About this opportunity

The Defense Logistics Agency Land and Maritime seeks procurement of safety relief valves, with proposals due November 16, 2026. The procurement is a total small business set-aside under DEV 2026-O0037.

Place of performance and delivery timeline are not specified in the solicitation notice. The NAICS code is 332919, Other Metal Valve and Pipe Fitting Manufacturing; PSC is 4820, Valves, Nonpowered. The procurement requires ISO 9001 certification and higher-level inspection per fixed-price inspection requirements. Contractor must comply with Buy American–Free Trade Agreements–Balance of Payments Program provisions and security prohibitions under CLASS DEVIATION 2026-O0025. Mandatory use of Workflow Pro (WFP) MOD ASSIST Module applies. Award evaluation uses Lowest Price Technically Acceptable (LPTA) criteria per clause WSSTERMMZ04. All contractual documents are considered issued when deposited in mail, transmitted by facsimile, or sent by electronic commerce methods including email; the government's acceptance of the contractor's proposal constitutes bilateral agreement on this issuing method.

Notice text

ITEM UNIQUE IDENTIFICATION AND VALUATION (JAN 2023)|19||||||||||||||||||||

HIGHER-LEVEL CONTRACT QUALITY REQUIREMENT (DEC 2014)|1|ISO 9001|

INSPECTION OF SUPPLIES--FIXED-PRICE (AUG 1996)|2|||

INSPECTION AND ACCEPTANCE - SHORT VERSION|8|x||x||||||

WIDE AREA WORKFLOW PAYMENT INSTRUCTIONS (JAN 2023)|16|Invoice and Receiving Report Combo||TBD|SPRMM1|TBD|TBD|TBD|TBD|||TBD|||||TBD|

MANDATORY USE OF WORKFLOW PRO (WFP) MOD ASSIST MODULE|1||

BUY AMERICAN-FREE TRADE AGREEMENTS-BALANCE OF PAYMENTS PROGRAM-BASIC (FEB 2024)|11||||||||||||

NOTICE OF TOTAL SMALL BUSINESS SET-ASIDE (DEV 2026-O0037)(FEB 2026)|1||

SECURITY PROHIBITIONS AND EXCLUSIONS (CLASS DEVIATION 2026-O0025)(FEB 2026)|7||||||||

SMALL BUSINESS PROGRAM REPRESENTATIONS (DEV 2026-O0037)(FEB 2026)|20|332919|750|||||||||||||||||||

ALTERNATE A, ANNUAL REPRESENTATIONS AND CERTIFICATIONS (DEVIATION 2026-O0043)(FEB 2026))|13|x|x|x|||x||||||||

NOTICE OF PRIORITY RATING FOR NATIONAL DEFENSE, EMERGENCY PERPARDENESS, AND ENRGY PROGAM USE (APRIL 2008))|2||x|

Award evaluations will be made using the Lowest Price Technically Acceptable (LPTA) criteria per clause WSSTERMMZ04 - Evaluation for Award (Lowest PricedTechnically Acceptable).

This procurement requires Higher Level Inspection.

1. All contractual documents (i.e. contracts, purchase orders, task orders,

Delivery orders, and modifications) related to the instant procurement are

considered to be "issued" by the government when copies are either deposited

in the mail, transmitted by facsimile, or sent by other electronic commerce

methods, such as email. The government's acceptance of the contractor's

proposal constitutes bilateral agreement to "issue" contractual documents as

detailed herein.

2. Drawings or technical data are/are not available for this item.

(Ifdrawings are available, include remark under "For Drawings")3. Delivery days_________aro.

4. Offer valid for _____ days.

5. When submitting quotes via Electronic Data Interchange (EDI), make sure

you specify any exceptions (i.e. Mil specs/standards, packaging, Inspection

& Acceptance (I&A), packaging houses etc) or follow up with a hardcopy of

the exceptions. If nothing is indicated or received, award will be based

upon solicitation requirements. Changes or requests for changes after

award will have consideration costs deducted on modifications.

