Village Power Communication Line Re-Routing

Closed Pre-Solicitation Posted

Solicitation number
FA568226QA003
Agency
Responses due
Set-aside
No set-aside

Opportunity facts

NAICS code
Not on record
PSC
Not on record
Place of performance
Campia Turzii Cluj 40510 Romania

Notice details come from SAM.gov. Updated .

About this opportunity

The Department of the Air Force United States Air Forces in Europe - Air Forces Africa is seeking contractor services to re-route the Village's power and communication distribution infrastructure from an above-ground cable tray system to an underground conduit network. The primary objective is to improve reliability, safety, and long-term maintainability while enabling future expansion of the infrastructure. Key requirements include excavating a 14-meter trench, installing four O110 mm PVC conduits in compliance with NEC, IEEE, IEC 60364-552, and applicable Romanian underground cable installation standards, and providing all labor, materials, equipment, and supervision necessary to complete the project. The contractor must demonstrate the ability to execute the work within a 14 working-day performance period and provide daily progress reports, as-built documentation, and a 12-month warranty on all workmanship and materials. The Pre-solicitation Notice was posted on April 8, 2026, with a deadline for responses or questions on April 17, 2026.

This is a non-set-aside procurement with no identified incumbent or current contractor mentioned in the opportunity documents. The contract specifications require precise technical execution, including trench dimensions with a finished depth of 90 centimeters and minimum width of 75 centimeters, installation of conduits with specific spacing requirements (5-7.5 centimeters between conduits), and proper bedding, backfill, and surface restoration to match existing conditions. The contractor must furnish all equipment, tools, vehicles, personal protective equipment, surveying equipment, and waste disposal services at their own cost. No specific dollar amount or budget range is disclosed in the pre-solicitation notice, though the scope of work is clearly defined with detailed technical requirements to guide contractor proposals and cost estimates during the formal solicitation phase.

Notice text

2 versions

Update #2 · Latest ·

Performance Work Statement: Village Power Communication Line Re‑Routing

1.0 Purpose and Background

The Village’s existing power and communication distribution network is currently routed above ground on a concrete pad using exposed cable trays. This configuration increases vulnerability to weather, physical damage, and operational disruptions. The purpose of this project is to relocate and reorganize the electrical and communication infrastructure into an underground conduit system to improve reliability, safety, and long‑term maintainability while enabling future expansion.

2.0 Scope of Work

The Contractor shall provide all labor, materials, equipment, and supervision required to install four, Ø110 mm underground PVC conduits for the Village’s power and communication lines, rerouting them from the existing concrete pad cable tray system into a new underground conduit network. Work includes:

  • Excavate a trench 14 meters in length with a finished depth of 80–90 cm and a minimum finished width of 45 cm, in full compliance with IEC 60364‑5‑52 and applicable Romanian underground cable installation standards.
  • Installing four, appropriately sized, Ø110 mm underground PVC conduits, for the Village’s power and communication lines conduits for electrical and communication lines.
  • Ensuring all conduits are left empty, capped at both ends, and not filled, sealed, or obstructed with foam or any other material.
  • All work must comply with NEC, IEEE, local utility standards, and site‑specific requirements.
  • Carry out compaction testing, depth verification, and documentation to demonstrate compliance.
  • Provide daily update emails on the progress of work detailing what had been accomplished that day

3.0 Requirements

    1. Excavation of Future Underground Conduit Locations

The contractor shall excavate a trench 14 meters in length with a finished depth of 90 cm and a minimum finished width of 75 cm, in full compliance with IEC 60364‑5‑52 and applicable Romanian underground cable installation standards.

3.1.1 Removal and disposal of previous conduit lines.

The contractor shall remove leftover conduit lines and dispose of any plastics or PVC from previous works.

3.2 Installation of Conduit lines

The contractor shall:

  • Provide a 10 cm 0/4mm clean masonry sand bedding layer at the bottom of the trench prior to conduit installation.
  • Use underground‑rated conduits, materials, and accessories suitable for permanent subsurface installation.
  • Install four (4) Ø110 mm PVC conduits along the full trench length in a 1×4 configuration, maintaining a minimum spacing of 5-7.5 cm between conduits horizontally and vertically, and ensure each conduit terminates 92 cm above finished ground level with a clean 90‑degree sweep, are properly capped, and remain free of obstructions. The use of foam, sealant, or any filler inside spare conduits is strictly prohibited.
  • Provide a draw-string in each conduit to facilitate future cable installation.
  • Maintain all required horizontal and vertical clearances from existing utilities. The Contractor is solely responsible for utility locating, verification, and avoidance.
    1. Trench Backfilling

