Z1DA--607-21-155 upgrade eagle and freight elevators (VA-23-00006591)

Closed Solicitation Posted

This opportunity was awarded. See the award notice from .

Solicitation number
36C25222B0034
Agency
Responses due
Set-aside
No set-aside

Opportunity facts

Notice details come from SAM.gov. Updated .

About this opportunity

This solicitation seeks proposals to upgrade two elevators at the William S. Middleton VA Hospital in Madison, Wisconsin. The Department of Veterans Affairs is procuring elevator modernization services including demolition, construction, equipment replacement, and mechanical, electrical, and plumbing work. Proposals will be evaluated based on price, technical approach, and past performance. Proposals are due by October 6, 2022.

This is a 100% set-aside for Service-Disabled Veteran-Owned Small Businesses under NAICS code 238290. The place of performance is the Veterans Integrated Service Network 12 facility located in Madison, Wisconsin. The estimated value is between $2-5 million to be completed within 550 calendar days from award. The elevators to be upgraded are the Eagle and Freight elevators.

Notice text

4 versions

Update #4 · Latest ·

Accompanying Amendment 36C25222B0034 0003

Accompanying Amendment 36C25222B0034 - 0003

Upgrade Eagle & Freight Elevators

William S. Middleton VA Hospital, Madison, WI

I. bid opening information:

the bid opening date is hereby changed as indicated below.

a. VIRTUAL BID OPENING INFORMATION:

1) Reminder, there will be no in-person public bid opening process this will be conducted as a public virtual activity.

2) The virtual bid opening will be available to the public via Microsoft Teams at the following link and/or phone number;

Click here to join the meeting

(Meeting will be available to be accessed 15 min prior to bid opening)

Meeting phone number: 872-701-0185

Phone Conference ID: 978273801#

3) IAW FAR 52.214-5 Submission of Bids and 14.202-8 Electronic Bids; Bids shall be provided via email to the Contracting Officer at john.meyers2@va.gov as follows;

Vendor bids are due via email as shown above at 12:00 PM local time on 10/6/2022.

The virtual public bid opening will be held at 1:00 PM local time on 10/6/2022 at the link and/or the phone # provided above.

A hard copy submission is not required. Any bids received after the date and time specified for receipt of bids will be processed in accordance with FAR 52.214-7 Late Submissions, Modifications, and Withdrawals of Bids (Nov 1999).

4) Ensure your complete bid including bid bond are provided in your submission. The successful low bidder is required to furnish their original bid bond within five (5) days after notification by the Contracting Officer.

5) It is highly recommended that Bidders submit their bid at least one hour prior to bid opening to avoid any transmission issues.

II. The following changes are made to the solicitation:

1. The attached revised SF 1442 page one, updates block 13. a. with the revised bid due date of 10/6/2022.

III. The following changes are made to the specifications:

1. Specification section 25 13 00 Building Automation Systems (BAS) Integration is hereby added to the project specifications.

There are no further changes.

Update #3 ·

Accompanying Amendment 36C25222B0034 0002

Accompanying Amendment 36C25222B0034 - 0002

Upgrade Eagle & Freight Elevators

William S. Middleton VA Hospital, Madison, WI

I. bid opening information:

There is no change to the bid opening date, the information remains the same as Amendment 0001 as listed below.

a. VIRTUAL BID OPENING INFORMATION:

1) Reminder, there will be no in-person public bid opening process this will be conducted as a public virtual activity.

2) The virtual bid opening will be available to the public via Microsoft Teams at the following link and/or phone number;

Click here to join the meeting

(Meeting will be available to be accessed 15 min prior to bid opening)

Meeting phone number: 872-701-0185

Phone Conference ID: 543269745#

3) IAW FAR 52.214-5 Submission of Bids and 14.202-8 Electronic Bids; Bids shall be provided via email to the Contracting Officer at john.meyers2@va.gov as follows;

Vendor bids are due via email as shown above at 12:00 PM local time on 9/29/2022.

The virtual public bid opening will be held at 1:00 PM local time on 9/29/2022 at the link and/or the phone # provided above.

A hard copy submission is not required. Any bids received after the date and time specified for receipt of bids will be processed in accordance with FAR 52.214-7 Late Submissions, Modifications, and Withdrawals of Bids (Nov 1999).

4) Ensure your complete bid including bid bond are provided in your submission. The successful low bidder is required to furnish their original bid bond within five (5) days after notification by the Contracting Officer.

5) It is highly recommended that Bidders submit their bid at least one hour prior to bid opening to avoid any transmission issues.

II. The following Questions and Answers / Clarifications are the result of bidders request(s) for information:

Q1. Can all work be done during normal daytime work shifts?