6. If you are not the manufacturer of the material you are offering, you MUST

State who the Original Equipment Manufacturer (OEM) is Commercial and

Government Entity Code (CAGE) code and the part number you are offering.

IF PROPOSING AS A DISTRIBUTOR OR DEALER TO THE OEM, PLEASE TAKE NOTE TO THE

TRACEABILITY REQUIREMENTS CITED IN CLAUSES DLATERMHZ01 IN THE SOLICITATION.

REFURBISHED MATERIAL IS NOT ACCEPTABLE.

7. Please provide an email address for follow up communications.

____________________________________________________________

8. It is recommended that vendors provide contact information to NAVSUP Weapon

System Support (WSS) Mechanicsburg in order to receive automated notifications

from Navy Electronic Commerce Online (NECO) when contracts/modifications

are issued by Defense Logistics Agency (DLA) Weapons Support Mechanicsburg

and posted on Procurement Integrated Enterprise Environment (PIEE)

Electronic Data Access (EDA). To receive these notifications, contact:

NAVSUPWSS code 025, procurement systems design and contract support division

Via email at NAVSUPWSSITIMPHelpdesk@navy.mil. Please include the following

information with your request: CAGE code, company name, address and

Point-of-Contact (POC) with phone number and email address.

9. Contractors can view their orders, contracts and modifications at the

EDA web tool. This web tool is located at the PIEE website. It is

recommended that the contractor register for EDA at https://piee.eb.mil/.

Click on new user and registration.

Any order resulting from this Request for Quotation will require electronic

submittal of Invoice and Receiving Report through PIEE-WAWF.

10. The following DLA Procurement Notes are applicable to this requirement:

E06 Inspection and Acceptance at Source (JUN 2018)

11. INSPECTION OF MATERIAL WILL BE AT (CAGE & ADDRESS):

______________________________________________________________

INSPECTION OF PACKAGING AND FINAL ACCEPTANCE OF MATERIAL WILL BE AT (CAGE &

ADDRESS):

______________________________________________________________

12. UCF SECTION F PRODUCTION FACILITY CHANGES

(a) The performance of any of the work contracted for in any place other than

that named in the contract is prohibited unless specifically approved by the

Contracting Officer. Written requests for a change in production facilities

must be submitted in writing to the Contracting Officer. Changes in

production facilities may be approved, provided:

(1) Performance by small business or in labor surplus areas as required by

the contract will not be changed;

(2) The change will not cause a delay in delivery or necessitate a change in

the purchase description;

(3) The free on board (f.o.b.) point is not changed; and

(4) Each request is supported by a price reduction of $250.00 to cover the

Government's administrative costs to process the change.

(b) The Government reserves the right to deny approval even if these four

elements are met.

\

1. SCOPE

1.1 This contract/purchase order contains the requirements for manufacture and the contract quality requirements for the VALVE,SAFETY RELIEF , part of the ;MK-91 MOD-3 (GMFCS) NATO; .

2. APPLICABLE DOCUMENTS

2.1 Applicable Documents - The document(s) listed below form a part of this contract/purchase order including modifications or exclusions.

2.1.1 Documents, drawings, and publications supplied are listed under "Drawing Number". These items should be retained until an award is made.

2.1.2 "Document References" listed below must be obtained by the Contractor. Ordering information is included as an attachment to this contract/purchase order.

2.1.3 The "Document Changes" section provides supersessions/changes to referenced documents.

2.2 Order of Precedence - In the event of a conflict between the text of this contract/purchase order and the references and/or drawings cited herein, the text of this contract/purchase order shall take precedence. Nothing in this contract/purchase order,

however, shall supersede applicable laws and regulations unless a specific exemption has been obtained.

