Perry, Georgia is requesting sealed bids for the Sadie Heights Flood Improvement Project Phase 2A, consisting of excavation, grading, and drainage-channel improvements between Stonegate Trail and Rocky Road, with bids due October 16, 2026 at 11:00 a.m. and a mandatory pre-bid meeting and field visit on September 22, 2026 at 2:00 p.m. at the City of Perry Administrative Building. This is a locally funded municipal project with no stated set-aside or preference restriction.
Phase 2A encompasses clearing and grubbing, mass rock excavation, grading, traffic control, demolition, erosion control, easement-related work including fence removal and relocation, tree removal, and structure relocation across multiple properties. Phase 2B will be constructed separately by the developer of the future Avion Park subdivision; both phases are anticipated to proceed concurrently and require coordination between the City's contractor and the developer's contractor. The scope spans approximately 82 line items with unit pricing required. Bidders must submit a Construction Contractor's Qualification Statement, Non-Collusion Affidavit, Security and Immigration Compliance Affidavit with E-Verify documentation, and a completed Bid Form. A $25 payment to Integrated Science & Engineering is required to obtain bidding documents. Bid security of 5% of the maximum bid price is mandatory.
Substantial Completion is required within 240 calendar days from Notice to Proceed; Final Completion within an additional 60 calendar days. Liquidated damages of $500 per day apply for delays beyond these milestones. The successful bidder must execute performance and payment bonds and provide contract insurance, with all documentation due within 15 business days of Notice of Award. Contract payments are progress-based with 5% retainage; upon Substantial Completion, payment reaches 100% of completed work less items requiring correction. Final payment includes interest on retained amounts per Georgia Code 13-10-81. Integrated Science & Engineering provides engineering services. Questions are due prior to the pre-bid meeting on September 22.
Opportunity text
The Flood Improvement Project Phase 2A consists of excavating and grading a portion of the regional inline stormwater pond and improving the drainage channels between Stonegate Trail and Rocky Road. The Phase 2B portion of the pond will be constructed separately by others and will consist of excavating and grading the remaining portion of the pond by the developer of the future Avion Park subdivision. Phase 2A and Phase 2B are anticipated to be constructed concurrently and will require coordination between the City's contractor and the developer's contractor. Together, the completed improvements will provide additional flood storage and improve drainage in Sadie Heights and the surrounding area.
Files
| File | Type | Posted |
|---|---|---|
| Sadie Heights Flood Improvement Project Phase.pdf |
On GovTribe
Work this opportunity
- Track it in your pipeline
- Similar opportunities
- Ask GovTribe AI about this opportunity