Z1DA--SPECIAL Repair Water Main Break (VA-22-00060338)
Award Notice Posted
- Solicitation number
- 36C26322Q0421
- Agency
-
Veterans Integrated Service Network 23
Veterans Health Administration, Department of Veterans Affairs
- Awarded
- to BKM Construction LLC
- Set-aside
- Service-Disabled Veteran-Owned Small Business
Opportunity facts
- Contract number
- 36C26322P0486 Federal contract award
- NAICS code
- 236220 Commercial and Institutional Building Construction
Notice details come from SAM.gov. Updated .
Notice text
Statement of Work
Water Main Repair
1. PROJECT SCOPE:
a. The primary objective of this project is to have a contractor identify location(s) of
underground water line leak(s), repair broken water line, backfill, replace
pavement, and haul waste off site. The location of this broken water line is South
of building 6 (Dental).
b. The Contractor shall promote safe practice by following all OSHA regulations
and specification 01-35-26 (safety requirements).
2. PLACE OF PERFORMANCE:
a. VA Nebraska-Western Iowa Health Care System, Omaha Campus, 4101
Woolworth Avenue, Omaha, Nebraska 68105
3. PERIOD OF PERFORMANCE AND SCHEDULE:
a. All services shall be successfully completed during the period of performance
from Award plus 15 days.
b. It is anticipated that the work will be phased between normal business hours
(Monday through Friday, 8:00 AM to 4:30 PM Central), after hours and weekends
to accommodate the period of performance.
c. The onsite evaluation services are anticipated to take no more than 15 working
days to complete. The Contractor and VA Technical Representative shall agree on
a timeframe for the work schedule.
d. A detailed work schedule of the services shall be discussed at the preliminary
project review meeting with the VA Technical Representative and other VA
personnel 1 day after contract award.
e. The services shall be scheduled to minimize the disruption to patient care, ER and
dental entrances. It is required that ambulance entry and exit are not affected
during repairs.
4. CONTRACTOR PERFORMANCE REQUIREMENTS:
a. Contractor to provide equipment and manpower to excavate to water line leak(s) in
parking lot 3, South of building 6 (Dental), in Parking Lot 3 adjacent to the Emergency
Room. See Illustration 1. Work will include removal of pavement, possible curb
removal sections as required to safely access the leaking water main. See below
illustrations for approximate location.
b. Contractor to provide equipment, materials, and labor to repair water line leak(s) causing
damage to the pavement in the location referenced above.
c. Contractor will excavate repair site deep enough to keep the water in the excavation
adequately below the pipe and have pumps available to maintain the excavation water
level below the level of the water pipe to avoid contamination. The interior of the
couplings, repair pipe and other fittings used for the repair must be cleaned and washed
with a bleach solution just before installation. Depending on the length of the repair pipe,
a cloth swab soaked in bleach may be needed to clean and disinfect the interior of the
pipe. Both exterior ends of the repair pipe must be cleaned and disinfected in the same
manner as the water main ends. Care must be taken not to contaminate the couplings or
repair pipe with soil or trench water during installation.
d. Contractor will disinfect water in the water main after repair to achieve a chlorine level of
at least 2 mg/L (200 PPM) for a minimum of 2 hours. After chlorine treatment, the water
in the system needs to be flushed to remove air and/or particulates. After flushing, the
level of chlorine remaining in the water cannot exceed 4 mg/L in accordance with EPA
drinking water standards.
e. Contractor to provide equipment, material, and labor to back fill the excavations around
pipes upon completion of repairs. Material used to backfill excavations at must be
suitable for the subgrade to support pavement and must be properly compacted. Backfill
over the water lines and in the vicinity of the valve will not use excavated material that is
saturated.
f. Contractor will replace pavement, and curb sections removed for the work. Pavement
work will take precautions to protect the work from subfreezing temperatures.
g. 1-year warranty for all work being performed.
h. The Contractor shall conduct a final review meeting with the VA Technical
Representative and other VA personnel. This final review meeting can be completed
virtually or at the Omaha VA Facility. During the final debrief the site will be reviewed
for the above requirements.
i. The contractor is responsible for setting up a barrier between the construction site and
public to avoid unauthorized access to the construction zone. The pavement repairs and
construction barrier should not exceed beyond the affected area.
j. If any property damage is caused by the Contractor in performance of the contracted
services, the Contractor shall provide the necessary repairs to the original or better
condition at no additional cost to the Government.