DRAWING DATA=2080073 |10001| B| |D|0001 | B|49998|0076931

DRAWING DATA=2080075 |10001| B| |D|0001 | B|49998|0090312

DRAWING DATA=2080076 |10001| B| |D|0001 | B|49998|0071424

DRAWING DATA=2468746 |10001| C| |D|0001 | C|49998|0037851

DRAWING DATA=2468746 |10001| C| |D|0002 | C|49998|0033878

DRAWING DATA=2468746 |10001| C| |D|0003 | C|49998|0029327

DRAWING DATA=2468746 |10001| C| |D|0004 | C|49998|0016497

DRAWING DATA=2888335 |10001| B| |D|0001 | B|49998|0073910

DRAWING DATA=2888335 |10001| B|PL |D|0001 | B|49998|0025126

DRAWING DATA=2888337 |10001| H| |F|0001 | H|49998|0086894

DRAWING DATA=2888338 |10001| D| |D|0001 | D|49998|0090955

DRAWING DATA=2888339 |10001| B| |D|0001 | B|49998|0077327

DRAWING DATA=2888343 |10001| B| |D|0001 | B|49998|0077923

DRAWING DATA=2888350 |10001| D| |D|0001 | D|49998|0089213

DRAWING DATA=2888350 |10001| D|PL |D|0001 | D|49998|0031890

DRAWING DATA=2888350 |10001| 1|QP |D|0000.COV | 1|49998|0025404

DRAWING DATA=2888350 |10001| 1|QP |D|0000.I | -|49998|0018616

DRAWING DATA=2888350 |10001| 1|QP |D|0000.II | 1|49998|0012645

DRAWING DATA=2888350 |10001| 1|QP |D|0000.III | -|49998|0009629

DRAWING DATA=2888350 |10001| 1|QP |D|0000.IV | -|49998|0015547

DRAWING DATA=2888350 |10001| 1|QP |D|0001 | 1|49998|0025390

DRAWING DATA=2888350 |10001| 1|QP |D|0002 | -|49998|0025596

DRAWING DATA=2888350 |10001| 1|QP |D|0003 | -|49998|0028083

DRAWING DATA=2888350 |10001| 1|QP |D|0004 | 1|49998|0021344

DRAWING DATA=2888350 |10001| 1|QP |D|0005 | 1|49998|0022532

DRAWING DATA=2888350 |10001| 1|QP |D|0006 | -|49998|0022042

DRAWING DATA=2888350 |10001| 1|QP |D|0007 | -|49998|0008224

DRAWING DATA=2888476 |10001| A| |D|0001 | A|49998|0046586

DRAWING DATA=2889758 |10001| A| |D|0001 | A|00000|0000000

DOCUMENT REF DATA=MIL-STD-105 | | |E |950227|A| | |

DOCUMENT REF DATA=MIL-F-14072 | | |D |901004|A| | |

DOCUMENT REF DATA=MS33649 | | |C |840802|A| | |

DOCUMENT REF DATA=MIL-I-45208 | | |A |810724|A|1 | |

DOCUMENT REF DATA=ASTM-E1119 | | | |860725|A| | |

DOCUMENT REF DATA=ASTM-D1193 | | | |910915|A| | |

DOCUMENT REF DATA=MIL-STD-13231 | | | |991102|A| | |

DOCUMENT REF DATA=ASTM-B139/B139M | | | |900223|A| | |

DOCUMENT REF DATA=NASM20995 | | | |980430|A| | |

DOCUMENT REF DATA=ASTM-A240/A240M | | | |940815|A| | |

DOCUMENT REF DATA=SAE-AS28778 | | | |010301|A| | |

DOCUMENT REF DATA=ASTM-A313/A313M | | | |921015|A| | |

DOCUMENT REF DATA=NASM33540 | | | |980630|A| | |

DOCUMENT REF DATA=ASME-B46.1 | | |85 |851205|A| | |

DOCUMENT REF DATA=ASTM-A484/A484M | | | |920815|A| | |

DOCUMENT REF DATA=SAE-AS5169 | | | |990928|A| | |

DOCUMENT REF DATA=ANSI-Z540.1 | | | |940727|A| | |

DOCUMENT REF DATA=ASTM-A580/A580M | | | |930215|A| | |

DOCUMENT REF DATA=ASTM-A582/A582M | | | |930316|A| | |

DOCUMENT REF DATA=DI-NDTI-80603 | | | |880601|A| | |

DOCUMENT REF DATA=DI-NDTI-80809 | | |B |970124|A| | |

DOCUMENT REF DATA=ASTM-A967 | | | |970331|A| | |

DOCUMENT REF DATA=MIL-STD-973 | | | |950113|A| |03|

DOCUMENT CHANGE DATA=AN814 |SAE-AS5169

DOCUMENT CHANGE DATA=ISO8402 |ISO9000

DOCUMENT CHANGE DATA=ISO9002 |ISO9001

