Substation maintenance

Closed Solicitation Posted

Solicitation number
000HCCA16-2017-12547
Agency
Responses due
Set-aside
Total Small Business

Opportunity facts

NAICS code
423690 Other Electronic Parts and Equipment Merchant Wholesalers
PSC
Not on record

Notice details come from SAM.gov. Updated .

Notice text

3 versions

Update #3 · Latest ·

2. I see the work is to be performed on weeknights. What time can we start? Can we work from 5 pm to 1 to 3 am? Also, do you all have lighting towers or should we furnish this?
Answer: The work will begin at 5:00 pm. The facility has to be up and running by 5:00 am. The panels that take care of the animal quarters will have to be scheduled with veterinarian and manager. We do not supply any light towers. We have emergency generators that supply lighting in most areas.

Update #2 ·

Question and Answer:

1. Do you all need the full testing done on the liquid filled transformers? Do you all want to Doble test the transformer?

Answer: The tests that are to be performed on the transformers are listed under 2.0 GENERAL REQUIREMENTS titled Transformers: Liquid-filled: All voltages Visual and Mechanical Inspection, all the items that are listed below that title will be performed if it applies to a particular transformer. We expect recommendations after all the inspections are made in this statement of work.

Update #1 ·

Title: Substation Maintenance
The Centers for Disease Control and Prevention (CDC) and the National Institute of Occupational Safety and Health (NIOSH), Morgantown, WV intends to award a sole source firm fixed price purchase order (if funds are available) to The Hite Company, PO Box 1754, Altoona, PA 16603-1754 for Electrical Substation Maintenance at the NIOSH Facility in Morgantown, WV.
CLIN 0001:
Substation Maintenance

Preventative Maintenance and testing on the CDC/NIOSH Morgantown site H-Bldg. and L-Bldg. main electrical substation systems consisting of (15) square D type D circuit breakers in Unit Substation
B-USSHV1 and (10) square type DS circuit breakers in Unit Substation B-USSLV01.


STATEMENT OF WORK
FOR
ELECTRICAL SUBSTATION MAINTENANCE
AT
NIOSH MORGANTOWN, WV.


1.0 INTRODUCTION
A) The CDC/NIOSH facility requires services of a Contractor performing preventive maintenance and testing on the L-building and H-building main electrical substation systems.


B) The maintenance and testing will be performed on weeknights and Saturdays with minimum interruption to the building operation and will be scheduled with the Building Manager.


2.0 GENERAL REQUIREMENTS


A) The contractor shall provide qualified technicians that can perform preventive maintenance on the electrical substation systems.


B) Electrical equipment that will have preventive maintenance and the testing that will be performed are as follows:


MAIN ELECTRIC ROOM
• 1 - Unit Substation - B-USSLV01, 480V Square D PZIII
• 15 - Breaker - Square D Type DS, Digitrip RMS 810 D trip Units
• 2 - Transformer - Oil Filled, 2500 KVA, Square D
• 2 - MV Fused Switch - Square D Type HVL
• 1 - Unit Substation B-USSHV01, 208V Square D PZIII
• 10 Breaker - Square D Type DS, Digitrip RMS 810 D trip Units
• 2 Transformer - Oil filled, 2500 KVA, Square D
• 2 - MV Fused Switch - Square D Type HVL


BUILDING H
• 1 - Breaker - Outdoor Enclosed Main MSB 1, 480V Westinghouse DS 416 Breaker, Amptector I-A Model, LSG
• 1 - Breaker - Outdoor Enclosed Main MSB 2, 480V Westinghouse DS 416 Breaker, Amptector I-A Model, LSG
• 1 - Switchboard - Main Gear Room, 480V Square D PZIII
• 6 Breaker - Square D Type DS Circuit Breakers, Digitrip RMS 510 trip Unit



SWITCHBOARD ASSEMBLIES: LOW VOLTAGE
• Visual and Mechanical Inspection.
• Document equipment nameplate data.
• Inspect physical, electrical, and mechanical condition of switchboard/switchgear and all components.
• Confirm correct application of lubricants at manufacturer's recommended locations.
• Verify tightness of accessible bolted electrical connections by calibrated torque-wrench.
• Confirm correct operation and sequencing of electrical and mechanical interlock systems.
• Inspect all mechanical indicating devices for correct operation.
• Verify that filters are in place and/or vents are clear.


