2025 Piping & Clearwell Improvements
Closed State & local contract opportunity Posted
- Solicitation number
- PE-66412-NONST-2025-000000011
- State
- Georgia
- Responses due
Opportunity facts
- Jurisdiction
- NIGP codes
- 63010 Coatings, Protective, Polyurethane, Etc.
- 91359 Construction And Upgrades, Wastewater Treatment Plant
- 91360 Construction, Water System/Plants, Main And Service Line
- 91391 Maintenance And Repair, Wastewater Treatment Plant
- 93462 Pipe And Pipe Fittings Maintenance And Repair
- 96848 Inspection Services, Electrical Instrumentation And Control
- UNSPSC codes
- 95121810 Irrigation and flood control waterworks
- 95121642 Sewage pumping station
- 72121505 Waste water and sewage treatment plant construction service
- 95121811 Aquaduct or other water supply conduit, except pipeline
- 95121643 Sewage outfall
- 72121504 Waste disposal plant construction service
- 72141121 Water main construction service
- 72141125 Pumping station construction service
- 95121805 Well
- 95121804 Water tower
- Point of contact
-
- Tiffany Barry tbarry@dccm.com (706) 213-3105
Opportunity details come from ssl.doas.state.ga.us. Updated .
About this opportunity
The state and local contract opportunity is a procurement by Dooly County, Georgia, for the 2025 Piping & Clearwell Improvements project at a water treatment plant. The project involves comprehensive renovations to enhance water production system reliability and efficiency, specifically including modifications to valves and piping, influent connection alterations to Clearwell No. 2, improvements to the chemical vault, renovations to Clearwell No. 1, storm drain system enhancements, and minor cosmetic plant renovations. Sealed bids are due by 10:00 AM local time on February 20, 2025, at Elberton City Hall, with a public bid opening immediately following. Contractor questions must be electronically submitted to tccm.com by February 6, 2025. Bidders are required to possess a valid Georgia "Utility Contractor" license and employ a certified "Utility Manager." The project documentation can be obtained from PeoplesQuigley | DCCM for a non-refundable fee of $100 per set, and is partially funded by the Georgia Environmental Finance Authority.
The contract opportunity requires bidders to submit a bid bond or certified cashier's check for 5% of the bid amount, with successful bidders needing to provide Performance and Payment Bonds covering 100% of the contract value. The project is subject to the Build America, Buy America Act requirements, which may impose additional procurement restrictions. While specific set-aside designations are not explicitly mentioned, the complexity of the project suggests a preference for experienced utility contractors with demonstrated capabilities in municipal water treatment infrastructure improvements. The City reserves the right to delay award for up to 60 days and maintains the discretion to reject any or all bids. Although a precise budget range is not specified in the available documentation, the comprehensive nature of the improvements and the involvement of the Georgia Environmental Finance Authority indicates a significant infrastructure investment for Dooly County's water treatment capabilities.
Opportunity text
The work consists of renovations to the water treatment plant system components to enhance the reliability and efficiency of water production. This includes the modification and addition of valves and piping, modification of influent connection to Clearwell No. 2, improvement of the piping and chemical vault, renovations to Clearwell No. 1, improvements to the storm drain system, and minor cosmetic renovations to the plant.
Files
| File | Type | Posted |
|---|---|---|
| SecAMmas _ 448_03G.pdf |
On GovTribe
Work this opportunity
- Track it in your pipeline
- Similar opportunities
- Ask GovTribe AI about this opportunity