DOCUMENT CHANGE DATA=MIL-C-45662 |ANSI-Z540.1

DOCUMENT CHANGE DATA=MIL-E-9500 |ASTM-E1119

DOCUMENT CHANGE DATA=MIL-M-13231 |MIL-STD-13231

DOCUMENT CHANGE DATA=MIL-STD-10 |ASME-B46.1

DOCUMENT CHANGE DATA=MIL-STD-109 |ISO8402

DOCUMENT CHANGE DATA=MS20995 |NASM20995

DOCUMENT CHANGE DATA=MS27778 |SAE-AS28778

DOCUMENT CHANGE DATA=MS29512 |SAE-AS29512

DOCUMENT CHANGE DATA=MS33540 |NASM33540

DOCUMENT CHANGE DATA=QQ-B-750 |ASTM-B139

DOCUMENT CHANGE DATA=QQ-C-390 |UNS92200

DOCUMENT CHANGE DATA=QQ-P-35 |ASTM-A967

DOCUMENT CHANGE DATA=QQ-S-764 |ASTM-A582 & A484

DOCUMENT CHANGE DATA=QQ-S-766 |ASTM-A240 UNS30400

DOCUMENT CHANGE DATA=QQ-W-423 |ASTM-A313 & A580

DOCUMENT CHANGE DATA=2468655-1(10001) |2468746(10001)

3. REQUIREMENTS

3.1 Manufacturing and Design - The VALVE,SAFETY RELIEF furnished under this contract/purchase order shall meet the material and physical requirements as specified ;0n drawing 2888350 cage 10001/w associated drawings and specs; .

3.2 Cage Code/Reference Number Items - The VALVE,SAFETY RELIEF furnished under this

contract/purchase order shall be the design represented by Cage Code(s)

reference number(s). Cage _______ ref. no.

;4J831 2888350

71905 2888350;

3.3 Marking - This item shall be physically identified in accordance

with ;MIL-STD-130, REV N, 16 NOV 2012; .

3.4 First Article Test Procedures are required and must be approved prior to any First Article Testing.

3.5 First Article Approval (Contractor Testing) - First Article Test (FAT) and approval is required.

3.6 Production Lot Test Procedures are required.

3.7 Production Lot Approval (Contractor Testing) - Production Lot Test and approval is required.

3.8 Configuration Control in accordance with MIL-STD-973 Short Form procedures - The requirements of MIL-STD-973 are hereby invoked in the contract/purchase order. The tailoring notes stated in the order cited in paragraph 6.2.1.3 are stated below:

A. Considered, tailoring implemented

B. Automated processing and submittal is not required.

Interactive access to digital data is not required.

C. Configuration audits are not required.

D. Contractor's configuration management plan is not requried.

E. Configuration terminology development documentation is required.

F. Only paragraphs 5.3.3.2, 5.3.6.4, 5.3.6.7, 5.3.6.7.3 are required.

G. FCD is not required.

H. ACD and PCD is not required.

I. Not Applicable (NA) to this contract/purchase order.

J. NA to this contract/purchase order.

K. NA to this contract/purchase order.

L. Paragraph 5.3.6 with the exception of paragraph 5.3.6.5 and

5.3.6.7.1 are required.

M. Paragraph 5.3.6.6 and 5.3.6.6.2 are required.

N. Paragraph 5.3.6.6.1 is not required unless specifically cited

elsewhere in Section "C" of this contract/purchase order.

O. The marking requirement is stated elsewhere in Section "C" of this

contract/purchase order.

P. Interface requirements are as specified on the drawings provided

with this contract/purchase order or the primary equipment

performance MIL-SPEC or STD cited in Section "C" of this

contract/purchase order.

