USACE SPK DBB ? MOTCO ERCIP 6. 25MW Generation Plant

Closed Solicitation Posted

Solicitation number
W9123823R0034
Agency
Responses due
Set-aside
Total Small Business

Opportunity facts

Notice details come from SAM.gov. Updated .

About this opportunity

This solicitation from the Department of the Army Corps of Engineers Engineering District Sacramento seeks the construction of a backup power generation plant at the Military Ocean Terminal in Concord, California. The successful offeror will install three diesel-powered electrical generators, a load bank, switchgear, fuel storage tanks, and an underground duct bank to provide approximately 6MW of backup power capacity. Proposals are due by August 18, 2023 and will be evaluated based on technical qualifications, past performance, and price.

The opportunity is set aside for total small businesses. The work includes constructing generator enclosures; emissions control equipment; a refueling lane; and a fuel polishing unit. An underground duct bank will also be trenched and direct buried. The estimated value is between $25-100 million and must be performed at the Military Ocean Terminal in Concord. The single point of contact for plans and specifications is the Procurement Integrated Enterprise Environment website.

Notice text

9 versions

Update #9 · Latest ·

AMENDMENT 0001 - update date for the submission of site visit access forms and provide an additional email address. Please note that if you already submitted your site visit access forms to the contract specialist, you do not need to re-submit. This project is in support of the Military Ocean Terminal, Concord (MOTCO), located in Concord California and will consist of the following: Construct a backup pow er generation plant, comprised of an array of three diesel powered electrical generators providing approx. 6MW of capacity, 2MW load bank, 1200-amp switchgear, 72,000-gal capacity fuel storage tanks for a 14-day supply of fuel, and approx. 12,000 linear feet of underground duct bank with 500kcmil pow er distribution conductors. Construction of the generators will require site prep f or the generator enclosures; tier-4 emissions control equipment; construction of a refueling lane to service fuel storage tanks; and a fuel polishing unit. Construction of the underground duct bank will consist of trenching and direct-burying of PVC conduit; installation of electrical lines and manholes; installation of duct bank conduit and conductors affixed underneath an existing vehicle bridge; and tie-in to existing electrical infrastructure on the installation, including break-before-make interconnection to PG and E utility grid. Per DFARS 236.204(ii) the magnitude of construction is estimated to be between $25,000,000 and $100,000,000.The only INTERESTED VENDORS LISTS (plan-holder/bidder list) is available via SAM.gov. Contractors are responsible for self-identifying as interested vendors and viewing other interested vendors. Contractors should check SAM.gov frequently for any changes to the interested vendors list and notice. **Note**: Contractors must be registered in the System for Award Management (SAM) at https://sam.gov/content/home prior to award of this contract. Solicitation documents, plans and specifications will only be available via the Procurement Integrated Enterprise Environment (PIEE) website, link provided below. Instructions on getting access to the PIEE Solicitation Module and submitting your proposal were provided with the Pre-Solicitation posting for this requirement and are also available via the PIEE website training module. Registration for plans and specifications should be made via the Procurement Integrated Enterprise Environment (PIEE) website https://wawf.eb.mil. Registration in PIEE is a multi step process and can take several days so plan accordingly. If you are not registered, the United States Government is not responsible for providing you with notifications of any changes to this solicitation. The solicitation will be available only as a direct download. It is therefore the Contractors responsibility to monitor the website daily for any posted changes or amendments to this solicitation. The plans and specifications and all notifications of changes to this solicitation shall only be made through this posting and modifications hereto. This solicitation is in .pdf format and requires Adobe Acrobat Reader. Adobe Acrobat Reader may be downloaded free of charge at http://www.adobe.com/products/read~~This amendment extends the proposal due date to 23 June 2023 and the ProjNet submission date to 13 June 2023. The site visit agenda, sign in list and site visit photos are attached.~~Amendment 0003 - This amendment extends the Proposal due date to 30 June 2023.~~Amendment 0004 to extend the proposal due date to 4:00 pm 10 July 2023.~~Amendment 0005 to extend the proposal due date to 4:00 pm on 20 July 2023.~~Amendment 0006: Update specifications/Plans, Add Past Performance Questionnaire, Update Wage Determination.~~Amendment 0007 - Add updated Pre-award Survey~~Amendment 0008, to Update the Wage Determination, Conformed Specifications and Plans.

