Y1NE--Repair and upgrade irrigation system
Closed Solicitation Posted
- Solicitation number
- 36C25722Q0961
- Agency
-
Veterans Integrated Service Network 17
Veterans Health Administration, Department of Veterans Affairs
- Responses due
- Set-aside
- No set-aside
Opportunity facts
- NAICS code
- 238220 Plumbing, Heating, and Air-Conditioning Contractors
Notice details come from SAM.gov. Updated .
Notice text
3 versions
Update #3 · Latest ·
SCOPE OF WORK
Thomas E Creek VA Medical Center
Amarillo,TX
Install irrigation controls and connect abandoned irrigation line
SCOPE OF WORK: This project will require providing and installation of 4 each - 2 wire irrigation controllers, and all necessary components to include 2 wire irrigation decoders controlling at total of 22 irrigation zones using existing automatic control valves. Project will include connecting bldg. 29 to existing irrigation main. Project will include wiring in irrigation section at bldg. 9 to existing control box. Project will include installing a total of 9 moisture sensors. 5 to existing control boxes and 4 to contractor provided and installed control boxes.
The Contractor shall provide and install 4 each irrigation controllers. 110V wiring for power to irrigation controllers to be provided by others.
The Contractor shall run new control wire from existing irrigation controller to 1 existing automatic control valve at bldg. 9.
The contractor shall tie in controllers to existing automatic control valves using new control wire per the schedule below.
Building 35, 4 zones with existing automatic control valves
Building 7 and 8, 4 zones with existing automatic control valves
Front of hospital (Parking lot N and building 33) 8 zones with existing automatic control valves
Lawn facing Amarillo Blvd ( Football Field ) 4 zones with existing automatic control valves.
The Contractor shall reconnect bldg. 29 to existing irrigation main. Please see attached irrigation drawings. Irrigation map is for illustration only to the contractor. Contractor to field verify tie in location and size.
The Contractor shall install moisture sensors for the new control boxes.
The Contractor shall field verify all controls and tie ins are functional and correct per mfgs. guidelines and to COR s satisfaction
The Contractor shall restore any and all damaged areas to pre-construction condition.
A pre-bid site walk through is requested.
Period of performance is 45 days from date of award to include lead time for materials.
Contractor and all workers shall wear an approved mask as source control for Covid 19 while inside the facility.
2. TECHNICAL SUPPORT: N/A
3. BADGES: All Contractor personnel are required to wear I.D. badges during the entire time he/she is on Government property. I.D. badges must have an identification picture and shall state the name of the individual and the company he/she represents. The Contractor is to coordinate with the COR to obtain the I.D. badge from the Police Service. The Contractor is to provide a list of names who shall be conducting the service. The Contractor will need a valid Driver s License or Federal ID.
4. REPORTING (During Normal Working Hours): The Contractor's Supervisor shall notify the COR when he/she arrives on station, prior to commencing work during the normal working hours of 8:00 a.m. through 4:30 p.m.
5. REPORTING (During Other than Normal Working Hours): The Contractor is not expected to work outside the Normal Working Hours unless first coordinating with the COR. No additional cost will be allowed for work scheduled outside of the Normal Working Hours.
6. CONTRACTOR S SERVICE REPORT: After all work is completed, the Contractor is required to submit, in writing, a complete report of services rendered, and deliver it to the CO and COR within the Engineering Service. If the COR is not available the Contractor can submit the report the next business day. This report must contain detailed description of the services or repairs performed. The Contractor shall document and report to the COR, any unsafe conditions or signs of misuse or abuse in regards to this equipment. The Service Technician shall document any problems along with their corrections and all performance verification on the field service report. The service report must be legible and signed by the COR.
Information on final report shall identify the following:
Contractor Name
Job Title
Location of job to include Building No. and Floor
Photographs of daily work activities
Daily Contractor, etc. Log-in Sheets
Transportation and Disposal Manifests
Date of service
7. INSURANCE REQUIREMENTS: The Contractor agrees to procure and maintain, while the contract is in effect, Workers Compensation and Employee s Public Liability Insurance in accordance with the laws of the governing state.
