USACE SPK DBB Construction - ARCF Natomas Reach E - Sutter County, CA

Closed Solicitation Posted

This opportunity was awarded. See the award notice from .

Solicitation number
W9123823B0011
Agency
ENDIST Sacramento US Army Corps of Engineers, Department of Defense
Responses due
Set-aside
No set-aside

Opportunity facts

NAICS code
237990 Other Heavy and Civil Engineering Construction
PSC
Y1PC Construction Of Unimproved Real Property (Land)

Notice details come from SAM.gov. Updated .

About this opportunity

The U.S. Army Corps of Engineers, Sacramento District, seeks to award a design-bid-build construction contract to build a seepage cutoff wall adjacent to an existing levee as part of the American River Common Features Natomas Basin Reach E project in Pleasant Grove, California. The contractor will be responsible for constructing a soil bentonite cutoff wall using native soil and bentonite via open trench construction along 3.4 miles of levee. Additional requirements include constructing a landside patrol road with access ramps; replacing five culverts, five gatewells and a manhole; removing and relocating irrigation systems; performing borrow site excavation; and implementing stormwater pollution prevention and best management practices. Proposals are due February 10, 2023. The award will be made based on best value determined by evaluating technical qualifications, past performance, and price.

There is no set-aside designated for this procurement. The primary NAICS code is 237110 and PSC code is R404. Four bids were received ranging from $27.8 million to $40.3 million. The work must be completed within two construction seasons or approximately 606 calendar days and will be performed in Pleasant Grove, California.

Notice text

6 versions

Update #6 · Latest ·

////////////////////////////////////////////////////////////////////Bid Abstract Posted 14FEB23////////////////////////////////////////////////////////////////////The purpose of amendment 0004 is as follows: (1) Update Attachment 02 - Wage Determination from General Decision Number: CA20220007 dated 16 Dec 2022 to General Decision Number: CA20230007 dated 20 Jan 2023. (2) Add Attachment 12 - Specifications (Revised 31 Jan 23).////////////////////////////////////////////////////////////////////The purpose of amendment 0003 is as follows:(1) Add attachment 11 - ARCF Reach E Geotechnical Data Report. ////////////////////////////////////////////////////////////////////The purpose of Amendment 0002 is the following: (1) Change the date ProjNet will close for new inquiries from 1:00 PM (1300) Pacific Standard Time (PST), 22 January 2023, to 1:00 PM (1300) PST, 23 January 2023. (2) Add Attachment 07 - Pre-Bid Meeting Attendance Roster (In Person) - 18 Jan 23 (3) Add Attachment 08 - Pre-Bid Meeting Virtual Attendance Roster - 18 Jan 23 (4) Add Attachment 09 - Site Visit Attendance Roster - 18 Jan 23 (5) Add Attachment 10 - ARCF Reach E Pre-Bid Meeting Presentation - 18 Jan 23////////////////////////////////////////////////////////////////////*Update*The purpose of Amendment 0001 is to make the following changes: 1. Update Attachment 6 - Site Visit Information2. Update Section 00 21 13 - Instructions to Bidders////////////////////////////////////////////////////////////////////USACE SPK has a requirement for design-bid-build construction services to construct a seepage cutoff wall adjacent to the landward side of the existing levee of the ARCF Natomas Basin Reach E segment, located in Pleasant Grove, CA. The Natomas Basin Reach E segment is located along the southwest bank of the Pleasant Grove Creek Canal (PGCC). The PGCC is an artificial channel that trends generally south-southeast to north-northwest, collecting surface water draining from Pleasant Grove Creek and several other seasonal streams from the east. The surface water is directed north-northeast into the Natomas Cross Canal and eventually to the Sacramento River. Reach E currently extends 3.4 miles between Sankey Road north to Howsley Road. The typical levee cross section has a crown width of twenty (20) feet, an asphalt road used by local traffic, and landside and riverside slopes of 1 vertical to 3 horizontal (1V:3H). The levee height varies between five (5) and seventeen (17) feet along the reach. The requirement is anticipated to include construction of a seepage cutoff wall adjacent to the landward side of the existing levee, including soil bentonite (SB) open trench construction using native soil with bentonite and water. It is anticipated the project requirements will include construction of a landside patrol road along the entire length of Reach E, that includes access ramps at identified locations; excavation and replacement of five (5) culverts; excavation and replacement of five (5) existing metal gatewells; excavation and replacement of a manhole; removal and relocation of irrigation systems; borrow site excavation; performance of Storm Water Pollution Prevention Plan (SWPPP) documents and implementation; and Best Management Practices (BMPs) installation. It is estimated that construction of the potential requirement can be completed within two (2) construction seasons, or approximately six hundred and six (606) calendar days.