Illustration 1: Building 6 (Dental) piping repairs
Illustration 2: Dental piping repairs
B. CONTRACTOR QUALIFICATIONS:
The contractor shall be licensed to operate excavation equipment.
C. GENERAL REQUIREMENTS:
a. Site investigation: The contractor will engage Engineering Maintenance and Operation
Staff in surveying activities. The contractor will promptly report any discrepancies to the
VA Technical Representative for clarification and if disruptions to patient care will
ensue.
b. Sustainable Principles. The Engineer shall incorporate green building and sustainable
practices and elements into solutions to the greatest extent practicable.
c. Badging. Contractor personnel who will be providing services on-site at the VA Facilities
will be required to obtain a flash badge prior to beginning services. A vendor badge can
be used in the interim and short term (during normal business hours). Documentation to
request and obtain a flash badge will be provided to the Contractor after contract award.
d. It shall be understood that, throughout performance of the contract, the Contractor s
personnel, while on VA property, shall adhere to all requirements and regulations that
govern the VA Health Care System and its property.
e. Among all other requirements, the VA Health Care System and its property is now
entirely smoke-free.
f. COVID-19 Protocols must be followed.
D. LIMITATIONS OF SUBCONTRACTING
a. By submission of an offer and execution of a contract, the Offeror/Contractor agrees in
performance of the contract in the case of a contract for Services, it will not pay more
than 50 percent of the amount paid by the Government for contract performance to
subcontractors that are not similarly situated entities. Any work that a similarly situated
entity further subcontracts will count toward the 50 percent subcontract amount that
cannot be exceeded.
b. An independent contractor shall be considered a subcontractor.
E. NATIONAL ARCHIVES AND RECORDS ADMINISTRATION (NARA) RECORDS
MANAGEMENT LANGUAGE FOR CONTRACTS
a. Citations to pertinent laws, codes, and regulations such as 44 U.S.C. Chapter 21, 29, 31
and 33; Freedom of Information Act (5 U.S.C. 552); Privacy Act (5 U.S.C. 552a); 36
CFR Part 1222 and Part 1228.
b. Contractor shall treat all deliverables under the contract as the property of the U.S.
Government for which the Government Agency shall have unlimited rights to use,
dispose of, or disclose such data contained therein as it determines to be in the public
interest.
c. Contractor shall not create or maintain any records that are not specifically tied to or
authorized by the contract using Government IT equipment and/or Government records.
d. Contractor shall not retain, use, sell, or disseminate copies of any deliverable that
contains information covered by the Privacy Act of 1974 or that which is generally
protected by the Freedom of Information Act.
e. Contractor shall not create or maintain any records containing any Government Agency
records that are not specifically tied to or authorized by the contract.
f. The Government Agency owns the rights to all data/records produced as part of this
contract.
g. The Government Agency owns the rights to all electronic information (electronic data,
electronic information systems, electronic databases, etc.) and all supporting
documentation created as part of this contract. Contractor must deliver sufficient
technical documentation with all data deliverables to permit the agency to use the data.
h. Contractor agrees to comply with Federal and Agency records management policies,
including those policies associated with the safeguarding of records covered by the
Privacy Act of 1974. These policies include the preservation of all records created or
received regardless of format [paper, electronic, etc.] or mode of transmission [e-mail,
fax, etc.] or state of completion [draft, final, etc.].
i. No disposition of documents will be allowed without the prior written consent of the
Contracting Officer. The Agency and its contractors are responsible for preventing the
alienation or unauthorized destruction of records, including all forms of mutilation.
Willful and unlawful destruction, damage or alienation of Federal records is subject to the
fines and penalties imposed by 18 U.S.C. 2701. Records may not be removed from the
legal custody of the Agency or destroyed without regard to the provisions of the agency
records schedules.
j. Contractor is required to obtain the Contracting Officer's approval prior to engaging in
any contractual relationship (sub-contractor) in support of this contract requiring the
disclosure of information, documentary material and/or records generated under or
relating to this contract. The Contractor (and any sub-contractor) is required to abide by
Government and Agency guidance for protecting sensitive and proprietary information. Awarded contract 36C26322P0486 to BKM CONSTRUCTION LLC for 110373.00000000 on 2022-05-13.
Files
| File | Type | Posted |
|---|---|---|
| 36C26322P0486_1.docx | DOCX document | |
| P03_Justification and Approval for Limited Sources (Signed)_Redacted.pdf |