Q. NA to this contract/purchase order.

R. All Class I changes to either a Government owned Configuration

Identification (CI) or baseline configuration shall be submitted to

the Procurement Contracting Officer for review and subsequent

approval - conditional approval or disapproval. NDI, COTS, and PDI

items previously accepted by the Government shall be submitted as

above. This process does not excuse the contractor from initially

offering to the Government an item which meets the minimum

technical and operational requirements set forth in this contract/

purchase order.

S. Preliminary Change Notices and Advance Change Study Notices are not

required.

T. NA to this contract/purchase order.

U. and V. Class II Engineering Change Proposal (ECP) may be carried

through provided the Government QAR reviews and concurs with the

classification review which resulted in the ECP being classified as

Class II.

W. Paragraph 5.4.3 is required.

X. Paragraph 5.4.4 is required.

Y. NORS are not required for this contract/purchase order.

Z. Short Form procedures are allowed.

AA. Paragraph 5.5.2 is not required for this contract/purchase order.

AB. Paragraph 5.5.7 is not required for this contract/purchase order.

AC. Paragraph 5.5.8 is not required for this contract/purchase order.

AD. Paragraph 5.6.2 is not required for this contract/purchase order.

AE. Paragarph 5.6.3 is not required for this contract/purchase order.

AF. Paragraph 5.4.2.2.3.2b is not required for this contract/purchase

order.

3.8.1 Configuration Control - When the Contractor has received authorization on a prior contract for the same NSN for the use of a drawing of a later revision status, that authorization is hereby extended to all succeeding contracts/purchase orders until

another drawing revision is approved. The Contractor will notify the PCO of this occurrence in each instance, in the response to the solicitation. Such notification shall be in writing setting forth the contract under which the prior authorization was granted,

the date of the granting of the authorization, and the name of the granting authority.

Contractors shall also refer technical inquiries (other than those covered by MIL-STD-973) on company letterhead signed by a responsible company official, with copies distributed as stated below.

The original and two copies of all Contractor generated correspondence regarding configuration shall be submitted to Contracting Officer, NAVICP-MECH, P.O. Box 2020, Mechanicsburg, PA 17055-0788.

Contractors are cautioned that implementing engineering changes, waivers, deviations or technical inquiries into the contract/purchase order without approval of the Contracting Officer will be at the sole risk of the Contractor.

4. QUALITY ASSURANCE

4.1 Responsibility for Inspection - Unless otherwise specified in the contract/purchase order, the Contractor is responsible for the performance of all inspection requirements as specified herein. Except as otherwise specified in the contract/purchase order,

the Contractor may use his own or any other facilities suitable for the performance of the inspection requirements specified herein, unless disapproved by the Government. The Government reserves the right to perform any of the inspections set forth in the

specification where such inspections are deemed necessary to assure supplies and services conform to prescribed requirements.

4.2 Responsibility for Compliance - All items must meet all requirements of this contract/purchase order. The inspection set forth in this specification shall become a part of the Contractor's overall inspection system or quality program. The absence of any

inspection requirements shall not relieve the Contractor of the responsibility of assuring that all products or supplies submitted to the Government for acceptance comply with all requirements of the contract/purchase order. Sampling in quality conformance

does not authorize submission of known defective material, either indicated or actual, not does it commit the Government to acceptance of defective material.

4.3 Records - Records of all inspection work by the Contractor shall be kept complete and available to the Government during the performance of contract/purchase order and for a period of 365 calendar days after final delivery of supplies.

4.4 First Article Test/Inspection (Contractor) - The Contractor shall conduct ;non-destructive; First Article Test/Inspection on ;ONE (1); unit(s) in accordance with requirements ;in accordance with drawing 2888350 and QP2888350 and all associated drawings

and specfications; .

4.5 First Article Test Procedures - (Government Approval) - The Contractor shall prepare and submit test procedures in accordance with the Contract Data Requirements List (DD Form 1423). The test procedures shall be approved prior to production.