Update #5 ·

////////////////////////////////////////////////////////////////////The purpose of amendment 0004 is as follows: (1) Update Attachment 02 - Wage Determination from General Decision Number: CA20220007 dated 16 Dec 2022 to General Decision Number: CA20230007 dated 20 Jan 2023. (2) Add Attachment 12 - Specifications (Revised 31 Jan 23).////////////////////////////////////////////////////////////////////The purpose of amendment 0003 is as follows:(1) Add attachment 11 - ARCF Reach E Geotechnical Data Report. ////////////////////////////////////////////////////////////////////The purpose of Amendment 0002 is the following: (1) Change the date ProjNet will close for new inquiries from 1:00 PM (1300) Pacific Standard Time (PST), 22 January 2023, to 1:00 PM (1300) PST, 23 January 2023. (2) Add Attachment 07 - Pre-Bid Meeting Attendance Roster (In Person) - 18 Jan 23 (3) Add Attachment 08 - Pre-Bid Meeting Virtual Attendance Roster - 18 Jan 23 (4) Add Attachment 09 - Site Visit Attendance Roster - 18 Jan 23 (5) Add Attachment 10 - ARCF Reach E Pre-Bid Meeting Presentation - 18 Jan 23////////////////////////////////////////////////////////////////////////////////////////////////////////////////////////////////////////*Update*The purpose of Amendment 0001 is to make the following changes: 1. Update Attachment 6 - Site Visit Information2. Update Section 00 21 13 - Instructions to Bidders////////////////////////////////////////////////////////////////////USACE SPK has a requirement for design-bid-build construction services to construct a seepage cutoff wall adjacent to the landward side of the existing levee of the ARCF Natomas Basin Reach E segment, located in Pleasant Grove, CA. The Natomas Basin Reach E segment is located along the southwest bank of the Pleasant Grove Creek Canal (PGCC). The PGCC is an artificial channel that trends generally south-southeast to north-northwest, collecting surface water draining from Pleasant Grove Creek and several other seasonal streams from the east. The surface water is directed north-northeast into the Natomas Cross Canal and eventually to the Sacramento River. Reach E currently extends 3.4 miles between Sankey Road north to Howsley Road. The typical levee cross section has a crown width of twenty (20) feet, an asphalt road used by local traffic, and landside and riverside slopes of 1 vertical to 3 horizontal (1V:3H). The levee height varies between five (5) and seventeen (17) feet along the reach. The requirement is anticipated to include construction of a seepage cutoff wall adjacent to the landward side of the existing levee, including soil bentonite (SB) open trench construction using native soil with bentonite and water. It is anticipated the project requirements will include construction of a landside patrol road along the entire length of Reach E, that includes access ramps at identified locations; excavation and replacement of five (5) culverts; excavation and replacement of five (5) existing metal gatewells; excavation and replacement of a manhole; removal and relocation of irrigation systems; borrow site excavation; performance of Storm Water Pollution Prevention Plan (SWPPP) documents and implementation; and Best Management Practices (BMPs) installation. It is estimated that construction of the potential requirement can be completed within two (2) construction seasons, or approximately six hundred and six (606) calendar days.

