Stoney Creek Campground Vault Toilets Site Work

Award Notice Posted

Solicitation number
129JGP19Q0079
Agency
Awarded
to Shipley Construction & Plumbing
Set-aside
Total Small Business

Opportunity facts

Contract number
129JGP19C0042 Federal contract award
NAICS code
237310 Highway, Street, and Bridge Construction
PSC
Not on record
Place of performance
Stoney Creek Campground on the Hume Lake Ranger District of the Sequoia National Forest and Giant Sequoia National Monument. Stone Creek Campground, California 93621, United States

Notice details come from SAM.gov. Updated .

Notice text

3 versions

Update #3 · Latest ·

Awarded Vendors: Shipley Construction and Plumbing. Contract Award Dollar Amount: $58,000.00. Contract Award Date: 2019-07-01.

Update #2 ·

This is the solicitation notice for the Stoney Creek Campground Vault Toilets Site Work. The work includes but is not limited to the following major items:
Stoney Creek Campground:
NOTE: The existing flush toilet buildings will be replaced with vault toilets by another contract separate from this contract. This contract will only construct site work after the new toilets are installed.
(1) Demolition of three septic tanks at locations of current flush toilet buildings. (2)Site preparation including minor site grading and compaction in preparation for placement of concrete and aggregate base for sidewalks and parking. (3) Construction of ADA accessible concrete sidewalks around six (6) new double vault toilet buildings installed in three pairs of two toilets each at three locations in the campground. (4)Construction of one aggregate surfaced ADA accessible parking space adjacent to each pair of new vault toilet buildings (total of three parking spaces) including signs.
This solicitation is being issued using Simplified Acquisition Procedures. A Government led site visit has not been scheduled for this project. Offerors are urged and expected to inspect the site where services are to be performed.

Update #1 ·

This is the pre-solicitation notice for the Stoney Creek Campground Vault Toilets Site Work. The work includes but is not limited to the following major items:
Stoney Creek Campground:
NOTE: The existing flush toilet buildings will be replaced with vault toilets by another contract separate from this contract. This contract will only construct site work after the new toilets are installed.
(1) Demolition of three septic tanks at locations of current flush toilet buildings. (2)Site preparation including minor site grading and compaction in preparation for placement of concrete and aggregate base for sidewalks and parking. (3) Construction of ADA accessible concrete sidewalks around six (6) new double vault toilet buildings installed in three pairs of two toilets each at three locations in the campground. (4)Construction of one aggregate surfaced ADA accessible parking space adjacent to each pair of new vault toilet buildings (total of three parking spaces) including signs.
This solicitation is being issued using Simplified Acquisition Procedures. The solicitation for this project will be posted on or about the 31st of May 2019..

Files