Public Liability Insurance: The Contractor shall comply with all applicable Federal and State laws with regard to liability arising or resulting from injury to or death of an employee in performing the work under this contract and shall save and hold the Government harmless against any or all loss, cost, damage, claim expense or liability whatsoever, because of accident or injury to persons or property of others occurring in the performance of this contract.
The Contractor shall be responsible for all damage to property, which may be done by him, or any contractor employee engaged in the performance of this contract.
Before commencing work under this contract, the Contractor shall furnish certification from his insurance company indicating that the coverage outlined in paragraphs (a) and (b) has been obtained and that it may not be changed or canceled without guaranteed thirty (30) days notice to the CO. The CO may waive the requirement if he determines that insurance certifications now on file are acceptable, however, new certifications shall be furnished prior to the expiration date.
GOVERNMENT HOLIDAYS:
Date
Holiday
Friday, December 31Â *
New Year's Day
Monday, January 17
Birthday of Martin Luther King, Jr.
Monday, February 21Â **
Washington s Birthday
Monday, May 30
Memorial Day
Monday, June 20Â *
Juneteenth National Independence Day
Monday, July 04
Independence Day
Monday, September 05
Labor Day
Monday, October 10
Columbus Day
Friday, November 11
Veterans Day
Thursday, November 24
Thanksgiving Day
Monday, December 26Â *
Christmas Day
INVOICE AND PAYMENT:
Payment to be made monthly, in arrears, following satisfactory performance by Contractor s personnel and upon receipt of a properly prepared invoice.Â
Contractor shall be required to invoice through the Tungsten System at http://www.tungsten-network.com/us/en/veterans-affairs/. Additional information regarding Tungsten shall be provided upon award.
The contract shall have current registration in the System for Award Management (SAM) for this solicitation; URL: www.sam.gov.
The invoice MUST be itemized to include the following information. Any information listed below, and not provided on an invoice, will render that invoice incomplete and the invoice will be returned for immediate correction.
Time period being invoiced for.
Description of services performed.
Unit Cost billed.
Extended amount due.
Invoice number, date, and; amount partial or full
Contract and obligation numbers.
10. SERVICE CALLS: Contractor shall provide in the space below, the name, location, and telephone number of the office where service calls are to be placed:
Name: __________________________________________________________
Address: __________________________________________________________
Telephone: __________________________________________________________
Point of Contact: __________________________________________________________
11. MATERIAL AND MATERIAL SAFETY DATA SHEETS (MSDS) and WASTE: The Contractor is responsible for having material data safety sheets (MSDS) available on-site for all chemicals, solvents, cleaners, paints, adhesives, etc. used by the contractor, and for following their precautions. The contractor shall collect, handle, transport, and remove any waste (solid, recyclable, universal, and hazardous) waste as needed and upon completion of the service contract. The contractor shall maintain the work area clean and in a safe manner throughout the duration of this contract. The Contractor shall report all recyclable waste to the COR monthly or upon completion of the contract. The Contractor shall provide any dumpsters to properly collect and dispose of waste generated as a result of the service. All waste generated shall be disposed of per applicable federal, state, and local regulations.
12. SMOKING: Smoking is not permitted within, or around, the AMAVAHCS facilities.
13. PARKING: Contractor vehicle shall have contractor identification and phone number. The Contractor shall coordinate with the COR during the Kick-Off Meeting for contractor vehicle parking. It is the responsibility of the Contractor s personnel to park only in designated parking areas. Parking information is available from the AMAVAHCS Police Service. The AMAVAHCS shall not validate or make reimbursement for parking violations of the Contractor s personnel under any circumstances.
14. PROTECTION FROM DAMAGE: The Contractor shall provide all labor, materials and equipment necessary to protect personnel, furnishings, equipment and buildings from damage; Contractor shall remove and replace movable items if necessary and shall replace or report any item damaged due to work performed under this contract equal to its original construction and finish.
15. EVALUATION FACTORS FOR AWARD: The Government shall award a contract resulting from this solicitation to the responsible Contractor whose offer conforming to the solicitation shall be most advantageous to the Government, price and other factors considered. Award shall be based on the following:
Base Bid. The Government shall evaluate the Contractor s proposal and evaluate the solicitation bid s. The Government reserves the right to award a contract at other than the lowest proposed bid after consideration of all factors.
