TD-66 CHILKAT PCB Remediation Removal and Disposal

Closed Solicitation Posted

This opportunity was awarded. See the award notice from .

Solicitation number
6991PE22Q000008
Agency
Responses due
Set-aside
Total Small Business

Opportunity facts

NAICS code
562910 Remediation Services
Place of performance
Benicia, California 94510, United States

Notice details come from SAM.gov. Updated .

Notice text

3 versions

Update #3 · Latest ·

The Suisun Bay Reserve Fleet (SBRF) has a requirement to conduct a hazardous material survey aboard the vessel to determine locations and quantities of hazardous materials/hazardous waste to be removed, including polychlorinated biphenyls (PCB).

The CHILKAT (TD-66) is an ex-U.S. Navy, Medium Harbor Tug:

  • Length, overall:  100 feet
  • Breadth, molded:  28 feet
  • Depth, molded:  14 feet, 3 inches.
  • Draft, light:  9 feet, 7 inches
  • Hull Number:  TD-66 (ex-YTM-773)
  • Construction:  Steel
  • Built:  1946, by Commercial Iron Works, Portland, OR
  • Displacement:  260 LT
  • Propulsion:  Single Screw
  • Main Engine(s):  Enterprise J-Series, 1250 HP.  Hours unknown since last overhaul.
  • Reduction Gear:  Morse Chain Marine Transmission
  • Exhaust:  Dry Stack
  • Auxiliaries:  Generators, (2) Detroit 6-71 series diesel engines driving General Electric 220VDC 60KW generators, (1) Electric Driven Fire Pump, 250 GPM, (2) Worthington Air Compressors

PCBs may be found in electrical wiring, ventilation ducting gasket materials, rubber gaskets, adhesives, thermal insulation materials, transformers, oil and grease, fluorescent light ballasts, capacitors, tapes, and coatings.

The period of performance is forty-five (45) days after arrival to the Shipyard.

Because this craft is not considered deep-seaworthy, all work must be performed on the vessel in the San Francisco Bay area, such area to include the up-river areas of Sacramento and Stockton.

This solicitation has been amended to extend the due date to 09AUG22.

Update #2 ·

The Suisun Bay Reserve Fleet (SBRF) has a requirement to conduct a hazardous material survey aboard the vessel to determine locations and quantities of hazardous materials/hazardous waste to be removed, including polychlorinated biphenyls (PCB).

The CHILKAT (TD-66) is an ex-U.S. Navy, Medium Harbor Tug:

  • Length, overall:  100 feet
  • Breadth, molded:  28 feet
  • Depth, molded:  14 feet, 3 inches.
  • Draft, light:  9 feet, 7 inches
  • Hull Number:  TD-66 (ex-YTM-773)
  • Construction:  Steel
  • Built:  1946, by Commercial Iron Works, Portland, OR
  • Displacement:  260 LT
  • Propulsion:  Single Screw
  • Main Engine(s):  Enterprise J-Series, 1250 HP.  Hours unknown since last overhaul.
  • Reduction Gear:  Morse Chain Marine Transmission
  • Exhaust:  Dry Stack
  • Auxiliaries:  Generators, (2) Detroit 6-71 series diesel engines driving General Electric 220VDC 60KW generators, (1) Electric Driven Fire Pump, 250 GPM, (2) Worthington Air Compressors

PCBs may be found in electrical wiring, ventilation ducting gasket materials, rubber gaskets, adhesives, thermal insulation materials, transformers, oil and grease, fluorescent light ballasts, capacitors, tapes, and coatings.

The period of performance is forty-five (45) days after arrival to the Shipyard.

Because this craft is not considered deep-seaworthy, all work must be performed on the vessel in the San Francisco Bay area, such area to include the up-river areas of Sacramento and Stockton.

This solicitation has been amended to extend the due date to 05AUG22.

Update #1 ·

The Suisun Bay Reserve Fleet (SBRF) has a requirement to conduct a hazardous material survey aboard the vessel to determine locations and quantities of hazardous materials/hazardous waste to be removed, including polychlorinated biphenyls (PCB).

The CHILKAT (TD-66) is an ex-U.S. Navy, Medium Harbor Tug:

  • Length, overall:  100 feet
  • Breadth, molded:  28 feet
  • Depth, molded:  14 feet, 3 inches.
  • Draft, light:  9 feet, 7 inches
  • Hull Number:  TD-66 (ex-YTM-773)
  • Construction:  Steel
  • Built:  1946, by Commercial Iron Works, Portland, OR
  • Displacement:  260 LT
  • Propulsion:  Single Screw
  • Main Engine(s):  Enterprise J-Series, 1250 HP.  Hours unknown since last overhaul.
  • Reduction Gear:  Morse Chain Marine Transmission
  • Exhaust:  Dry Stack
  • Auxiliaries:  Generators, (2) Detroit 6-71 series diesel engines driving General Electric 220VDC 60KW generators, (1) Electric Driven Fire Pump, 250 GPM, (2) Worthington Air Compressors

PCBs may be found in electrical wiring, ventilation ducting gasket materials, rubber gaskets, adhesives, thermal insulation materials, transformers, oil and grease, fluorescent light ballasts, capacitors, tapes, and coatings.

The period of performance is forty-five (45) days after arrival to the Shipyard.

Because this craft is not considered deep-seaworthy, all work must be performed on the vessel in the San Francisco Bay area, such area to include the up-river areas of Sacramento and Stockton.

Files

File Type Posted
6991PE22Q000008.pdf PDF

Notice history

Notice Type Posted
TD-66 CHILKAT PCB Remediation Removal and Disposal Award Award Award Notice
This notice Latest solicitation Solicitation

On GovTribe

Work this opportunity

  • Track it in your pipeline
  • Find teaming partners
  • Similar opportunities
  • Ask GovTribe AI about this opportunity

GovTribe for Federal Contractors