ELECTRICAL TESTS
• Perform insulation-resistance tests on each bus section, phase-to-phase and phase-to-ground.
• Verify operation of switchgear/switchboard heaters.


CIRCUIT BREAKERS: LOW-VOLTAGE POWER (ANSI/IEEE C37.13)
VISUAL AND MECHANICAL INSPECTION
• Document equipment nameplate data on test report.
• Inspect physical and mechanical condition.
• Confirm correct application of lubricants at manufacturer's recommended locations.
• Inspect anchorage, alignment, and grounding.
• Inspect arc chutes.
• Verify that all maintenance devices are available for servicing and operating the breaker.
• Perform all mechanical operator and contact alignment tests on both the breaker and its operating mechanism.
• Verify tightness of accessible bolted bus connections by calibrated torque-wrench method.
• Check cell fit and element alignment.
• Check racking mechanism.


ELECTRICAL TESTS
• Perform a contact-resistance test in accordance with manufacturers recommended procedure.
• Perform an insulation-resistance test at 1000 volts dc from pole-to-pole and from each pole-to-ground with breaker closed and across open contacts of each phase.
• Determine the following using secondary current injection:
o Minimum pickup current by
o Long-time delay
o Short-time pickup and delay
o Ground-fault pickup and delay
o Instantaneous pickup value
• Activate auxiliary protective devices such as under voltage relays, to insure operation of shunt trip devices.
• Check the operation of electrically operated breakers in their cubicles.
• Verify correct operation of any auxiliary features such as trip and pickup indicator, electrical close and
trip operation, trip-free, and antipump function.
• Check electric charging mechanism, if applicable.


AIR SWITCHES: MEDIUM-VOLTAGE, METAL-ENCLOSED
VISUAL AND MECHANICAL INSPECTION
• Document equipment nameplate data on test report.
• Inspect physical and mechanical condition.
• Confirm correct application of lubricants at manufacturer's recommended locations.
• Verify appropriate anchorage and required area clearances.
• Verify appropriate equipment grounding.
• Verify correct blade alignment, blade penetration, travel stops, and mechanical operation.
• Verify tightness of accessible bolted electrical connections by calibrated torque-wrench method.
• Check all interlocking systems for correct operation and sequencing, and key distribution, if applicable.
• Verify correct phase-barrier materials and installation.
• Inspect all indicating and control devices for correct operation.


ELECTRICAL TESTS
• Perform insulation-resistance tests on each pole, phase-to-phase and phase-to-ground with switch closed and across each open pole for one minute.
• Verify heater operation.
• Perform a contact-resistance test for Square D HVL/cc and Visi-Vac devices.


TRANSFORMERS: LIQUID-FILLED: ALL VOLTAGES
VISUAL AND MECHANICAL INSPECTION
• Document equipment nameplate data on test report.
• Inspect physical and mechanical condition.
• Verify that alarm, control, and trip settings on temperature indicators are as specified.
• Verify that cooling fans and pumps operate correctly and that fan and pump motors have correct overcurrent protection.
• Verify operation of all alarm, control, and trip circuits from temperature and level indicators, pressure relief device, and fault pressure relay.
• Verify tightness of accessible bolted electrical connections by calibrated torque-wrench.
• Verify correct liquid level in all tanks and bushings.
• Verify that positive pressure is maintained on nitrogen-blanketed transformers.
• Verify correct equipment grounding.


ELECTRICAL TESTS
• Perform insulation-resistance tests, winding-to-winding and each winding-to-ground.
• Perform a turns-ratio test on all no-load tap-changer positions and all load tap-changer positions. Verify that tap setting is as specified.
• Remove a sample of insulating liquid in accordance with ASTM D-923 and be test for the following:
o Dielectric breakdown voltage: ASTM D-877 and/or ASTM D-1816.
o Acid neutralization number: ASTM D-974.
o Specific gravity: ASTM D-1298.
o Interfacial tension: ASTM D-971 or ASTM D-2285.
o Color: ASTM D-1500.
o Visual Condition: ASTM D-1524.
o Parts per million water: ASTM D-1533. Required on 25 kV or higher voltages and on all silicone-filled units.



C) The Contractor shall carry out activities in a manner that will allow access to the facilities at all times

D) The Contractor shall perform work in a manner that will allow conduct of business of
The CDC/NIOSH without discomfort to the occupants as much as possible. Work will be performed on scheduled weeknights after 6:00 PM and scheduled Saturdays excluding holidays.