Experience and Past Performance. The Government shall review the Contractor corporate performance, experience, and accomplishments. The Contractor shall provide three (3) references that the Contractor has provided a similar service. The Government shall also assess the overall experience and past performance of subcontractors and suppliers. The Contractor shall provide a list of subcontractor(s) along with their overall experience and past performance.
Technical Expertise. The Government shall review the Contractor corporate technical expertise. The Contractor shall provide training(s), license(s), and certification(s) allowing the contractor to perform Asbestos Removal.
Bid Options. The Contractor proposal shall be evaluated per the provision at FAR Part 52.217-5 Evaluation of Options (JUL 1990).
VHA Supplemental Contract Requirements for Combatting COVID-19 as shown below is hereby incorporated into the scope of work for the subject contract:
Contractor employees who work in or travel to VHA locations must comply with the following:
Documentation requirements:
If fully vaccinated, contractors shall show proof of vaccination.
NOTE: Acceptable proof of vaccination includes a signed record of immunization from a health care provider or pharmacy, a copy of the COVID-19 Vaccination Record Card (CDC Form MLS-319813_r, published on September 3, 2020), or a copy of medical records documenting the vaccination.
If unvaccinated, contractors shall show negative COVID-19 test results dated within three calendar days prior to desired entry date. Test must be approved by the Food and Drug Administration (FDA) for emergency use or full approval. This includes tests available by a doctor s order or an FDA approved over-the-counter test that includes an affiliated telehealth service.
Documentation cited in this section shall be digitally or physically maintained on each contractor employee while in a VA facility and is subject to inspection prior to entry to VA facilities and after entry for spot inspections by Contracting Officer Representatives (CORs) or other hospital personnel.
Documentation will not be collected by the VA; contractors shall, at all times, adhere to and ensure compliance with federal laws designed to protect contractor employee health information and personally identifiable information.Â
Contractor employees are subject to daily screening for COVID-19 and may be denied entry to VA facilities if they fail to pass screening protocols. As part of the screening process contractors may be asked screening questions found on the COVID-19 Screening Tool. Check regularly for updates.
Contractor employees who work away from VA locations, but who will have direct contact with VA patients shall self-screen utilizing the COVID-19 Screening Tool, in advance, each day that they will have direct patient contact and in accordance with their person or persons who coordinate COVID-19 workplace safety efforts at covered contractor workplaces. Contractors shall, at all times, adhere to and ensure compliance with federal laws designed to protect contractor employee health information and personally identifiable information.Â
Contractor must immediately notify their COR or Contracting Officer if contract performance is jeopardized due to contractor employees being denied entry into VA Facilities.
For indefinite delivery contracts: Contractor agrees to comply with VHA Supplemental Contract Requirements for any task or delivery orders issued prior to this modification when performance has already commenced.
The Contractor hereby releases, waives, and discharges the Government from any and all liabilities (direct or indirect), obligations, claims, appeals, demands and requests for equitable adjustment (absent fraud), administrative or judicial, legal or equitable, arising out of, or related to this modification.  In consideration of this modification, agreed to herein as a complete equitable adjustment of the contactor s proposal arising under or related to the change(s) identified above, the contractor hereby releases the Government from any and all liability under this contract for further adjustment attributed to the contactor s proposal.  All other terms and conditions remain in full force and effect.
There are no other changes to the terms and conditions of this contract as a result of this modification.
Update #2 ·
SCOPE OF WORK
Thomas E Creek VA Medical Center
Amarillo,TX
Install irrigation controls and connect abandoned irrigation line
SCOPE OF WORK: This project will require providing and installation of 4 each - 2 wire irrigation controllers, and all necessary components to include 2 wire irrigation decoders controlling at total of 22 irrigation zones using existing automatic control valves. Project will include connecting bldg. 29 to existing irrigation main. Project will include wiring in irrigation section at bldg. 9 to existing control box. Project will include installing a total of 9 moisture sensors. 5 to existing control boxes and 4 to contractor provided and installed control boxes.
The Contractor shall provide and install 4 each irrigation controllers. 110V wiring for power to irrigation controllers to be provided by others.
The Contractor shall run new control wire from existing irrigation controller to 1 existing automatic control valve at bldg. 9.