A1. Noise concerns and any potential scheduling will be evaluated on a case-by-case basis during the project considering the level of noise/vibration and the impacted area type.

Normal VA business hours are 7am-4:30pm. All work must be coordinated to minimize disruption and downtime. Potential scheduling will be evaluated on a case-by-case basis. See Drawing G002 Note 15 for additional requirements.

Q2. Can the Site Superintendent fulfill the duties of the SSHO as well?

A2. Yes.

Q3. What is the anticipated award / NTP / Start timeline for this project?

A3. Anticipated Award: Oct 25, 2022. Anticipated Notice to Proceed: November 7., 2022. Elevator modernization and elevator shutdowns cannot start until submittals have been approved and materials ship timeline has been established. See Spec 01 00 00 and Drawings G002 & 003 for Phasing requirements.

Q4. How will extended lead times on new equipment be delt with? Items like HVAC Equipment, Electrical Gear, and elevator equipment?

A4. Equipment lead time are unpredictable and now industry norm. Extended lead times will be dealt with on a case-by-case basis. Contractor to keep the VA informed of any possible or anticipated delivery delays that may potentially impact the project schedule.

Q5. Is there a specific location for a site construction Trailer / Staging Area / Dumpsters? If so, can you please advise where it is located?

A5. Construction trailer is not allowed specifically for this project. Staging Space is limited. VA will seek to provide limited space and duration staging on as as-needed basis.

Q6. Will a Construction Fence be required around the staging area and trailer?

A6. Outside staging area is not permitted nor is a trailer.

Q7. In section 01 00 00 1.12.C, referring to delivering two electronic copies of complete As Builts after each completed phase. This also applies to shop drawings. If electronic, does the VA require two?

A7. Yes. Section 01 00 00 1.12.D states paragraphs A,B and C shall also apply to shop drawings.

Q8. Per section 01 00 00.1.18.B, Does the VA require four hard copies of the completed O&M? Do the manuals require delivery when the equipment arrives or at substantial completion?

A8. Two hard copies of the O & M Manuals are acceptable, to be delivered at the completion of the project.

Q9. Is a submittal log/register required for submission by the contractor for this project? Reference 01 33 23 1.3.C, the VA provides the initial submittal register.

A9. Yes.

Q10. Is Submittal Exchange required for this project and who shall pay for the services of Submittal Exchange?

A10. VA intends to pursue purchasing Submittal Exchange for this project, at cost to the government.

Q11. Reference 01 35 26. Page 1. The TOC references 1.13 as Tuberculosis Screening but it appears that section was removed from the part of the spec and 1.13 as contained in the specifications is actually Fire Safety . Please confirm the TOC of specification Section 01 35 26 is not correct and TB Screenings are not part of this project.

A11. Spec Section 01 35 26 is not correct. TB Screening is not required.

Q12. Would Infection Controls Barriers like Edge Guard be allowed on the 8th floor for the Temporary Dust Partitions from Floor to ceiling and then fire Rated poly above the ceiling? Existing mechanicals and utilities above ceilings could cause full height partitions to be extremely difficult.

A12. Yes, Edge Guard is acceptable.

Q13. Will crane picks for the rigging of HVAC equipment and materials be restricted to federal holidays and weekends?

A13. No.

Q14. Is AISC Steel Certification required for Both the Fabricator and the installer?

A14. Yes, refer to 05 12 00, 3 1.5 A.& B.

Q15. Is the Third-Party Fire Penetration inspector hired by contractor or the VA?

A15. Yes, refer to 07 84 00, 1.5.

Q16. Will the VA be providing the services of a Commissioning Agent? As there is not a Commissioning Specification in this project, what is expected from the contractor for Commissioning?

A16. Commissioning/Commissioning Agent is not required on this Project.

Q17. Specification Section 23 31 00, 3.1, item K . Please clarify the expectations of ductwork cleaning. How far back do we clean when connecting new ductwork to existing. It would seem unreasonable to clean all the way back to the existing exhaust fan or air handling unit.

A17. At the point of new connection, clean the first two feet of the existing ductwork.

Q18. Specification Section 23 31 00, duct cleaning. During construction we have will the ends of all new ductwork wrapped in plastic to protect the integrity of the ductwork. Plastic will be removed just prior to system start up. Will machine cleaning of protected ductwork be a requirement of the project

A18. No.

Q19. Has the VA tested the ductwork and mechanical systems scheduled for demolition or relocation for biohazards. If the ductwork or equipment are contaminated, remediation will be required and due to insurance protocol, we cannot subcontract for the remediation.

A19. There is no known biohazards involved in this project.

Q20. Specification Section 23 31 00, Section 3.2, items B thru H , will leak testing be required on ductwork down stream of air terminal units?

