Modification to Order #N4008421F4486_1702972 (QC1022-2) RM21-1012 FSS REPAIR FIRE PUMPS AND PIPING SYSTEM PHASE 2&3, F-200090
Past New Requirement Updated
- Agency
-
Navy NAVFAC Far East
Naval Facilities Engineering Command, Department of Defense
- Solicitation expected
- Estimated value
- Up to $2,000,000
- Set-aside
- No set-aside
Forecast facts
- Anticipated award
- NAICS code
- Not on record
- Place of performance
- FPO, AP
- Forecast number
- N40084-26-RFPREQ-FE-D-GARCIA FEAD-0032
Forecast details come from the Navy's Long Range Acquisition Estimates. Agencies' dates and values are estimates.
About this forecast
The Department of the Navy Naval Facilities Engineering Command Far East is modifying an awarded task order to de-scope fire water distribution pipeline installation, fire hydrant assemblies with bollards and accessories, earthworks (excavation, backfilling, compaction), pavement restoration, testing services, and lead-based paint management and disposal coordination with host nation compliance. The modification is fixed-price, sole-source, and estimated to release and award on 2026-04-01 under an indefinite-delivery contract vehicle.
The estimated award value does not exceed $2 million. The modification also addresses storage and Government pickup or transportation of materials previously invoiced in April 2024 and March 2026, to be maintained per manufacturer specifications at designated locations. Work is performed by NAVFAC Far East, with the requirement office at D-Garcia ROICC, NAVFAC Far East.
Forecast text
The Government proposes to de-scope the following from the awarded task order.
1.The removal and provision of fire water distribution pipeline, fire hydrant assemblies including bollards, its components and accessories. This includes earthworks such as excavation, backfilling and compaction. Restoration of disturbed pavement.
2.The provision of testing.
3.The performance of Lead-based paint management/control including host nation laws for waste regulations for segregation, containment, removal and disposal. The requirement of coordination for Lead waste management and disposal with NSF PWD Environmental.
4.All the materials that are paid by the Government under 1st invoice dated April 2024 (Enclosure 1) and 2nd invoice dated March 2026 (Enclosure 2) should be stored properly per manufacturer’s instruction and will be available for Government pick up anytime or transported to Government designated location.