Schiller Park Detention Pond and Storm Sewer Installation Project, Schiller Park, Illinois (USACE ACQUISITION)
Closed Pre-Solicitation Posted
This opportunity was awarded. See the award notice from , or the latest solicitation from .
- Solicitation number
- W912P622B0010
- Agency
-
ENDIST Chicago
US Army Corps of Engineers, Department of Defense
- Responses due
- Set-aside
- Total Small Business
Opportunity facts
- NAICS code
- 237110 Water and Sewer Line and Related Structures Construction
- Place of performance
- Schiller Park, Illinois 60176, United States
Notice details come from SAM.gov. Updated .
About this opportunity
This pre-solicitation notice is issued by the United States Army Corps of Engineers Chicago District to inform potential contractors of an upcoming Invitation for Bid for the Schiller Park Detention Pond and Storm Sewer Installation Project in Schiller Park, Illinois. The project involves installing approximately 1200 linear feet of storm sewer and six manholes at one location, connecting to an existing line, as well as creating a 1.5 million gallon detention pond. At a second location, the project extends an existing storm sewer by approximately 2500 linear feet to prevent flooding. Competition is reserved for small business concerns only under NAICS 237110 with a size standard of $39.5 million. Bids are due on or about September 26th, 2022.
The acquisition is set aside exclusively for small business concerns. The estimated value is between $500,000 and $1 million. Key details include installing 1200 linear feet of storm sewer and six manholes at the first location, connecting to an existing line and creating a 1.5 million gallon detention pond. An additional 2500 linear feet of storm sewer will be installed at the second location along with 16 manholes and 19 catch basins to prevent flooding. All solicitation documents will be available for download on SAM.gov on or around August 25th, with bids due on or around September 26th, 2022.
Notice text
This Pre-Solicitation Notice is being issued by the United States Army Corps of Engineers - Chicago District to inform interested/potential contractors of the District's imminent issue of an Invitation for Bid Package for its construction project entitled, "Schiller Park Detention Pond and Storm Sewer Installation - Section 219, Schiller Park, IL. (USACE Acquisition)."
PROJECT INFORMATION:
Under the contract, the contractor will provide service to install a detention pond and storm sewers at two locations, on and around Seymour Avenue and Soreng Avenue.
At the first location, approximately 1200 linear feet of storm sewer and six manholes is planned from the intersection of Scott Street and Seymour Avenue, eastward through Shelton Field, to the intersection of Soreng Avenue and 25th Avenue where it would connect with the existing storm sewer line. Sewer installation would also occur from the intersection of Soreng Avenue and Emerson Drive southward to Garden Court. Additionally, a vacant parcel of land owned by the Village of Schiller Park would be used to create an approximately 1.5-million-gallon storm water detention pond connected to this new storm sewer installation.
At the second location, the existing storm sewer on Seymour Avenue would be extended northward to the 4000 and 4100 blocks of Wesley Terrace, Grace Street, Kolze Avenue, and Gremley Terrace to expand the capacity of the storm sewer system and prevent flooding in this area. This extension would consist of approximately 2500 linear feet of 24-inch pipe for the main line, 380 linear feet of 12-inch pipe for the drainage laterals, 16 manholes, and 19 catch basins.
CONTRACTING OFFICE: USACE Chicago District, 231 SOUTH LaSALLE STREET, SUITE 1500, Chicago, IL 60604
ACQUISITION INFORMATION: Competition for this acquisition is RESERVED EXCLUSIVELY for Small Business Concerns. The North American Industry System Classification Code is 237110, with a small business size standard in dollars of $39.5 Million. The magnitude of cost for construction is estimated between $500,000.00 and $1,000,000.00.
The Solicitation (Invitation for Bids – “IFB”) will be downloadable from the INTERNET ONLY. The project specification files are Portable Document Format (PDF) files and can be viewed, navigated, or printed using Adobe Acrobat Reader. Once the package is released into advertisement at this website ("SAM.gov"), interested bidders may download the full package, includes: specification and drawings files
The Solicitation package is planned for advertisement on or about August 25, 2022, with bids due on or about September 26, 2022.
IN THE CASE OF A DISCREPANCY BETWEEN THE DATES PUBLISHED IN THIS NOTICE AND THOSE CALLED OUT IN THE IFB DOCUMENT, THE DATES IN THE IFB DOCUMENT OVERRIDES THOSE PUBLISHED HEREIN THIS NOTICE; THIS IS RELATIVE TO THE IFB ISSUANCE DATE AND THE DUE DATE FOR BIDS.
IMPORTANT POLICY: Bidders are REQUIRED to be registered in the System for Award Management (SAM) AT THE TIME ITS BID IS SUBMITTED to comply with the annual representations and certifications requirements. Registration can be completed free of charge at www.sam.gov. Request for solicitation packages made by telephone, fax or e-mail will not be honored. The Point of Contact for this acquisition is Mr. Casimir Brzozowiec at Casimir.Brzozowiec@USACE.Army.mil.
Please include Solicitation Number W912P622B0010 on all correspondence.
Notice history
| Notice | Type | Posted |
|---|---|---|
| Schiller Park IL Stormwater Improvements - Section 219 | Award Notice | |
| Schiller Park IL Stormwater Improvements - Section 219 | Solicitation | |
| This notice | Pre-Solicitation |
Similar open opportunities
On GovTribe
Work this opportunity
- Track it in your pipeline
- Find teaming partners
- Similar opportunities
- Ask GovTribe AI about this opportunity