USACE Sabine-Neches Waterway Channel Improvement Project, Port Arthur Canal, Taylor's Bayou, Pipeline Dredging in
Closed Pre-Solicitation Posted
- Solicitation number
- W912HY25X12M6
- Agency
-
ENDIST Galveston
US Army Corps of Engineers, Department of Defense
- Responses due
- Set-aside
- No set-aside
Opportunity facts
- NAICS code
- 237990 Other Heavy and Civil Engineering Construction
- PSC
- Y1KB Construction Of Canals
- Place of performance
- Port Arthur, Texas 77642, United States
Notice details come from SAM.gov. Updated .
About this opportunity
The U.S. Army Corps of Engineers, Galveston District is seeking information from industry regarding their capabilities to perform the Sabine-Neches Waterway Channel Improvement Project, which includes pipeline dredging of approximately 6 million cubic yards and construction of a 1,400 linear foot sheet pile wall in the Port Arthur Canal and Taylor's Bayou area of Jefferson County, Texas. Contractors must demonstrate experience in deep draft navigation channel dredging, capable of excavating 26,000 cubic yards per day. The estimated contract value is between $100 million and $250 million, with the solicitation anticipated to be issued in November 2025, proposals due in December 2025, and award in June 2026. Interested firms must respond to this Sources Sought notice by December 16, 2024.
This opportunity is not set-aside for any specific business size or type. The NAICS code is 237990 - Other Heavy and Civil Engineering Construction, and the PSC is Y1KB - Construction Of Canals. No potential incumbents or current contractors are named, and the government has not provided a specific budget range for this project.
Notice text
Contractor should demonstrate construction experience as a prime contractor for Pipeline Dredging, Deep Draft Navigation Channels. Contractor should demonstrate experience in excavating 26,000 Cubic Yards (CYs) per day utilizing a Pipeline Dredge on a Deep Draft Navigation Dredging requirement. The Estimated Number of CYs to be removed for this requirement is Six (6) Million.
In addition to the dredging requirements, this project will also require a Sheet Pile Wall that will need to be constructed along the channel. The Estimated Linear Feet (LF) for this wall is 1,400.
Sources Sought notice is attached for further details
Files
| File | Type | Posted |
|---|---|---|
| Sources Sought Synopsis_SNWW__C7 _Port Arthur Canal.pdf |
Similar open opportunities
On GovTribe
Work this opportunity
- Track it in your pipeline
- Find teaming partners
- Similar opportunities
- Ask GovTribe AI about this opportunity