E) The Contractor shall perform work in a diligent manner and achieve completion within the specified performance period.



3.0 CONTRACT ADMINISTRATION


• The Contractor shall not perform work that is outside the SOW unless directed in writing by the Contracting Officer (COR). Any work done by the Contractor outside the SOW without direction from the COR will be at the Contractor's own risk and at no cost to CDC/NIOSH.


• The COR shall provide a Notice to Proceed (NTP) to begin performance of work after the contract award.


• Facility Manager at CDC/NIOSH shall be designated as Contracting Officer's Representative (COR) for administration of this contract. The COR shall coordinate schedule for each phase, approve technical submittals, inspect work, monitor Progress, accept completed work, review invoices, review change orders, and issue/receive Government Furnished Items. The COR has the authority to direct the Contractor to stop performance of work if unsafe work conditions are observed.


4.0 RESPONSIBILITY OF THE CONTRACTOR


The Contractor shall keep the Phoenix lab control systems in safe working order.


a) Safety - The Contractor is required that all the technical personnel sent to the NIOSH Morgantown facility utilize safe work practices, and shall conduct their work safely while providing this service. Contractors shall comply with all OSHA regulations and facility specific safety protocols as informed by the COR. The Company shall provide technicians trained to utilize personal protective equipment (PPE) as necessary, and comply with confined space, electrical lock-out tag-out, fall protection and other safety protocols as necessary. The Contractor shall submit a Health & Safety Plan upon award of the contract summarizing their safety procedures and training to the Contracting Officer's Representative. This plan shall be provided to the NIOSH Environmental Health & Safety (EH&S) Department for compliance review and must meet the approval of EH&S. The Contractor shall be required to clarify any discrepancies in their Health & Safety Plan to the satisfaction of EH&S.


b) The contractor shall prepare and implement a safety management plan specific to the SOW based on hazards analyses of the activities. A copy of the safety management plan shall be provided to the COR for reference. The Contractor shall promptly report all mishaps / accidents at site to the COR.


c) The Contractor shall prepare and institute a quality management plan specific to the SOW. The plan shall describe the standard operating procedures for technical approvals, procurement actions, site inspections, testing and corrective actions. A copy of the quality management plan shall be provided to the COR for reference.


d) The Contractor shall comply with security requirements and be responsible for conduct of employees and subcontractors at work site.


e) The Contractor shall be liable for the damages caused by the Contractor's negligent performance of any of the services furnished under this contract.


5.0 SECURITY REQUIREMENTS


a) Facility Access - Contractor personnel will be required to comply with all NIOSH Morgantown security protocols in effect. Facility access, personnel identification badges and parking tags must be coordinated through the security office. The Contractor shall be required to sign-in and out with NIOSH Security at the L-Building Main Entrance. All Contractor personnel are required to present for verification, valid federal identification for the facility visitor sign-in procedure. All Contractor vehicles are subject to search by CDC Security. Vehicles containing prohibited items will not be allowed to enter the NIOSH Morgantown site and the Contractor shall be directed to leave and shall schedule a return site visit as necessary to perform the service.



6.0 PAYMENTS


a) This is a fixed priced contract. The Contractor shall submit payment request on the basis of work completed. The COR will review and recommend the invoice for payment.


b) The Contractor shall specifically identify the last invoice as "Final Invoice." The final invoice shall include the remaining payment claimed to be due under the base contract and all modifications issued, if any. The final invoice shall also have the Contractor's Release of Claims Certificate and the Workmanship Warranty attached.


This contract action is for a services for which the government intends to solicit and negotiate with only one source under the authority of FAR 13.106-1(b) (SAP) and 41 U.S.C 3304(a) (1). Interested persons may identify their interest and capability to respond to the requirement or submit proposals.
The notice of intent is not a request for competitive quotations; however, all quotations/responses received within (15) days of the issuance of this notice will be considered by the Government. A determination by the Government not to compete this proposed contract based upon responses to this notice is solely within the discretion of the Government. Information received will normally be considered solely for the purpose of determining whether to conduct a competitive procurement. Any quotation/response should be e-mailed to purchasing agent Rebecca Mullenax at rmullenax@cdc.gov by COB on June 19, 2017.

On GovTribe

Work this opportunity

  • Track it in your pipeline
  • Find teaming partners
  • Similar opportunities
  • Ask GovTribe AI about this opportunity

GovTribe for Federal Contractors