04-2J88U4 Bridge Scour Repair
Open State & local contract opportunity Posted
- Solicitation number
- 04-2J88U4
- State
- California
- Responses due
Opportunity facts
- Jurisdiction
- Point of contact
-
- Office Engineer occa@dot.ca.gov (916) 227-6299
Opportunity details come from constructionbidsource.com. Updated .
About this opportunity
The California Department of Transportation (Caltrans) is soliciting bids for bridge scour repair at the No Name Creek Bridge on State Highway 29 near Calistoga in Napa County, with bids due December 15, 2026, submitted electronically via Bid Express. The contract is a non-federal-aid project with a Small Business Enterprise (SBE) participation goal of 5 percent and a Disabled Veteran Business Enterprise (DVBE) goal of 5 percent. Bidders must submit a 10 percent bidder's security and complete SBE and DVBE documentation as required.
The scope covers scour hole repair, rock slope protection, erosion control, landscape work, and temporary traffic control, with a 64-line-item bid schedule spanning water pollution control, excavation, concrete repair, plant establishment, and roadway markings. Temporary barriers and crash cushions must comply with MASH test levels. The contractor must hold a Class A license or a combination of Class C licenses (C-12, C-27, C-8) constituting a majority of the work. Creek channel work is limited to June 15 through October 15 annually. The project requires local material sampling and analysis for lead contamination, lead compliance planning, and fire safety protocols specific to the project area near Lake County. The contractor must coordinate with coincident or adjacent contracts. The contract incorporates the 2025 Standard Specifications and 2025 Standard Plans, and prevailing wages apply as determined by the California Director of Industrial Relations.
The estimated project cost is $880,000. Work must be completed within 80 working days excluding plant establishment work, or within 330 working days including it, with plant establishment work completed within 250 working days.
Opportunity text
General work description: Bridge scour repair. Complete the work, excluding plant establishment work, within 80 working days. Complete the work, including plant establishment work, within 330 working days. Complete the plant establishment work within 250 working days.
Files
| File | Type | Posted |
|---|---|---|
| 04-2J88U4 Bridge Scour Repair.pdf |
On GovTribe
Work this opportunity
- Track it in your pipeline
- Similar opportunities
- Ask GovTribe AI about this opportunity