The contractor shall tie in controllers to existing automatic control valves using new control wire per the schedule below.
Building 35, 4 zones with existing automatic control valves
Building 7 and 8, 4 zones with existing automatic control valves
Front of hospital (Parking lot N and building 33) 8 zones with existing automatic control valves
Lawn facing Amarillo Blvd ( Football Field ) 4 zones with existing automatic control valves.
The Contractor shall reconnect bldg. 29 to existing irrigation main. Please see attached irrigation drawings. Irrigation map is for illustration only to the contractor. Contractor to field verify tie in location and size.
The Contractor shall install moisture sensors for the new control boxes.
The Contractor shall field verify all controls and tie ins are functional and correct per mfgs. guidelines and to COR s satisfaction
The Contractor shall restore any and all damaged areas to pre-construction condition.
A pre-bid site walk through is requested.
Period of performance is 45 days from date of award to include lead time for materials.
Contractor and all workers shall wear an approved mask as source control for Covid 19 while inside the facility.
2. TECHNICAL SUPPORT: N/A
3. BADGES: All Contractor personnel are required to wear I.D. badges during the entire time he/she is on Government property. I.D. badges must have an identification picture and shall state the name of the individual and the company he/she represents. The Contractor is to coordinate with the COR to obtain the I.D. badge from the Police Service. The Contractor is to provide a list of names who shall be conducting the service. The Contractor will need a valid Driver s License or Federal ID.
4. REPORTING (During Normal Working Hours): The Contractor's Supervisor shall notify the COR when he/she arrives on station, prior to commencing work during the normal working hours of 8:00 a.m. through 4:30 p.m.
5. REPORTING (During Other than Normal Working Hours): The Contractor is not expected to work outside the Normal Working Hours unless first coordinating with the COR. No additional cost will be allowed for work scheduled outside of the Normal Working Hours.
6. CONTRACTOR S SERVICE REPORT: After all work is completed, the Contractor is required to submit, in writing, a complete report of services rendered, and deliver it to the CO and COR within the Engineering Service. If the COR is not available the Contractor can submit the report the next business day. This report must contain detailed description of the services or repairs performed. The Contractor shall document and report to the COR, any unsafe conditions or signs of misuse or abuse in regards to this equipment. The Service Technician shall document any problems along with their corrections and all performance verification on the field service report. The service report must be legible and signed by the COR.
Information on final report shall identify the following:
Contractor Name
Job Title
Location of job to include Building No. and Floor
Photographs of daily work activities
Daily Contractor, etc. Log-in Sheets
Transportation and Disposal Manifests
Date of service
7. INSURANCE REQUIREMENTS: The Contractor agrees to procure and maintain, while the contract is in effect, Workers Compensation and Employee s Public Liability Insurance in accordance with the laws of the governing state.
Public Liability Insurance: The Contractor shall comply with all applicable Federal and State laws with regard to liability arising or resulting from injury to or death of an employee in performing the work under this contract and shall save and hold the Government harmless against any or all loss, cost, damage, claim expense or liability whatsoever, because of accident or injury to persons or property of others occurring in the performance of this contract.
The Contractor shall be responsible for all damage to property, which may be done by him, or any contractor employee engaged in the performance of this contract.
Before commencing work under this contract, the Contractor shall furnish certification from his insurance company indicating that the coverage outlined in paragraphs (a) and (b) has been obtained and that it may not be changed or canceled without guaranteed thirty (30) days notice to the CO. The CO may waive the requirement if he determines that insurance certifications now on file are acceptable, however, new certifications shall be furnished prior to the expiration date.
GOVERNMENT HOLIDAYS:
Date
Holiday
Friday, December 31Â *
New Year's Day
Monday, January 17
Birthday of Martin Luther King, Jr.
Monday, February 21Â **
Washington s Birthday
Monday, May 30
Memorial Day
Monday, June 20Â *
Juneteenth National Independence Day
Monday, July 04
Independence Day
Monday, September 05
Labor Day
Monday, October 10
Columbus Day
Friday, November 11
Veterans Day
Thursday, November 24
Thanksgiving Day
Monday, December 26Â *
Christmas Day
INVOICE AND PAYMENT:
Payment to be made monthly, in arrears, following satisfactory performance by Contractor s personnel and upon receipt of a properly prepared invoice.Â
Contractor shall be required to invoice through the Tungsten System at http://www.tungsten-network.com/us/en/veterans-affairs/. Additional information regarding Tungsten shall be provided upon award.