The contractor shall:

  • After conduit placement, backfill with 21 cm of 0/4mm clean masonry sand to cover the exposed conduits. This will lead to a total sand layer of 31 cm due to the bedding layer and additional backfill.
  • Install warning tape 30cm above conduit crown.
  • After sand layer, the trench will be backfilled with 37mm of 0/32mm well-graded crushed aggregate.
    1. Concrete Capping

The contractor shall:

  • Restore the surface with a 22 cm concrete slab matching the adjacent concrete thickness, strength, finish and appearance.
  • The repaired section will be flush with surrounding surfaces with no visible differential in texture, color, or elevation.
    1. Additional Requirements

The contractor must:

  • Implement all necessary site protection, erosion control, and restoration measures throughout the work.

    • This includes wearing protective helmets, gloves, knee pads, and respiratory masks to protect from cuts, inhaling concrete dust, and any other potential bodily injury
  • Maintain daily progress logs and submit daily work reports inPDF format to the Contracting Officer and the Project Manager.
  • Clean any the surriounding area of leftover materials, dust, and debris.
  • Fill hole located by the designated red circle on figure 2. This should be done manually with shovels and at the end of the project to ensure there is no damage done to the concrete foundation and the structures surrounding it.
  • Execute work from 9AM to 5PM.
  • Not pour concrete when storms are suspected during the curing time of the concrete.

4.0 Deliverables

The Contractor shall deliver:

• Underground routing plan and construction drawings.

• Material submittals and technical data sheets.

• As‑built drawings showing conduit paths, depths, and cable identification.

5.0 Period of Performance

The period of performance is 14 working days from Notice to Proceed (NTP). A detailed schedule with milestones shall be submitted within 10 days upon award.

6.0 Place of Performance

All work will occur within the Village boundaries at the existing concrete pad cable tray locations and along the approved underground routing corridors.

7.0 USG & RoAF Assistance

The U.S. Government and Romanian Air Force may provide:

• Access to controlled areas and work zones.

• Coordination with local authorities and utility providers.

• Review and approval of submittals and design documents.

• Oversight and quality assurance inspections.

• No tools, materials, or labor will be provided by RoAF or USAF unless specifically stated.

8.0 Contractor‑Furnished Equipment/Information

The Contractor shall provide:

• All tools, equipment, vehicles, and machinery required for trenching and conduit installation.

• All conduits.

• PPE for all personnel.

• Surveying and testing equipment.

• Waste disposal and site restoration materials.

9.0 Acceptance Criteria

Work will be accepted when:

• All installations meet NEC, IEEE, and project specifications.

• Conduits are verified to contain draw strings and to be capped and unobstructed.

• As‑built documentation is complete and accurate.

• The site is restored to its original or improved condition.

• All deficiencies identified during inspections are corrected.

• A final inspection must be completed and documented prior to project closeout.

10.0 Security Requirements

The Contractor shall:

• Comply with all USG and RoAF security protocols. Base access requests must be submitted at least 7 days in advance.

• Ensure personnel have proper identification and authorization.

• Protect sensitive infrastructure information.

• Follow controlled‑area procedures where applicable.

11.0 Safety

The Contractor shall implement a comprehensive safety plan that includes:

• OSHA‑compliant work practices.

• Daily safety briefings and hazard assessments.

• Proper trenching and shoring.

• Immediate reporting of accidents or near‑miss incidents.

12.0 Warranty

The Contractor shall provide a minimum 12‑month warranty on all workmanship and installed materials, starting from the date of final acceptance. All defects identified during the warranty period shall be corrected at no additional cost.

13.0 Appendix

The Appendix may include:

• Site maps and routing diagrams

• Material specifications

• Safety plan

• Environmental protection plan

• Quality control plan

Update #1 ·

Performance Work Statement: Village Power Communication Line Re‑Routing

1.0 Purpose and Background

The Village’s existing power and communication distribution network is currently routed above ground on a concrete pad using exposed cable trays. This configuration increases vulnerability to weather, physical damage, and operational disruptions. The purpose of this project is to relocate and reorganize the electrical and communication infrastructure into an underground conduit system to improve reliability, safety, and long‑term maintainability while enabling future expansion.

2.0 Scope of Work

The Contractor shall provide all labor, materials, equipment, and supervision required to install four, Ø110 mm underground PVC conduits for the Village’s power and communication lines, rerouting them from the existing concrete pad cable tray system into a new underground conduit network. Work includes:

• Installing appropriately sized conduits for electrical and communication lines.