There is hereby created an option for the Government to waive the requirement for submission of a test procedure. If the Offeror has had its test procedure previously approved by the Government, furnish the name of the approval activity, date of

approval, and contract number under which the test procedure was approved.

In the event the Government exercises the option to waive submission of a test procedure, the previously approved procedure shall apply to the contract/purchase order.

4.6 First Article Test/Inspection Report - The Contractor shall prepare and submit a report in accordance with the Contract Data Requirements List (DD Form 1423). The report shall be approved prior to production.

4.7 Production Lot Test Procedures - (Government Approval) - The Contractor shall prepare and submit test procedures in accordance with the Contract Data Requirements List (DD Form 1423).

There is hereby created an option for the Government to waive the requirement for submission of a test procedure. If the Offeror has had its test procedure proviously approved by the Government, furnish the name of the approval activity, date of approval,

and contract number under which the test procedure was approved.

In the event the Government exercises the option to waive submission of a test procedure, the previously approved procedure shall apply to the contract/purchase order.

4.8 Production Lot Test (Contractor) - The Contractor shall perform 100% production testing in accordance with ;the approved test/inspection procedure for drawing 2888350 and QP2888350; .

4.9 Production Lot Test/Inspection Report - The Contractor shall prepare and submit a report in accordance with the Contract Data Requirements List (DD Form 1423).

4.10 Production Lot Test Approval - Production Lot Test approval is required prior to shipment of the Production Lot.

5. PACKAGING

5.1 Preservation, Packaging, Packing and Marking - Preservation, Packaging, Packing and Marking shall be in accordance with the Contract/Purchase Order Schedule and as specified below.

MIL-STD 2073 PACKAGING APPLIES AS FOUND ELSEWHERE IN THE SCHEDULE

6. NOTES

6.1 Ordering Information for Document References - The Department of Defense Single Stock Point (DODSSP), Website http://www.dsp.dla.mil/, provides product information for the Department Of Defense Index Of Specifications and Standards (DODISS)

(i.e.Military/Federal Specifications and Standards), Data Item Descriptions (DIDs), and other DODSSP Products. Most Specifications can obtained directly from http://quicksearch.dla.mil/

A. Availability of Cancelled Documents - The DODSSP offers cancelled documentsthat are required by private industry in fulfillment of contractual obligationsin paper format. Documents can be requested by phoning the Subscription Services Desk.

B. Commercial Specifications, Standards, and Descriptions - These specifications, standards and descriptions are not available from Government sources. Theymay be obtained from the publishers of the applicable societies.

C. Ordnance Standards (OS), Weapons Specifications (WS), and NAVORD OSTD 600 Pages - These type publications may be obtained by submitting a request to:

Commander, Indian Head Division, Naval Surface Warfare Center

Code 8410P, 101 Strauss Avenue

Indian Head, MD 20640-5035

D. On post-award actions, requests for "Official Use Only" and "NOFORN" (Not Releasable To Foreign Nationals) documents must identify the Government ContractNumber, and must be submitted via the cognizant Defense Contract Management Command (DCMC) for

certification of need for the document. On pre-award actions such requests must be submitted to the PCO for certification of need for the document.

E. NOFORN Military Specifications and Standards (including Amendments, Change Notices and Supplements, but NOT interim Changes) to be ordered from:

Contracting Officer

NAVSUP-WSS

Code 87321

5450 Carlisle Pike

P.O. Box 2020

Mechanicsburg, Pa. 17055-0788

F. Nuclear Reactor Publications Assigned NAVSEA Documents and Identification Numbers (i.e. NAVSEA Welding Standard, NAVSEA 250-1500-1) are to be ordered enue:

Commanding Officer

NAVSUP-WSS

Code 009

5450 Carlisle Pike

P.O. Box 2020

Mechanicsburg, Pa. 17055-0788

G. Technical Manuals Assigned NAVSEA Identification Numbers (i.e. NAVSEA Welding And Brazing Procedure, NAVSEA S9074-AQ-GIB-010/248) are to be ordered from:

Commanding Officer

NAVSUP-WSS

Code 1 Support Branch

700 Robbins Avenue

Philadelphia, Pa. 19111-5094

H. Interim Changes and Classified Specifications must be obtained by submitting a request on DD Form 1425 to NAVSUP-WSS.

6.2 In accordance with OPNAVINST 5510.1 all documents and drawings provided by the U.S. Navy to perspective Contractors must include a "Distribution Statement" to inform the contractor of the limits of distribution, and the safeguarding of the information

contained on those documents and drawings.