The contract shall have current registration in the System for Award Management (SAM) for this solicitation; URL: www.sam.gov.
The invoice MUST be itemized to include the following information. Any information listed below, and not provided on an invoice, will render that invoice incomplete and the invoice will be returned for immediate correction.
Time period being invoiced for.
Description of services performed.
Unit Cost billed.
Extended amount due.
Invoice number, date, and; amount partial or full
Contract and obligation numbers.
10. SERVICE CALLS: Contractor shall provide in the space below, the name, location, and telephone number of the office where service calls are to be placed:
Name: __________________________________________________________
Address: __________________________________________________________
Telephone: __________________________________________________________
Point of Contact: __________________________________________________________
11. MATERIAL AND MATERIAL SAFETY DATA SHEETS (MSDS) and WASTE: The Contractor is responsible for having material data safety sheets (MSDS) available on-site for all chemicals, solvents, cleaners, paints, adhesives, etc. used by the contractor, and for following their precautions. The contractor shall collect, handle, transport, and remove any waste (solid, recyclable, universal, and hazardous) waste as needed and upon completion of the service contract. The contractor shall maintain the work area clean and in a safe manner throughout the duration of this contract. The Contractor shall report all recyclable waste to the COR monthly or upon completion of the contract. The Contractor shall provide any dumpsters to properly collect and dispose of waste generated as a result of the service. All waste generated shall be disposed of per applicable federal, state, and local regulations.
12. SMOKING: Smoking is not permitted within, or around, the AMAVAHCS facilities.
13. PARKING: Contractor vehicle shall have contractor identification and phone number. The Contractor shall coordinate with the COR during the Kick-Off Meeting for contractor vehicle parking. It is the responsibility of the Contractor s personnel to park only in designated parking areas. Parking information is available from the AMAVAHCS Police Service. The AMAVAHCS shall not validate or make reimbursement for parking violations of the Contractor s personnel under any circumstances.
14. PROTECTION FROM DAMAGE: The Contractor shall provide all labor, materials and equipment necessary to protect personnel, furnishings, equipment and buildings from damage; Contractor shall remove and replace movable items if necessary and shall replace or report any item damaged due to work performed under this contract equal to its original construction and finish.
15. EVALUATION FACTORS FOR AWARD: The Government shall award a contract resulting from this solicitation to the responsible Contractor whose offer conforming to the solicitation shall be most advantageous to the Government, price and other factors considered. Award shall be based on the following:
Base Bid. The Government shall evaluate the Contractor s proposal and evaluate the solicitation bid s. The Government reserves the right to award a contract at other than the lowest proposed bid after consideration of all factors.
Experience and Past Performance. The Government shall review the Contractor corporate performance, experience, and accomplishments. The Contractor shall provide three (3) references that the Contractor has provided a similar service. The Government shall also assess the overall experience and past performance of subcontractors and suppliers. The Contractor shall provide a list of subcontractor(s) along with their overall experience and past performance.
Technical Expertise. The Government shall review the Contractor corporate technical expertise. The Contractor shall provide training(s), license(s), and certification(s) allowing the contractor to perform Asbestos Removal.
Bid Options. The Contractor proposal shall be evaluated per the provision at FAR Part 52.217-5 Evaluation of Options (JUL 1990).
VHA Supplemental Contract Requirements for Combatting COVID-19 as shown below is hereby incorporated into the scope of work for the subject contract:
Contractor employees who work in or travel to VHA locations must comply with the following:
Documentation requirements:
If fully vaccinated, contractors shall show proof of vaccination.
NOTE: Acceptable proof of vaccination includes a signed record of immunization from a health care provider or pharmacy, a copy of the COVID-19 Vaccination Record Card (CDC Form MLS-319813_r, published on September 3, 2020), or a copy of medical records documenting the vaccination.
If unvaccinated, contractors shall show negative COVID-19 test results dated within three calendar days prior to desired entry date. Test must be approved by the Food and Drug Administration (FDA) for emergency use or full approval. This includes tests available by a doctor s order or an FDA approved over-the-counter test that includes an affiliated telehealth service.