Update #4 ·

////////////////////////////////////////////////////////////////////The purpose of amendment 0003 is as follows:1. Add attachment 11 - ARCF Reach E Geotechnical Data Report.////////////////////////////////////////////////////////////////////////////////////////////////////////////////////////////////////////The purpose of Amendment 0002 is the following: (1) Change the date ProjNet will close for new inquiries from 1:00 PM (1300) Pacific Standard Time (PST), 22 January 2023, to 1:00 PM (1300) PST, 23 January 2023. (2) Add Attachment 07 - Pre-Bid Meeting Attendance Roster (In Person) - 18 Jan 23 (3) Add Attachment 08 - Pre-Bid Meeting Virtual Attendance Roster - 18 Jan 23 (4) Add Attachment 09 - Site Visit Attendance Roster - 18 Jan 23 (5) Add Attachment 10 - ARCF Reach E Pre-Bid Meeting Presentation - 18 Jan 23////////////////////////////////////////////////////////////////////////////////////////////////////////////////////////////////////////*Update*The purpose of Amendment 0001 is to make the following changes: 1. Update Attachment 6 - Site Visit Information2. Update Section 00 21 13 - Instructions to Bidders////////////////////////////////////////////////////////////////////USACE SPK has a requirement for design-bid-build construction services to construct a seepage cutoff wall adjacent to the landward side of the existing levee of the ARCF Natomas Basin Reach E segment, located in Pleasant Grove, CA. The Natomas Basin Reach E segment is located along the southwest bank of the Pleasant Grove Creek Canal (PGCC). The PGCC is an artificial channel that trends generally south-southeast to north-northwest, collecting surface water draining from Pleasant Grove Creek and several other seasonal streams from the east. The surface water is directed north-northeast into the Natomas Cross Canal and eventually to the Sacramento River. Reach E currently extends 3.4 miles between Sankey Road north to Howsley Road. The typical levee cross section has a crown width of twenty (20) feet, an asphalt road used by local traffic, and landside and riverside slopes of 1 vertical to 3 horizontal (1V:3H). The levee height varies between five (5) and seventeen (17) feet along the reach. The requirement is anticipated to include construction of a seepage cutoff wall adjacent to the landward side of the existing levee, including soil bentonite (SB) open trench construction using native soil with bentonite and water. It is anticipated the project requirements will include construction of a landside patrol road along the entire length of Reach E, that includes access ramps at identified locations; excavation and replacement of five (5) culverts; excavation and replacement of five (5) existing metal gatewells; excavation and replacement of a manhole; removal and relocation of irrigation systems; borrow site excavation; performance of Storm Water Pollution Prevention Plan (SWPPP) documents and implementation; and Best Management Practices (BMPs) installation. It is estimated that construction of the potential requirement can be completed within two (2) construction seasons, or approximately six hundred and six (606) calendar days.

Update #3 ·

////////////////////////////////////////////////////////////////////The purpose of Amendment 0002 is the following: (1) Change the date ProjNet will close for new inquiries from 1:00 PM (1300) Pacific Standard Time (PST), 22 January 2023, to 1:00 PM (1300) PST, 23 January 2023. (2) Add Attachment 07 - Pre-Bid Meeting Attendance Roster (In Person) - 18 Jan 23 (3) Add Attachment 08 - Pre-Bid Meeting Virtual Attendance Roster - 18 Jan 23 (4) Add Attachment 09 - Site Visit Attendance Roster - 18 Jan 23 (5) Add Attachment 10 - ARCF Reach E Pre-Bid Meeting Presentation - 18 Jan 23////////////////////////////////////////////////////////////////////////////////////////////////////////////////////////////////////////*Update*The purpose of Amendment 0001 is to make the following changes: 1. Update Attachment 6 - Site Visit Information2. Update Section 00 21 13 - Instructions to Bidders////////////////////////////////////////////////////////////////////USACE SPK has a requirement for design-bid-build construction services to construct a seepage cutoff wall adjacent to the landward side of the existing levee of the ARCF Natomas Basin Reach E segment, located in Pleasant Grove, CA. The Natomas Basin Reach E segment is located along the southwest bank of the Pleasant Grove Creek Canal (PGCC). The PGCC is an artificial channel that trends generally south-southeast to north-northwest, collecting surface water draining from Pleasant Grove Creek and several other seasonal streams from the east. The surface water is directed north-northeast into the Natomas Cross Canal and eventually to the Sacramento River. Reach E currently extends 3.4 miles between Sankey Road north to Howsley Road. The typical levee cross section has a crown width of twenty (20) feet, an asphalt road used by local traffic, and landside and riverside slopes of 1 vertical to 3 horizontal (1V:3H). The levee height varies between five (5) and seventeen (17) feet along the reach. The requirement is anticipated to include construction of a seepage cutoff wall adjacent to the landward side of the existing levee, including soil bentonite (SB) open trench construction using native soil with bentonite and water. It is anticipated the project requirements will include construction of a landside patrol road along the entire length of Reach E, that includes access ramps at identified locations; excavation and replacement of five (5) culverts; excavation and replacement of five (5) existing metal gatewells; excavation and replacement of a manhole; removal and relocation of irrigation systems; borrow site excavation; performance of Storm Water Pollution Prevention Plan (SWPPP) documents and implementation; and Best Management Practices (BMPs) installation. It is estimated that construction of the potential requirement can be completed within two (2) construction seasons, or approximately six hundred and six (606) calendar days.