Update #8 ·

AMENDMENT 0001 - update date for the submission of site visit access forms and provide an additional email address. Please note that if you already submitted your site visit access forms to the contract specialist, you do not need to re-submit. This project is in support of the Military Ocean Terminal, Concord (MOTCO), located in Concord California and will consist of the following: Construct a backup pow er generation plant, comprised of an array of three diesel powered electrical generators providing approx. 6MW of capacity, 2MW load bank, 1200-amp switchgear, 72,000-gal capacity fuel storage tanks for a 14-day supply of fuel, and approx. 12,000 linear feet of underground duct bank with 500kcmil pow er distribution conductors. Construction of the generators will require site prep f or the generator enclosures; tier-4 emissions control equipment; construction of a refueling lane to service fuel storage tanks; and a fuel polishing unit. Construction of the underground duct bank will consist of trenching and direct-burying of PVC conduit; installation of electrical lines and manholes; installation of duct bank conduit and conductors affixed underneath an existing vehicle bridge; and tie-in to existing electrical infrastructure on the installation, including break-before-make interconnection to PG and E utility grid. Per DFARS 236.204(ii) the magnitude of construction is estimated to be between $25,000,000 and $100,000,000.The only INTERESTED VENDORS LISTS (plan-holder/bidder list) is available via SAM.gov. Contractors are responsible for self-identifying as interested vendors and viewing other interested vendors. Contractors should check SAM.gov frequently for any changes to the interested vendors list and notice. **Note**: Contractors must be registered in the System for Award Management (SAM) at https://sam.gov/content/home prior to award of this contract. Solicitation documents, plans and specifications will only be available via the Procurement Integrated Enterprise Environment (PIEE) website, link provided below. Instructions on getting access to the PIEE Solicitation Module and submitting your proposal were provided with the Pre-Solicitation posting for this requirement and are also available via the PIEE website training module. Registration for plans and specifications should be made via the Procurement Integrated Enterprise Environment (PIEE) website https://wawf.eb.mil. Registration in PIEE is a multi step process and can take several days so plan accordingly. If you are not registered, the United States Government is not responsible for providing you with notifications of any changes to this solicitation. The solicitation will be available only as a direct download. It is therefore the Contractors responsibility to monitor the website daily for any posted changes or amendments to this solicitation. The plans and specifications and all notifications of changes to this solicitation shall only be made through this posting and modifications hereto. This solicitation is in .pdf format and requires Adobe Acrobat Reader. Adobe Acrobat Reader may be downloaded free of charge at http://www.adobe.com/products/read~~This amendment extends the proposal due date to 23 June 2023 and the ProjNet submission date to 13 June 2023. The site visit agenda, sign in list and site visit photos are attached.~~Amendment 0003 - This amendment extends the Proposal due date to 30 June 2023.~~Amendment 0004 to extend the proposal due date to 4:00 pm 10 July 2023.~~Amendment 0005 to extend the proposal due date to 4:00 pm on 20 July 2023.~~Amendment 0006: Update specifications/Plans, Add Past Performance Questionnaire, Update Wage Determination.~~Amendment 0007 - Add updated Pre-award Survey

