Replacement of Fabric Roof and End Walls for Aluminum Framed Structure
Closed Solicitation Posted
- Solicitation number
- W91ZLK-22-Q-0001
- Agency
-
ACC Aberdeen Proving Ground
Army Contracting Command, Department of Defense
- Responses due
- Set-aside
- Total Small Business
Opportunity facts
- NAICS code
- 332311 Prefabricated Metal Building and Component Manufacturing
- PSC
- J083 Maint/Repair/Rebuild Of Equipment- Textiles, Leather, Furs, Apparel/Shoe Findings, Tents/Flags
- Place of performance
- Maryland 21010, United States
Notice details come from SAM.gov. Updated .
Notice text
2 versions
Update #2 · Latest ·
29 NOV 2021: CORRECTIONS
Firm Fixed Price (FFP) proposals MUST be signed, dated, and received by 10:00 a.m. EST, 02 December 2021
Questions and responses have been posted.
The contractor shall design, fabricate, and install new 22 oz. fabric panels for the roof and end walls of CCDC-CBC’s existing fabric walled aluminum framed structure. The structure is ~135’ long and has 10 ribs (9 bays). The roof section shall be made of one large membrane panel. The end wall has one penetration for the exhaust fan and is approximately 60 ft. wide and 30 ft. tall. The replacement fabric shall be the same material weight, type, and color as the rest of the structure. The replacement fabric shall include pockets at just above ground level to be used for applying down tension. The roof replacement shall be completed without the need to remove items stored inside.
Update #1 ·
The contractor shall design, fabricate, and install new 22 oz. fabric panels for the roof and end walls of CCDC-CBC’s existing fabric walled aluminum framed structure. The structure is ~135’ long and has 10 ribs (9 bays). The roof section shall be made of one large membrane panel. The end wall has one penetration for the exhaust fan and is approximately 60 ft. wide and 30 ft. tall. The replacement fabric shall be the same material weight, type, and color as the rest of the structure. The replacement fabric shall include pockets at just above ground level to be used for applying down tension. The roof replacement shall be completed without the need to remove items stored inside.