Documentation cited in this section shall be digitally or physically maintained on each contractor employee while in a VA facility and is subject to inspection prior to entry to VA facilities and after entry for spot inspections by Contracting Officer Representatives (CORs) or other hospital personnel.
Documentation will not be collected by the VA; contractors shall, at all times, adhere to and ensure compliance with federal laws designed to protect contractor employee health information and personally identifiable information.Â
Contractor employees are subject to daily screening for COVID-19 and may be denied entry to VA facilities if they fail to pass screening protocols. As part of the screening process contractors may be asked screening questions found on the COVID-19 Screening Tool. Check regularly for updates.
Contractor employees who work away from VA locations, but who will have direct contact with VA patients shall self-screen utilizing the COVID-19 Screening Tool, in advance, each day that they will have direct patient contact and in accordance with their person or persons who coordinate COVID-19 workplace safety efforts at covered contractor workplaces. Contractors shall, at all times, adhere to and ensure compliance with federal laws designed to protect contractor employee health information and personally identifiable information.Â
Contractor must immediately notify their COR or Contracting Officer if contract performance is jeopardized due to contractor employees being denied entry into VA Facilities.
For indefinite delivery contracts: Contractor agrees to comply with VHA Supplemental Contract Requirements for any task or delivery orders issued prior to this modification when performance has already commenced.
The Contractor hereby releases, waives, and discharges the Government from any and all liabilities (direct or indirect), obligations, claims, appeals, demands and requests for equitable adjustment (absent fraud), administrative or judicial, legal or equitable, arising out of, or related to this modification.  In consideration of this modification, agreed to herein as a complete equitable adjustment of the contactor s proposal arising under or related to the change(s) identified above, the contractor hereby releases the Government from any and all liability under this contract for further adjustment attributed to the contactor s proposal.  All other terms and conditions remain in full force and effect.
There are no other changes to the terms and conditions of this contract as a result of this modification.
Update #1 ·
PART I - INSTRUCTIONS, CONDITIONS AND NOTICES TO OFFERORS
PART I/SECTION A REQUEST FOR QUOTE
This is a Request for Quote in accordance with FAR Part 13. Potential offerors must follow all instructions in order to be compliant with the solicitation.
It is the responsibility of the offeror to verify that their offer is complete. The offeror is responsible for submitting all required forms and documents with the offer.
The Government will award a single contract resulting from this solicitation to a responsible SDVOSB offeror whose offer conforming to the solicitation will be most advantageous to the Government based on Past Performance and Price.
I.1A JOINT VENTURES
If submitting an offer as a joint venture as defined by P.L. 109-461 AND Department of Veterans Affairs I.L. 049-06-4, http://www.vetbiz.gov/library/jtventure.pdf , an offeror must provide a copy of the joint venture agreement specific to the project that is consistent with the percentage of required work and net proceed. Additionally, the offeror must provide a breakdown or labor of which is to be performed by the SDVOSB firm and that which is performed by the small business joint venture firm and that which is sub-contracted. All Joint Ventures will be required to be registered and verified as an entity in VETBIZ.
I.2A SELECTION CRITERIA/QUOTE PREPARATION INSTRUCTIONS
Quotes will be evaluated in accordance with FAR 13.106 Simplified Acquisition Procedures
Award will be made based on the following factors:
Factor 1 Past Performance
Factor 2-- Price
Offerors are encouraged to provide their best offers with the past performance information requested for evaluation. The Government, based on the offered material presented, will award to the offeror that best demonstrates to be most advantageous for the Government.
Factor 1 - Past Performance: Offerors shall provide past performance information on two (2) federal, state, local government or private contract of similar type, scope, size and complexity. If a completed Contractor Performance Assessment Reporting System (CPARS) evaluation is available, it shall be submitted with the quote. The Government may also evaluate recent and relevant past performance, based upon sources available to the contracting officer that may include Past Performance Information Retrieval System (PPIRS), Federal Awardee Performance and Integrity Information System (FAPIIS) and Electronic Subcontract Reporting System (eSRS). IF THE OFFEROR CANNOT PROVIDE A CPARS FOR PROJECTS LISTED IN FACTOR 1, then the offeror shall submit Past Performance Questionnaires (PPQ).