Update #7 ·

AMENDMENT 0001 - update date for the submission of site visit access forms and provide an additional email address. Please note that if you already submitted your site visit access forms to the contract specialist, you do not need to re-submit. This project is in support of the Military Ocean Terminal, Concord (MOTCO), located in Concord California and will consist of the following: Construct a backup pow er generation plant, comprised of an array of three diesel powered electrical generators providing approx. 6MW of capacity, 2MW load bank, 1200-amp switchgear, 72,000-gal capacity fuel storage tanks for a 14-day supply of fuel, and approx. 12,000 linear feet of underground duct bank with 500kcmil pow er distribution conductors. Construction of the generators will require site prep f or the generator enclosures; tier-4 emissions control equipment; construction of a refueling lane to service fuel storage tanks; and a fuel polishing unit. Construction of the underground duct bank will consist of trenching and direct-burying of PVC conduit; installation of electrical lines and manholes; installation of duct bank conduit and conductors affixed underneath an existing vehicle bridge; and tie-in to existing electrical infrastructure on the installation, including break-before-make interconnection to PG and E utility grid. Per DFARS 236.204(ii) the magnitude of construction is estimated to be between $25,000,000 and $100,000,000.The only INTERESTED VENDORS LISTS (plan-holder/bidder list) is available via SAM.gov. Contractors are responsible for self-identifying as interested vendors and viewing other interested vendors. Contractors should check SAM.gov frequently for any changes to the interested vendors list and notice. **Note**: Contractors must be registered in the System for Award Management (SAM) at https://sam.gov/content/home prior to award of this contract. Solicitation documents, plans and specifications will only be available via the Procurement Integrated Enterprise Environment (PIEE) website, link provided below. Instructions on getting access to the PIEE Solicitation Module and submitting your proposal were provided with the Pre-Solicitation posting for this requirement and are also available via the PIEE website training module. Registration for plans and specifications should be made via the Procurement Integrated Enterprise Environment (PIEE) website https://wawf.eb.mil. Registration in PIEE is a multi step process and can take several days so plan accordingly. If you are not registered, the United States Government is not responsible for providing you with notifications of any changes to this solicitation. The solicitation will be available only as a direct download. It is therefore the Contractors responsibility to monitor the website daily for any posted changes or amendments to this solicitation. The plans and specifications and all notifications of changes to this solicitation shall only be made through this posting and modifications hereto. This solicitation is in .pdf format and requires Adobe Acrobat Reader. Adobe Acrobat Reader may be downloaded free of charge at http://www.adobe.com/products/read~~This amendment extends the proposal due date to 23 June 2023 and the ProjNet submission date to 13 June 2023. The site visit agenda, sign in list and site visit photos are attached.~~Amendment 0003 - This amendment extends the Proposal due date to 30 June 2023.~~Amendment 0004 to extend the proposal due date to 4:00 pm 10 July 2023.~~Amendment 0005 to extend the proposal due date to 4:00 pm on 20 July 2023.~~Amendment 0006: Update specifications/Plans, Add Past Performance Questionnaire, Update Wage Determination.

Update #6 ·

AMENDMENT 0001 - update date for the submission of site visit access forms and provide an additional email address. Please note that if you already submitted your site visit access forms to the contract specialist, you do not need to re-submit. This project is in support of the Military Ocean Terminal, Concord (MOTCO), located in Concord California and will consist of the following: Construct a backup pow er generation plant, comprised of an array of three diesel powered electrical generators providing approx. 6MW of capacity, 2MW load bank, 1200-amp switchgear, 72,000-gal capacity fuel storage tanks for a 14-day supply of fuel, and approx. 12,000 linear feet of underground duct bank with 500kcmil pow er distribution conductors. Construction of the generators will require site prep f or the generator enclosures; tier-4 emissions control equipment; construction of a refueling lane to service fuel storage tanks; and a fuel polishing unit. Construction of the underground duct bank will consist of trenching and direct-burying of PVC conduit; installation of electrical lines and manholes; installation of duct bank conduit and conductors affixed underneath an existing vehicle bridge; and tie-in to existing electrical infrastructure on the installation, including break-before-make interconnection to PG and E utility grid. Per DFARS 236.204(ii) the magnitude of construction is estimated to be between $25,000,000 and $100,000,000.The only INTERESTED VENDORS LISTS (plan-holder/bidder list) is available via SAM.gov. Contractors are responsible for self-identifying as interested vendors and viewing other interested vendors. Contractors should check SAM.gov frequently for any changes to the interested vendors list and notice. **Note**: Contractors must be registered in the System for Award Management (SAM) at https://sam.gov/content/home prior to award of this contract. Solicitation documents, plans and specifications will only be available via the Procurement Integrated Enterprise Environment (PIEE) website, link provided below. Instructions on getting access to the PIEE Solicitation Module and submitting your proposal were provided with the Pre-Solicitation posting for this requirement and are also available via the PIEE website training module. Registration for plans and specifications should be made via the Procurement Integrated Enterprise Environment (PIEE) website https://wawf.eb.mil. Registration in PIEE is a multi step process and can take several days so plan accordingly. If you are not registered, the United States Government is not responsible for providing you with notifications of any changes to this solicitation. The solicitation will be available only as a direct download. It is therefore the Contractors responsibility to monitor the website daily for any posted changes or amendments to this solicitation. The plans and specifications and all notifications of changes to this solicitation shall only be made through this posting and modifications hereto. This solicitation is in .pdf format and requires Adobe Acrobat Reader. Adobe Acrobat Reader may be downloaded free of charge at http://www.adobe.com/products/read~~This amendment extends the proposal due date to 23 June 2023 and the ProjNet submission date to 13 June 2023. The site visit agenda, sign in list and site visit photos are attached.~~Amendment 0003 - This amendment extends the Proposal due date to 30 June 2023.~~Amendment 0004 to extend the proposal due date to 4:00 pm 10 July 2023.~~Amendment 0005 to extend the proposal due date to 4:00 pm on 20 July 2023.