A20. There are no Air Terminals to be installed during this project.

Q21. Do the VA require the MEPF contractors need to include hours for training? If so can you please advise what Training will be required?

A21. Training requirements are limited to the specification requirements.

Q22. Above ceiling demolition of MEP s that are not shown on the drawing and not able to be investigated at the walk thru. How are these to be handled?

A22. If above ceiling mechanical/utility conflicts are found and are not specifically address by the plans and specifications. Notify the COR at the time of discovery for further direction.

Q23. If conflicts between new work and existing mechanicals / Utilities are found to exist above the ceiling, that are not indicated on the drawings, will these items require relocation by the contractor, or will the VA have these items relocated?

A23. If above ceiling mechanical/utility conflicts are found and are not specifically address by the plans and specifications. Notify the COR at the time of discovery for further direction.

Q24. Please advise how access to the Elevator pits are going to be dealt with. How will they be classified and what are the procedures for accessing them Limited access, or non-Permit required confined space, or Permit required confined space? Please advise of classification and procedures for access.

A24. The VA does not consider the elevator pits as confined spaces. Eagle Elevator Pit is a walk-in pit, with limited key controlled for authorized personnel only. Elevators #5 & #6 are below grade pits assessable by standard elevator industry practice. Qualified elevator and VA personnel only are allowed access to the pits.

Q25. Are new handrails required to be added to the tops of the existing cars and is there space for the new handrails?

A25. Yes, there is space for new car top handrails. The elevator modernizations are required to meet all applicable portions of ASME 17.1 2019. This includes installation of car top handrails.

Q26. Is fire treated plywood required for the sub floor for the new flooring? As there have been issues with flooring adhesive adhering to fire treated plywood. Please advise.

A26. Contractor may substitute a 5-ply marine grade plywood for treated plywood.

Q27. Amendment 001 adds scope to the project. Removal of the SPS dumbwaiters. Will added drawings be issued in another amendment to clarify and detail out the scope of work for other trades? Electrical, Infection control requirements, Padlock specifications, are any new finished required. Please advise.

A27. No drawings of the dumbwaiters will be issued. All work associated with the removal of the dumbwaiter as detailed in the amendment shall be completed by licensed qualified elevator tradesmen. Infection control containment barrier is limited room B48 . Work will be subject to an infection control risk assessment as defined in specification 01 35 26. Work will be subject to the results of that assessment.

Q28. Will this added scope of the dumbwaiters change the overall performance period of the contract?

A28. Overall performance period will not change.

Q29. In reviewing the Amendment 001 and the added scope for the decommissioning of the dumbwaiters, I was asked if there would be another walk thru for the Dumbwaiter removal Scope?

A29. There are no additional site visits scheduled. Contractor may request a site visit if desire. Contact Brendan McLaughlin at 608-256-1901 x11157 or Jason Dickman at 608-256-1901 x11173

Q30. If there are no plans to install a new dumbwaiter in the future, do these have to be decommissioned by an elevator company?

A30. The dumbwaiters have been shut-down and are not in service. Â Removal (decommissioning) of the dumbwaiter equipment should be performed by qualified elevator mechanics. Â Â

III. general information:

Replace the S07 Wage Determination with the attached revised S07 Wage Determination

There are no further changes.

Update #2 ·

Accompanying Amendment 36C25222B0034 - 0001

Accompanying Amendment 36C25222B0034 - 0001

Upgrade Eagle & Freight Elevators

William S. Middleton VA Hospital, Madison, WI

I. bid opening information:

a. VIRTUAL BID OPENING INFORMATION:

1) Reminder, there will be no in-person public bid opening process this will be conducted as a public virtual activity.

2) The virtual bid opening will be available to the public via Microsoft Teams at the following link and/or phone number;

Click here to join the meeting

(Meeting will be available to be accessed 15 min prior to bid opening)

Meeting phone number: 872-701-0185

Phone Conference ID: 543269745#

3) IAW FAR 52.214-5 Submission of Bids and 14.202-8 Electronic Bids; Bids shall be provided via email to the Contracting Officer at john.meyers2@va.gov as follows;

Vendor bids are due via email as shown above at 12:00 PM local time on 9/29/2022.

The virtual public bid opening will be held at 1:00 PM local time on 9/29/2022 at the link and/or the phone # provided above.

A hard copy submission is not required. Any bids received after the date and time specified for receipt of bids will be processed in accordance with FAR 52.214-7 Late Submissions, Modifications, and Withdrawals of Bids (Nov 1999).

4) Ensure your complete bid including bid bond are provided in your submission. The successful low bidder is required to furnish their original bid bond within five (5) days after notification by the Contracting Officer.