There are 7 (seven) seperate distribution statement codes used for non-classified documents and drawings. The definition for each is as follows:

A... approved for public release; distribution is unlimited.

B... distribution authorized to US Governments agencies only.

C... distribution authorized to US Government agencies and their contractors.

D... distribution authorized to DoD and DoD contractors only.

E... distribution authorized to DoD Components only.

F... further distribution only as directed by Commander, Naval Sea

Systems Command, code 09T.

X... distribution is authorized to US Government agencies and private individuals or enterprises eligible to obtain export controlled technical

data in accordance with OPNAVINST 5510.161.

6.3 Notice To Distributors/Offerors - Consideration for award of contract shall be given only to authorized distributors of the original manufacturer's item represented in this solicitation. If you desire to be considered as a potential source for award of

this contract, proof of being an authorized distributor shall be provided on company letterhead signed by a responsible company official and sent with your offer to the Procurement Contracting Officer.

DATE OF FIRST SUBMISSION=060 DAC

Block 12 - Submit for approval prior to First Article Test/Inspection.

Block 12 - Resubmit no later than ;15; days after disapproval.

Block 14 - Port Hueneme Division, Naval Surface Warfare Center, ;code 5D21; ,Port Hueneme, CA 93043-5007.

Block 14A - ISEA information copy cover letter and first page of data shall be clearly marked "Information Copy".

;Copies of passing reports shall be submitted to our distribution listing. ;

DATE OF FIRST SUBMISSION=180 DAC

Block 12 - Submit for approval prior to production.

Block 12 - Resubmit no later than ;15; days after disapproval.

Block 14 - Port Hueneme Division, Naval Surface Warfare Center, ;Code 5D21; ,Port Hueneme, CA 93043-5007.

Block 14A - ISEA information copy cover letter and first page of data shall be clearly marked "Information Copy".

;Copies of passing reports shall be submitted to our distribution listing.;

DATE OF FIRST SUBMISSION=060 DAC

Block 12 - Submit for approval prior to production.

Block 12 - Resubmit no later than ;15; days after disapproval.

1.1 The DCMC QAR approved deliverable shall be sent, within 10 days of approval, to activities listed under distribution. Block 14 - Port Hueneme Division, Naval Surface Warfare Center, ;Code 5D21; ,Port Hueneme, CA 93043-5007.

Block 14A - ISEA information copy cover letter and first page of data shall be clearly marked "Information Copy".

;Copies of passing reports shall be submitted to our distribution listing.;

DATE OF FIRST SUBMISSION=ASREQ

1.2 Block 12 - Submit for approval in accordance with the Delivery Schedule.

Block 12 - Resubmit no later than ;15; days after disapproval.

1.3 The DCMC QAR approved deliverable shall be sent, within 10 days of approval, to activities listed under distribution. Block 14 - Port Hueneme Division, Naval Surface Warfare Center, ;Code 5D21; ,Port Hueneme, CA 93043-5007.

Block 14A - ISEA information copy cover letter and first page of data shall be clearly marked "Information Copy".

;Copies of passing reports shall be submitted to our distribution listing.;

Similar open opportunities

Opportunity Agency Set-aside Responses due
Valve, safety relief NAICS 332911 Land and Maritime Total Small Business
Valve, safety relief NAICS 332911 Land and Maritime No set-aside
Valve, safety relief NAICS 332911 Land and Maritime Total Small Business
Valve, safety relief NAICS 332911 Land and Maritime Total Small Business
Valve, safety relief NAICS 332911 Land and Maritime No set-aside

On GovTribe

Work this opportunity

  • Track it in your pipeline
  • Find teaming partners
  • Similar opportunities
  • Ask GovTribe AI about this opportunity