Update #5 ·

AMENDMENT 0001 - update date for the submission of site visit access forms and provide an additional email address. Please note that if you already submitted your site visit access forms to the contract specialist, you do not need to re-submit. This project is in support of the Military Ocean Terminal, Concord (MOTCO), located in Concord California and will consist of the following: Construct a backup pow er generation plant, comprised of an array of three diesel powered electrical generators providing approx. 6MW of capacity, 2MW load bank, 1200-amp switchgear, 72,000-gal capacity fuel storage tanks for a 14-day supply of fuel, and approx. 12,000 linear feet of underground duct bank with 500kcmil pow er distribution conductors. Construction of the generators will require site prep f or the generator enclosures; tier-4 emissions control equipment; construction of a refueling lane to service fuel storage tanks; and a fuel polishing unit. Construction of the underground duct bank will consist of trenching and direct-burying of PVC conduit; installation of electrical lines and manholes; installation of duct bank conduit and conductors affixed underneath an existing vehicle bridge; and tie-in to existing electrical infrastructure on the installation, including break-before-make interconnection to PG and E utility grid. Per DFARS 236.204(ii) the magnitude of construction is estimated to be between $25,000,000 and $100,000,000.The only INTERESTED VENDORS LISTS (plan-holder/bidder list) is available via SAM.gov. Contractors are responsible for self-identifying as interested vendors and viewing other interested vendors. Contractors should check SAM.gov frequently for any changes to the interested vendors list and notice. **Note**: Contractors must be registered in the System for Award Management (SAM) at https://sam.gov/content/home prior to award of this contract. Solicitation documents, plans and specifications will only be available via the Procurement Integrated Enterprise Environment (PIEE) website, link provided below. Instructions on getting access to the PIEE Solicitation Module and submitting your proposal were provided with the Pre-Solicitation posting for this requirement and are also available via the PIEE website training module. Registration for plans and specifications should be made via the Procurement Integrated Enterprise Environment (PIEE) website https://wawf.eb.mil. Registration in PIEE is a multi step process and can take several days so plan accordingly. If you are not registered, the United States Government is not responsible for providing you with notifications of any changes to this solicitation. The solicitation will be available only as a direct download. It is therefore the Contractors responsibility to monitor the website daily for any posted changes or amendments to this solicitation. The plans and specifications and all notifications of changes to this solicitation shall only be made through this posting and modifications hereto. This solicitation is in .pdf format and requires Adobe Acrobat Reader. Adobe Acrobat Reader may be downloaded free of charge at http://www.adobe.com/products/read~~This amendment extends the proposal due date to 23 June 2023 and the ProjNet submission date to 13 June 2023. The site visit agenda, sign in list and site visit photos are attached.~~Amendment 0003 - This amendment extends the Proposal due date to 30 June 2023.~~Amendment 0004 to extend the proposal due date to 4:00 pm 10 July 2023.

Update #4 ·

AMENDMENT 0001 - update date for the submission of site visit access forms and provide an additional email address. Please note that if you already submitted your site visit access forms to the contract specialist, you do not need to re-submit. This project is in support of the Military Ocean Terminal, Concord (MOTCO), located in Concord California and will consist of the following: Construct a backup pow er generation plant, comprised of an array of three diesel powered electrical generators providing approx. 6MW of capacity, 2MW load bank, 1200-amp switchgear, 72,000-gal capacity fuel storage tanks for a 14-day supply of fuel, and approx. 12,000 linear feet of underground duct bank with 500kcmil pow er distribution conductors. Construction of the generators will require site prep f or the generator enclosures; tier-4 emissions control equipment; construction of a refueling lane to service fuel storage tanks; and a fuel polishing unit. Construction of the underground duct bank will consist of trenching and direct-burying of PVC conduit; installation of electrical lines and manholes; installation of duct bank conduit and conductors affixed underneath an existing vehicle bridge; and tie-in to existing electrical infrastructure on the installation, including break-before-make interconnection to PG and E utility grid. Per DFARS 236.204(ii) the magnitude of construction is estimated to be between $25,000,000 and $100,000,000.The only INTERESTED VENDORS LISTS (plan-holder/bidder list) is available via SAM.gov. Contractors are responsible for self-identifying as interested vendors and viewing other interested vendors. Contractors should check SAM.gov frequently for any changes to the interested vendors list and notice. **Note**: Contractors must be registered in the System for Award Management (SAM) at https://sam.gov/content/home prior to award of this contract. Solicitation documents, plans and specifications will only be available via the Procurement Integrated Enterprise Environment (PIEE) website, link provided below. Instructions on getting access to the PIEE Solicitation Module and submitting your proposal were provided with the Pre-Solicitation posting for this requirement and are also available via the PIEE website training module. Registration for plans and specifications should be made via the Procurement Integrated Enterprise Environment (PIEE) website https://wawf.eb.mil. Registration in PIEE is a multi step process and can take several days so plan accordingly. If you are not registered, the United States Government is not responsible for providing you with notifications of any changes to this solicitation. The solicitation will be available only as a direct download. It is therefore the Contractors responsibility to monitor the website daily for any posted changes or amendments to this solicitation. The plans and specifications and all notifications of changes to this solicitation shall only be made through this posting and modifications hereto. This solicitation is in .pdf format and requires Adobe Acrobat Reader. Adobe Acrobat Reader may be downloaded free of charge at http://www.adobe.com/products/read~~This amendment extends the proposal due date to 23 June 2023 and the ProjNet submission date to 13 June 2023. The site visit agenda, sign in list and site visit photos are attached.~~Amendment 0003 - This amendment extends the Proposal due date to 30 June 2023.