• Ensuring all conduits are left empty, capped at both ends, and not filled, sealed, or obstructed with foam or any other material.

• All work must comply with NEC, IEEE, local utility standards, and site‑specific requirements.

3.0 Requirements

The Contractor shall perform the following work:

  • Use underground‑rated conduits, materials, and accessories suitable for permanent subsurface installation.
  • Excavate a trench 14 meters in length with a finished depth of 80–90 cm and a minimum finished width of 45 cm, in full compliance with IEC 60364‑5‑52 and applicable Romanian underground cable installation standards.
  • Provide a 10 cm sand bedding layer at the bottom of the trench prior to conduit installation.
  • Install four (4) Ø110 mm PVC conduits along the full trench length in a 2×2 configuration, maintaining a minimum spacing of 5 cm between conduits horizontally and vertically, and ensure each conduit terminates 92 cm above finished ground level with a clean 90‑degree sweep, are properly capped, and remain free of obstructions. The use of foam, sealant, or any filler inside spare conduits is strictly prohibited.
  • Provide a draw string in each conduit to facilitate future cable installation.
  • Maintain all required horizontal and vertical clearances from existing utilities. The Contractor is solely responsible for utility locating, verification, and avoidance.
  • After conduit placement, install 10 cm of sand cover above the conduits, resulting in a total sand thickness of 20 cm.
  • Install warning tape at the standard depth above the sand layer.
  • Backfill with well-graded soil after sand cover and cap with concrete equivalent to the height of the rest of the concrete pad.
  • Implement all necessary site protection, erosion control, and restoration measures throughout the work.
  • Maintain daily progress logs and submit daily work reports inPDF format.

4.0 Deliverables

The Contractor shall deliver:

• Underground routing plan and construction drawings.

• Material submittals and technical data sheets.

• As‑built drawings showing conduit paths, depths, and cable identification.

5.0 Period of Performance

The period of performance is 14 working days from Notice to Proceed (NTP). A detailed schedule with milestones shall be submitted within 10 days upon award.

6.0 Place of Performance

All work will occur within the Village boundaries at the existing concrete pad cable tray locations and along the approved underground routing corridors.

7.0 USG & RoAF Assistance

The U.S. Government and Romanian Air Force may provide:

• Access to controlled areas and work zones.

• Coordination with local authorities and utility providers.

• Review and approval of submittals and design documents.

• Oversight and quality assurance inspections.

• No tools, materials, or labor will be provided by RoAF or USAF unless specifically stated.

8.0 Contractor‑Furnished Equipment/Information

The Contractor shall provide:

• All tools, equipment, vehicles, and machinery required for trenching and conduit installation.

• All conduits.

• PPE for all personnel.

• Surveying and testing equipment.

• Waste disposal and site restoration materials.

9.0 Acceptance Criteria

Work will be accepted when:

• All installations meet NEC, IEEE, and project specifications.

• Conduits are verified to contain draw strings and to be capped and unobstructed.

• As‑built documentation is complete and accurate.

• The site is restored to its original or improved condition.

• All deficiencies identified during inspections are corrected.

• A final inspection must be completed and documented prior to project closeout.

10.0 Security Requirements

The Contractor shall:

• Comply with all USG and RoAF security protocols. Base access requests must be submitted at least 7 days in advance.

• Ensure personnel have proper identification and authorization.

• Protect sensitive infrastructure information.

• Follow controlled‑area procedures where applicable.

11.0 Safety

The Contractor shall implement a comprehensive safety plan that includes:

• OSHA‑compliant work practices.

• Daily safety briefings and hazard assessments.

• Proper trenching and shoring.

• Immediate reporting of accidents or near‑miss incidents.

12.0 Warranty

The Contractor shall provide a minimum 12‑month warranty on all workmanship and installed materials, starting from the date of final acceptance. All defects identified during the warranty period shall be corrected at no additional cost.

Files

File Type Posted
Village Power Communication Line ReRouting SOW V2.docx DOCX document
Village Power Communication Line ReRouting SOW.docx DOCX document

Similar open opportunities

Opportunity Agency Set-aside Responses due
Pre-Solicitation Notice - Trenching, Conduit and Ground-well Installation Saint Andrew Saint Andrew Jamaica · NAICS 238910 Department of State No set-aside

On GovTribe

Work this opportunity

  • Track it in your pipeline
  • Find teaming partners
  • Similar opportunities
  • Ask GovTribe AI about this opportunity