5) It is highly recommended that Bidders submit their bid at least one hour prior to bid opening to avoid any transmission issues.

II. The following change(s) are to be made to the solicitation:

Specification section 14 21 10, paragraph 1.9 Removal of Materials and Equipment on page 14 21 10-7 is hereby amended to add paragraph C. as follows;

C. Within 150 days from contract award: The Contractor shall decommission and remove the two SPS Dumbwaiters and all dumbwaiter equipment on all floor levels. Contractor shall remove all dumbwaiter supervisory panel, microprocessor control systems, controls cabinets and support stands; remove drive motors, including all steel beam support structures, hoist ropes and traveling cables; remove dumbwaiter car and car frame members, steel car guides and rails in the shaft, steel supports, fastenings, shaft way sensors, switches, call & send operations and corridor operating stations; remove all wiring and raceways (control & power) from within the dumbwaiter shaft to all call buttons, controls and landing lights, position indicators on all floor levels; remove all electrical (conductors, wireways and conduits) back to disconnect switches and j-boxes; remove the above ceiling high/low volt wiring, connections, signal device and transformers from the dumbwaiter controls to the adjacent corridor.

Contractor shall install stainless steel cover plates over removed call button & landing light indictor wall boxes. All items disconnected and removed shall be disposed of offsite by the Contractor.

Final removal of dumbwaiter cars and equipment shall be in Room B 48. All work in this room shall be performed within a dust proof containment and a HEPA Vac air scrubber.

One landing access door on each level to be padlocked closed. The other to remain secured from operation from inside the hoist way by overriding the door safety interlock or other approved method. Contractor shall provide heavy duty contractor grade hasp and keyed padlock to lock and secure one door on each floor level. Padlocks shall be keyed alike.

Contractor shall follow VA Risk Assessment and OSHA safety policies, standard safe work practices, and take such safety precautions as the VA Safety Engineer or his/her designee may deem prudent.

III. general information:

Pre-Bid/Site Visit attendance attached

There are no further changes.

Update #1 ·

.

Files

File Type Posted
S06 - Spec Section 251300 - Integration.pdf PDF
S06 - SF 1442.pdf PDF
36C25222B0034 0003.docx DOCX document
P07 - Wage Determination Revised.pdf PDF
36C25222B0034 0002.docx DOCX document
S04 - Pre-Bid Sign in Sheet.pdf PDF
36C25222B0034 0001.docx DOCX document
S02 - Volume 2 Drawings.pdf PDF
S02 - Volume 1 Drawings.pdf PDF
S02 - Volume 1 Specifications.pdf PDF
P07 - Wage Determination.pdf PDF
36C25222B0034_1.docx DOCX document
S02 - Volume 2 Specifications.pdf PDF
Show all 13

Notice history

Notice Type Posted
Z1DA--607-21-155 upgrade eagle and freight elevators (VA-23-00006591) Award Award Notice
This notice Latest solicitation Solicitation
Z1DA--607-21-155 upgrade eagle and freight elevators (VA-23-00006591) Original Pre-Solicitation

Similar open opportunities

Opportunity Agency Set-aside Responses due
J039--561A4-25-500 Elevator Upgrade & Modernization Repairs at VA NJ HCS Lyons Buildings 6 & 53 Department of Veterans Affairs New Jersey Healthcare System Lyons, New Jersey 07939, United States · NAICS 238290 Veterans Integrated Service Network 2 Service-Disabled Veteran-Owned Small Business
Z1DA--Modernize Damen (Bldg. 1) Elevators Construction 537-24-101 Chicago, Illinois 60612, United States · NAICS 238290 Veterans Integrated Service Network 12 Service-Disabled Veteran-Owned Small Business
Expand 111 OR Department 2AS Phase 1 - Construction - Milwaukee, WI - Project:695-501 Milwaukee, Wisconsin 53295, United States · NAICS 236220 VA Technology Acquisition Center Service-Disabled Veteran-Owned Small Business
Z1DA--Project 695-24-107 Replace Boilers 4 and 5 Clement J. Zablocki, VA Medical Center 5000 West National Avenue Milwaukee, WI 53295 United States · NAICS 238220 Veterans Integrated Service Network 12 Service-Disabled Veteran-Owned Small Business
J036--NTX Elevator Inspection | BASE + OPTIONS | 549 | NEED DATE 12. 2026 Department of Veterans Affairs North Texas VA medical centers Dallas, Texas 76218, United States · NAICS 541350 Veterans Integrated Service Network 17 Service-Disabled Veteran-Owned Small Business

On GovTribe

Work this opportunity

  • Track it in your pipeline
  • Find teaming partners
  • Similar opportunities
  • Ask GovTribe AI about this opportunity