Update #3 ·

AMENDMENT 0001 - update date for the submission of site visit access forms and provide an additional email address. Please note that if you already submitted your site visit access forms to the contract specialist, you do not need to re-submit. This project is in support of the Military Ocean Terminal, Concord (MOTCO), located in Concord California and will consist of the following: Construct a backup pow er generation plant, comprised of an array of three diesel powered electrical generators providing approx. 6MW of capacity, 2MW load bank, 1200-amp switchgear, 72,000-gal capacity fuel storage tanks for a 14-day supply of fuel, and approx. 12,000 linear feet of underground duct bank with 500kcmil pow er distribution conductors. Construction of the generators will require site prep f or the generator enclosures; tier-4 emissions control equipment; construction of a refueling lane to service fuel storage tanks; and a fuel polishing unit. Construction of the underground duct bank will consist of trenching and direct-burying of PVC conduit; installation of electrical lines and manholes; installation of duct bank conduit and conductors affixed underneath an existing vehicle bridge; and tie-in to existing electrical infrastructure on the installation, including break-before-make interconnection to PG and E utility grid. Per DFARS 236.204(ii) the magnitude of construction is estimated to be between $25,000,000 and $100,000,000.The only INTERESTED VENDORS LISTS (plan-holder/bidder list) is available via SAM.gov. Contractors are responsible for self-identifying as interested vendors and viewing other interested vendors. Contractors should check SAM.gov frequently for any changes to the interested vendors list and notice. **Note**: Contractors must be registered in the System for Award Management (SAM) at https://sam.gov/content/home prior to award of this contract. Solicitation documents, plans and specifications will only be available via the Procurement Integrated Enterprise Environment (PIEE) website, link provided below. Instructions on getting access to the PIEE Solicitation Module and submitting your proposal were provided with the Pre-Solicitation posting for this requirement and are also available via the PIEE website training module. Registration for plans and specifications should be made via the Procurement Integrated Enterprise Environment (PIEE) website https://wawf.eb.mil. Registration in PIEE is a multi step process and can take several days so plan accordingly. If you are not registered, the United States Government is not responsible for providing you with notifications of any changes to this solicitation. The solicitation will be available only as a direct download. It is therefore the Contractors responsibility to monitor the website daily for any posted changes or amendments to this solicitation. The plans and specifications and all notifications of changes to this solicitation shall only be made through this posting and modifications hereto. This solicitation is in .pdf format and requires Adobe Acrobat Reader. Adobe Acrobat Reader may be downloaded free of charge at http://www.adobe.com/products/read~~This amendment extends the proposal due date to 23 June 2023 and the ProjNet submission date to 13 June 2023. The site visit agenda, sign in list and site visit photos are attached.