Update #2 ·

////////////////////////////////////////////////////////////////////*Update*The purpose of Amendment 0001 is to make the following changes: 1. Update Attachment 6 - Site Visit Information2. Update Section 00 21 13 - Instructions to Bidders////////////////////////////////////////////////////////////////////USACE SPK has a requirement for design-bid-build construction services to construct a seepage cutoff wall adjacent to the landward side of the existing levee of the ARCF Natomas Basin Reach E segment, located in Pleasant Grove, CA. The Natomas Basin Reach E segment is located along the southwest bank of the Pleasant Grove Creek Canal (PGCC). The PGCC is an artificial channel that trends generally south-southeast to north-northwest, collecting surface water draining from Pleasant Grove Creek and several other seasonal streams from the east. The surface water is directed north-northeast into the Natomas Cross Canal and eventually to the Sacramento River. Reach E currently extends 3.4 miles between Sankey Road north to Howsley Road. The typical levee cross section has a crown width of twenty (20) feet, an asphalt road used by local traffic, and landside and riverside slopes of 1 vertical to 3 horizontal (1V:3H). The levee height varies between five (5) and seventeen (17) feet along the reach. The requirement is anticipated to include construction of a seepage cutoff wall adjacent to the landward side of the existing levee, including soil bentonite (SB) open trench construction using native soil with bentonite and water. It is anticipated the project requirements will include construction of a landside patrol road along the entire length of Reach E, that includes access ramps at identified locations; excavation and replacement of five (5) culverts; excavation and replacement of five (5) existing metal gatewells; excavation and replacement of a manhole; removal and relocation of irrigation systems; borrow site excavation; performance of Storm Water Pollution Prevention Plan (SWPPP) documents and implementation; and Best Management Practices (BMPs) installation. It is estimated that construction of the potential requirement can be completed within two (2) construction seasons, or approximately six hundred and six (606) calendar days.

Update #1 ·

USACE SPK has a requirement for design-bid-build construction services to construct a seepage cutoff wall adjacent to the landward side of the existing levee of the ARCF Natomas Basin Reach E segment, located in Pleasant Grove, CA.The Natomas Basin Reach E segment is located along the southwest bank of the Pleasant Grove Creek Canal (PGCC). The PGCC is an artificial channel that trends generally south-southeast to north-northwest, collecting surface water draining from Pleasant Grove Creek andseveral other seasonal streams from the east. The surface water is directed north-northeast into the Natomas Cross Canal and eventually to the Sacramento River. Reach E currently extends 3.4 miles between Sankey Road north to Howsley Road. The typical levee cross section has a crown width of twenty (20) feet, an asphalt road used by local traffic, and landside and riverside slopes of 1 vertical to 3 horizontal (1V:3H). The levee height varies between five (5) and seventeen (17) feet along the reach. The requirement is anticipated to include construction of a seepage cutoff wall adjacent to the landward side of the existing levee, including soil bentonite (SB) open trench construction using native soil with bentonite and water. It is anticipated the project requirements will include construction of a landside patrol road along the entire length of Reach E, that includes access ramps at identified locations; excavation and replacement of five (5) culverts; excavation and replacement of five (5) existing metal gatewells; excavation and replacement of a manhole; removal and relocation of irrigation systems; borrow site excavation; performance of Storm Water Pollution Prevention Plan (SWPPP) documents and implementation; and Best Management Practices (BMPs) installation. It is estimated that construction of the potential requirement can be completed within two (2) construction seasons, or approximately six hundred and six (606) calendar days.

Attachments

Files attached to this notice, newest first
File Type Posted
Bid Abstract - ARCF Natomas Reach E (W9123823B0011).pdf PDF

Notice history

Notices posted for this opportunity, newest first
Notice Type Posted
USACE SPK DBB Construction - ARCF Natomas Reach E - Sutter County, CA Award Award Notice
USACE SPK DBB Construction - ARCF Natomas Reach E - Sutter County, CA This notice · Latest solicitation Solicitation
USACE SPK DBB Construction - ARCF Natomas Reach E - Sutter County, CA Pre-Solicitation
USACE SPK DBB Construction - ARCF Natomas Reach E - Sutter County, CA Original Pre-Solicitation

On GovTribe

Work this opportunity on GovTribe

  • Track it in your pipeline
  • Find teaming partners
  • Similar opportunities
  • Ask GovTribe AI about this opportunity