If you have any questions, please contact Dustin Bartholomew at Dustin.Bartholomew@va.gov. Completed PPQs should be submitted directly from your client via email to Dustin.Bartholomew@va.gov. If the offeror is unable to contact a client for a project(s) before closing date, the offeror should complete and submit with the quote and the first page of the PPQ, which will provide contract and client information for the respective project(s). Offerors should follow-up with clients/references to ensure timely submittal of questionnaires.
Basis of Evaluation: Past Performance will be evaluated in accordance with FAR 13.106-2 and award will be made to the offeror presenting the best value to the Government.
Factor 2 - Price: Offerors shall provide pricing as requested in the Schedule of Service identified within the SF1442
The Government will award a contract resulting from this solicitation to the responsible offeror whose offer conforming to the solicitation will be most advantageous to the Government, price and other factors considered.
SAFETY Special Standards of Responsibility
(a) Solicitation Submittal Requirements:
The Offeror shall submit the following information: (For a partnership or joint venture, the following submittal requirements are required for each Contractor who is part of the partnership or joint venture and for the entity itself. EMR shall not be submitted for subcontractors.)
OSHA or EPA Violation(s):
Offerors shall provide Summary of Work-Related Injuries and Illnesses, affirming that the
Offeror has no more than three serious, or one repeat, or one willful OSHA or EPA violation(s) in the past 3 years
(2) Experience Modification Rate (EMR):
Offerors shall provide documentation to show that the offeror has an Experience Modification Rate (EMR) of equal to or less than 1.0.
PART I/SECTION B - INSTRUCTIONS, CONDITIONS AND NOTICES TO OFFERORS
I.1B COST RANGE: Less than $25,000. REQUESTS FOR INFORMATION:
All requests for information must be submitted in writing to the Contracting Officer for action no later than the date shown in Block 10 of the Standard Form 1442, Solicitation, Offer and Award.
I.3B QUOTE REQUIREMENTS
52.219-14Â Limitations on Subcontracting
(e) Limitations on subcontracting. By submission of an offer and execution of a contract, the Contractor agrees that in performance of a contract assigned a North American Industry Classification System (NAICS) code for
(3)General construction, it will not pay more than 85 percent of the amount paid by the Government for contract performance, excluding the cost of materials, to subcontractors that are not similarly situated entities. Any work that a similarly situated entity further subcontracts will count towards the prime contractor's 85 percent subcontract amount that cannot be exceeded; or
(4)Construction by special trade contractors, it will not pay more than 75 percent of the amount paid by the Government for contract performance, excluding the cost of materials, to subcontractors that are not similarly situated entities. Any work that a similarly situated entity further subcontracts will count towards the prime contractor's 75 percent subcontract amount that cannot be exceeded.
General Quotes shall be submitted in response to this solicitation. Quotes shall be submitted via email to Dustin.Bartholomew@va.gov. Emails are limited to five (5) MB. The quote, in its entirety, shall not exceed two emails (one email for price, and one email for technical/past performance) of 5MB each. Price shall be in a separate electronic document from the technical and past performance portions of the quote. Failures to submit in the format required and clearly address those factors may result in rejection of the offer. Further details on electronic submission are outlined below. Offerors shall include all required Representations and Certifications and complete their registration in System for Award Management (SAM). See FAR 52.204-7 and 52.204-8, of this solicitation.
Quotes shall be received by 2:00 PM Central Standard Time on September 16th, 2022. There will be no public opening. Submit quotes to: Dustin.Bartholomew@va.gov.
Files
| File | Type | Posted |
|---|---|---|
| 36C25722Q0961 0002.docx | DOCX document | |
| 36C25722Q0961 0001.docx | DOCX document | |
| 36C25722Q0961.docx | DOCX document |
Notice history
| Notice | Type | Posted |
|---|---|---|
| This notice | Solicitation | |
| Y1NE--Repair and upgrade irrigation system | Pre-Solicitation |
On GovTribe
Work this opportunity
- Track it in your pipeline
- Find teaming partners
- Similar opportunities
- Ask GovTribe AI about this opportunity