Update #2 ·

AMENDMENT 0001 - update date for the submission of site visit access forms and provide an additional email address. Please note that if you already submitted your site visit access forms to the contract specialist, you do not need to re-submit. This project is in support of the Military Ocean Terminal, Concord (MOTCO), located in Concord California and will consist of the following: Construct a backup pow er generation plant, comprised of an array of three diesel powered electrical generators providing approx. 6MW of capacity, 2MW load bank, 1200-amp switchgear, 72,000-gal capacity fuel storage tanks for a 14-day supply of fuel, and approx. 12,000 linear feet of underground duct bank with 500kcmil pow er distribution conductors. Construction of the generators will require site prep f or the generator enclosures; tier-4 emissions control equipment; construction of a refueling lane to service fuel storage tanks; and a fuel polishing unit. Construction of the underground duct bank will consist of trenching and direct-burying of PVC conduit; installation of electrical lines and manholes; installation of duct bank conduit and conductors affixed underneath an existing vehicle bridge; and tie-in to existing electrical infrastructure on the installation, including break-before-make interconnection to PG and E utility grid. Per DFARS 236.204(ii) the magnitude of construction is estimated to be between $25,000,000 and $100,000,000.The only INTERESTED VENDORS LISTS (plan-holder/bidder list) is available via SAM.gov. Contractors are responsible for self-identifying as interested vendors and viewing other interested vendors. Contractors should check SAM.gov frequently for any changes to the interested vendors list and notice. **Note**: Contractors must be registered in the System for Award Management (SAM) at https://sam.gov/content/home prior to award of this contract. Solicitation documents, plans and specifications will only be available via the Procurement Integrated Enterprise Environment (PIEE) website, link provided below. Instructions on getting access to the PIEE Solicitation Module and submitting your proposal were provided with the Pre-Solicitation posting for this requirement and are also available via the PIEE website training module. Registration for plans and specifications should be made via the Procurement Integrated Enterprise Environment (PIEE) website https://wawf.eb.mil. Registration in PIEE is a multi step process and can take several days so plan accordingly. If you are not registered, the United States Government is not responsible for providing you with notifications of any changes to this solicitation. The solicitation will be available only as a direct download. It is therefore the Contractors responsibility to monitor the website daily for any posted changes or amendments to this solicitation. The plans and specifications and all notifications of changes to this solicitation shall only be made through this posting and modifications hereto. This solicitation is in .pdf format and requires Adobe Acrobat Reader. Adobe Acrobat Reader may be downloaded free of charge at http://www.adobe.com/products/read

Update #1 ·

This project is in support of the Military Ocean Terminal, Concord (MOTCO), located in Concord California and will consist of the following: Construct a backup pow er generation plant, comprised of an array of three diesel powered electrical generators providing approx. 6MW of capacity, 2MW load bank, 1200-amp switchgear, 72,000-gal capacity fuel storage tanks for a 14-day supply of fuel, and approx. 12,000 linear feet of underground duct bank with 500kcmil pow er distribution conductors. Construction of the generators will require site prep f or the generator enclosures; tier-4 emissions control equipment; construction of a refueling lane to service fuel storage tanks; and a fuel polishing unit. Construction of the underground duct bank will consist of trenching and direct-burying of PVC conduit; installation of electrical lines and manholes; installation of duct bank conduit and conductors affixed underneath an existing vehicle bridge; and tie-in to existing electrical infrastructure on the installation, including break-before-make interconnection to PG and E utility grid. Per DFARS 236.204(ii) the magnitude of construction is estimated to be between $25,000,000 and $100,000,000.The only INTERESTED VENDORS LISTS (plan-holder/bidder list) is available via SAM.gov. Contractors are responsible for self-identifying as interested vendors and viewing other interested vendors. Contractors should check SAM.gov frequently for any changes to the interested vendors list and notice. **Note**: Contractors must be registered in the System for Award Management (SAM) at https://sam.gov/content/home prior to award of this contract. Solicitation documents, plans and specifications will only be available via the Procurement Integrated Enterprise Environment (PIEE) website, link provided below. Instructions on getting access to the PIEE Solicitation Module and submitting your proposal were provided with the Pre-Solicitation posting for this requirement and are also available via the PIEE website training module. Registration for plans and specifications should be made via the Procurement Integrated Enterprise Environment (PIEE) website https://wawf.eb.mil. Registration in PIEE is a multi step process and can take several days so plan accordingly. If you are not registered, the United States Government is not responsible for providing you with notifications of any changes to this solicitation. The solicitation will be available only as a direct download. It is therefore the Contractors responsibility to monitor the website daily for any posted changes or amendments to this solicitation. The plans and specifications and all notifications of changes to this solicitation shall only be made through this posting and modifications hereto. This solicitation is in .pdf format and requires Adobe Acrobat Reader. Adobe Acrobat Reader may be downloaded free of charge at http://www.adobe.com/products/read

Notice history

Notice Type Posted
This notice Latest solicitation Solicitation
USACE SPK -DBB – Military Ocean Terminal Concord (MOTCO) ERCIP 6. 25MW Generation Plant Original Pre-Solicitation