P-8A MS (COMMS) MUOS mod to add Lot 13 and SDD A/C_N0001921G0006_N0001923F0458
Past New Requirement Updated
- Agency
-
Naval Air Systems Command HQ
Naval Air Systems Command, Department of Defense
- Solicitation expected
- Estimated value
- $2,000,000 to $7,500,000
- Set-aside
- No set-aside
Forecast facts
- Anticipated award
- Through
- NAICS code
- 336411 Aircraft Manufacturing
- Place of performance
- Pax River, MD
- Forecast number
- N00019-26-RFPREQ-APM290-0633
Forecast details come from the Navy's Long Range Acquisition Estimates. Agencies' dates and values are estimates.
About this forecast
Naval Air Systems Command is modifying Contract N0001921G0006 to add 7 Lot-13 P-8A Poseidon aircraft with MUOS (Mobile User Objective System) capability and 4 System Design and Demonstration aircraft, extending the period of performance from December 31, 2026 to December 31, 2028 to align with SATURN modification testing and accommodate delayed B-Kit funding. The modification updates contract documentation, increases the ceiling, and modifies the statement of work to address miscommunication between Boeing and the Navy regarding test aircraft definitions and to consolidate scheduled maintenance windows.
The estimated modification cost is $3.5 million against a total award value range of $2 million to $7.5 million, with performance at Patuxent River, Maryland. This sole-source modification to the existing basic ordering agreement employs cost-reimbursement pricing and was released for solicitation in fiscal 2026 quarter 2, with an estimated award date of July 1, 2026. The contracting office is Naval Air Systems Command HQ (N00019-HQ), supporting program executive office APM290 (PEO A), and requires no facility or personnel security clearances.
Forecast text
Modification to Contract # N0001921G0006
Order number: N0001923F0458
Increase ceiling, update one CDRL, modify SOW.
MUOS Contract Modification Objectives:
1. Add Qty 7 USN Lot-13 BuNo MUOS NRE
a. Lot-13 did not exist when original contract was awarded
2. Add Qty 4 USN System Design and Demonstration (SDD) MUOS NRE
a. Miscommunication between Boeing and USN on definition of test aircraft.
3. Extend the PoP from December 31 2026 to December 31 2028.
a. Match up with the SATURN PoP so that test aircraft only has to be taken out of service once for both modifications.
b. MUOS and SATURN have been pushed back to FR-125 this schedule better aligns with the test software releases.
c. PMA-209 funding for B-Kits has been delayed by 1 year. FY27 to FY28.
Estimated Cost of Mod is $3.5M based on existing MUOS and SATURN NRE contracts