2026 City Overlay #2
Closed State & local contract opportunity Posted
- Solicitation number
- S-18-26
- State
- Wyoming
- Responses due
Opportunity facts
- Jurisdiction
- Point of contact
-
- TJ Barttelbort tbarttelbort@cheyennecity.org (307) 773-1045
Opportunity details come from procurement.opengov.com. Updated .
About this opportunity
The City of Cheyenne, Wyoming, acting on behalf of Natrona County, is soliciting sealed bids via Invitation for Bid (IFB #S-18-26) for the 2026 City Overlay #2 project, a comprehensive roadway and pedestrian infrastructure improvement initiative funded through the City's 1% Sales Tax program. The scope of work encompasses over 80 line items across four primary corridors (Concord Road, Hickory Place, Pershing Boulevard, and Hynds Boulevard/Kennedy Drive/Stinner Road) totaling approximately 6.3 miles and including asphalt milling, patching, and paving; excavation and grading; concrete pavement replacement; curb and gutter reconstruction; sidewalk installation; alley restoration; utility adjustments; signage installation; landscaping restoration; irrigation repairs; traffic control measures; pavement markings and thermoplastic striping; ADA detectable warning plates; and erosion and stormwater management measures. Bidders must be able to execute work in compliance with the 2022 City of Cheyenne and Board of Public Utilities Construction Specifications and Standard Drawings, provide detailed quality control and material testing through AASHTO-accredited independent laboratories, maintain commercial general liability insurance of $1,000,000 per occurrence and business automobile liability insurance of $1,000,000 combined single limit, and furnish performance and payment bonds equal to 100 percent of the accepted bid. Electronic bids must be submitted via the City's eProcurement Portal by 2:00 PM Mountain Time on June 8, 2026, with a question submission deadline of May 28, 2026 and an optional pre-bid meeting scheduled for May 20, 2026 at 2:00 PM via Zoom; contract award is anticipated for July 13, 2026, with Notice to Proceed on approximately July 20, 2026, and project completion required by December 31, 2026.
Wyoming resident contractors receive a five percent (5%) price preference and may not subcontract more than 30 percent of work to nonresidents, with Wyoming materials and labor preferred and a five percent (5%) cost differential allowable. All bidders must submit a bid guarantee equal to five percent (5%) of the total bid amount in the form of a bid bond or cashier's check, along with non-collusion affidavits, subcontractor lists, and all required bidding documentation; bids lacking required documentation will be deemed non-responsive. The contract award will be made to the lowest total responsive bid from the most qualified and responsible bidder, provided the bid does not exceed available project funds. The City will withhold five percent (5%) retainage from all progress payments for contracts exceeding $50,000 for a minimum of forty-one calendar days following publication of Notice of Final Settlement in compliance with Wyoming Statute 16-6-116, with mobilization payment structured incrementally from 10 percent upon the first estimate to 100 percent upon completion. No specific incumbent vendors or current contractors are identified in the procurement documents, and the contract includes a mandatory two-year warranty period commencing from the date of Substantial Completion. While the exact total project budget is not explicitly stated, the scope encompasses substantial quantities including 31,660 square yards of cold asphalt milling, 3,947 tons of plant mix bituminous pavement, and thousands of linear feet of pavement markings across multiple corridors, indicating a project value likely in the multi-million dollar range.
Opportunity text
This project generally consists of roadway and pedestrian infrastructure improvements, including asphalt milling, patching, paving, excavation, grading, alley restoration, and concrete pavement replacement. The work also includes reconstruction and installation of curb and gutter, sidewalks, valley pans, drain pans, drive approaches, utility adjustments, signage, landscaping restoration, irrigation repairs, and erosion and stormwater management measures.
Additional improvements include traffic control, pavement markings, thermoplastic striping and symbols, ADA detectable warning plates, and other related appurtenances necessary to complete the roadway, pedestrian, and traffic safety enhancements.
Files
On GovTribe
Work this opportunity
- Track it in your pipeline
- Similar opportunities
- Ask GovTribe AI about this opportunity