About this opportunity

The U.S. Army Corps of Engineers, Huntington Engineering District intends to solicit roller gate fabrication services for the Winfield Lock and Dam in Red House, West Virginia, and is requesting industry input by August 24, 2026 through a Request for Information notice.

The RFI seeks contractor feedback on fabrication methodology and design alternatives to inform the eventual solicitation. Questions target critical cost and schedule drivers: submerged arc welding applicability for skin plate splices, economies of scale across one to three gates, labor savings from eliminating grinding on non-intersecting welds, 100% radiographic testing logistics and production rates, and comparative efficiency of multi-piece designs with transverse splices (welded or bolted). The government also solicits input on bolted end shields and aprons, slip-critical versus welded connections, and assembly location preferences (shop final assembly versus field completion). Contractors are asked whether the contract structure—construction contractor working under a prime versus standalone supply-fabrication—affects bid likelihood, and what risk mitigation steps USACE should consider.

Technical drawings (sheets S-501 through S-507) are attached and cover structural design, material specifications, and installation procedures. NAICS 332312 (Fabricated Structural Metal Manufacturing) and PSC 9640 (Iron and Steel Primary and Semifinished Products) apply. No set-aside is anticipated. Place of performance is Red House, West Virginia.

Notice text

This Request For Information Notice is intended to garner industry input for questions regarding Roller Gate Fabrication for the Winfiled Lock and Dam Located in Red House, West Virgina. 

Interested Contractors are encouraged to reply to the following questions after reviewing the Attached Technical Drawings:

     1. Can the skin plate splices be performed using submerged arc welding?

     2. Economies of scale: Are there significant efficiencies related to fabrication of 1 gate v 2 gates v 3 gates, etc.

     3. Not grinding skin plate welds—What is the time and labor savings? Would not staggering skin plate splices increase efficiency/benefit fabrication? Note that splice welds would still be required to be ground flush at the intersections of longitudinal and transverse splice welds a minimum of 4” in all directions.     

     4. What factors do you consider when doing 100% RT on this quantity of welds? Shutting down shop? How is this cost factored in? What is the production rate? Cost per test?

     5. Would a design featuring multiple pieces (2-4) with transverse gate splice(s) benefit fabrication? Would you prefer this splice be welded or bolted using slip critical bolted connection. Note that full assembly would be required at the shop prior to shipment for a full shop fit assembly.

     6. Would a design featuring bolted on end shields and/or apron benefit fabrication/increase efficiency?

     7. Would you be more or less likely to bid if this was a Construction Contractor (i.e. working with a prime contractor to install) vs a supply fabrication contract.

     8. What can USACE do to reduce risk/contingency in bidding a project like this?

     9. Are there connections that would be more cost efficient bolted instead of welded? Would it be more cost efficient to weld, or use slip critical bolts to connect splices on the skin plate(longitudinal and transverse)?

     10. Are there a fabrication cost difference between bearing type and slip-critical bolted connections.

     11. If final assembly of the gates is allowed in the field during installation, is this something that would be a benefit for fabrication/increase efficiency?

Files

File Type Posted
Drawings.pdf PDF

Similar open opportunities

Opportunity Agency Set-aside Responses due
Winfield Locks and Dam Major Rehab Industry Day Red House, West Virginia 25168, United States ENDIST Huntington No set-aside
Sources Sought for Calcaiseu River Saltwater Barrier FRP Tainter Gate NAICS 326199 ENDIST New Orleans No set-aside

On GovTribe

Work this opportunity

  • Track it in your pipeline
  • Find teaming partners
  • Similar opportunities
  • Ask GovTribe AI about this opportunity