Replace Pacific East District Superintendent? s Office, Yokota AB, Japan
Closed Solicitation Posted
This opportunity was awarded. See the award notice from .
- Solicitation number
- W912HV22B0011
- Agency
-
ENDIST Japan
US Army Corps of Engineers, Department of Defense
- Responses due
- Set-aside
- No set-aside
Opportunity facts
- NAICS code
- 236220 Commercial and Institutional Building Construction
- PSC
- Y1AA Construction Of Office Buildings
Notice details come from SAM.gov. Updated .
About this opportunity
The U.S. Army Corps of Engineers Engineering District Japan seeks to construct a new District Superintendent's Office facility at Yokota Air Base in Japan. The solicitation requires the design and construction of a new office building to house administrative functions and staff. The facility must meet all applicable Department of Defense, Department of Defense Education Activity, and federal sustainability standards. Proposals were due by October 12, 2022 and evaluated based on price and technical factors, with the lowest priced bid from a technically acceptable offeror to be selected for award.
There was no set-aside designation for this procurement. The projected NAICS code is 2362 and PSC code S206. Two bids were received in response, with the lowest bid of 1,898,818,389 Yen submitted by Nippo Corporation, while the government estimate was 2,165,000,000 Yen. The new facility will be constructed at Yokota Air Base in Japan and include staff offices, conference rooms, storage, secure network equipment rooms, training facilities, and restrooms to fully support the administrative functions of the District Superintendent's Office.
Notice text
7 versions
Update #7 · Latest ·
12 October 2022 - Abstract of Bids has been attached to this announcement.
***********************************************************************************************
5 October 2022 - AM-0003 removes spare part requirement, Replace DSO, Yokota. Amendment can be downloaded from https://piee.eb.mil/sol/xhtml/unauth/search/oppMgmtLink.xhtml?solNo=W912HV22B0011
***********************************************************************************************
Visit 'https://piee.eb.mil/sol/xhtml/unauth/search/oppMgmtLink.xhtml?solNo=W912HV22B0011' to obtain more details.*
30 August 2022, Update
Description: This amendment 0002 of the solicitation incorporates updated versions of drawings and specs after reviewing RFI submissions. In addition, the bid due date is extended to 12 October 2022 at 14:00 JST. Please download all the updated files via PIEE. The amendment is in the end of the webpage.
Construct a District Superintendent?s Office (DSO) facility with functional areas containing staff private offices, staff open offices, conference rooms, storage, Secure Internet Protocol Router (SIPR) room, training room, training room kitchenette, logistics warehouse, production suite, information technology workbench, staff lounge, telecommunications rooms, restrooms, an entrance/reception area, and other required areas for a fully functional administrative office. Typical construction is anticipated to consist of shallow foundation systems, reinforced concrete and structural steel framing, and reinforced concrete bearing and shear-walls. Interior construction will consist of reinforced concrete interior bearing and shear-walls, gypsum wallboard partitions, and operable/movable partition walls. Construction also includes a stand-alone water pump facility for fire protection. Department of Defense (DoD) and Department of Defense Education Activity (DoDEA) principles for high performance and sustainable building requirements will be included in the design and construction of the project in accordance with federal laws and Executive Orders. Low Impact Development will be included in the design and construction of this project as appropriate. Anti-Terrorism/Force Protection (AT/FP) features will comply with AT/FP regulations, and physical security mitigation in accordance with DoD Minimum Anti-Terrorism Standards for Buildings and any Theater-specific requirements. Facilities will be designed to provide cyber security engineering and validation as specified in DoD Unified Facilities Criteria. Please read the entire solicitation and attachments for details.
Update #6 ·
5 October 2022 - AM-0003 removes spare part requirement, Replace DSO, Yokota. Amendment can be downloaded from https://piee.eb.mil/sol/xhtml/unauth/search/oppMgmtLink.xhtml?solNo=W912HV22B0011
***********************************************************************************************
Visit 'https://piee.eb.mil/sol/xhtml/unauth/search/oppMgmtLink.xhtml?solNo=W912HV22B0011' to obtain more details.*
30 August 2022, Update
Description: This amendment 0002 of the solicitation incorporates updated versions of drawings and specs after reviewing RFI submissions. In addition, the bid due date is extended to 12 October 2022 at 14:00 JST. Please download all the updated files via PIEE. The amendment is in the end of the webpage.
Construct a District Superintendent?s Office (DSO) facility with functional areas containing staff private offices, staff open offices, conference rooms, storage, Secure Internet Protocol Router (SIPR) room, training room, training room kitchenette, logistics warehouse, production suite, information technology workbench, staff lounge, telecommunications rooms, restrooms, an entrance/reception area, and other required areas for a fully functional administrative office. Typical construction is anticipated to consist of shallow foundation systems, reinforced concrete and structural steel framing, and reinforced concrete bearing and shear-walls. Interior construction will consist of reinforced concrete interior bearing and shear-walls, gypsum wallboard partitions, and operable/movable partition walls. Construction also includes a stand-alone water pump facility for fire protection. Department of Defense (DoD) and Department of Defense Education Activity (DoDEA) principles for high performance and sustainable building requirements will be included in the design and construction of the project in accordance with federal laws and Executive Orders. Low Impact Development will be included in the design and construction of this project as appropriate. Anti-Terrorism/Force Protection (AT/FP) features will comply with AT/FP regulations, and physical security mitigation in accordance with DoD Minimum Anti-Terrorism Standards for Buildings and any Theater-specific requirements. Facilities will be designed to provide cyber security engineering and validation as specified in DoD Unified Facilities Criteria. Please read the entire solicitation and attachments for details.
Update #5 ·
*Visit 'https://piee.eb.mil/sol/xhtml/unauth/search/oppMgmtLink.xhtml?solNo=W912HV22B0011' to obtain more details.*
30 August 30, 2022, Update
Discerption: This amendment 0002 of the solicitation incorporates updated versions of drawings and specs after reviewing RFI submissions. In addition, the bid due date is extended to 12 October 2022 at 14:00 JST. Please download all the updated files via PIEE. The amendment is in the end of the webpage.
Construct a District Superintendent?s Office (DSO) facility with functional areas containing staff private offices, staff open offices, conference rooms, storage, Secure Internet Protocol Router (SIPR) room, training room, training room kitchenette, logistics warehouse, production suite, information technology workbench, staff lounge, telecommunications rooms, restrooms, an entrance/reception area, and other required areas for a fully functional administrative office. Typical construction is anticipated to consist of shallow foundation systems, reinforced concrete and structural steel framing, and reinforced concrete bearing and shear-walls. Interior construction will consist of reinforced concrete interior bearing and shear-walls, gypsum wallboard partitions, and operable/movable partition walls. Construction also includes a stand-alone water pump facility for fire protection. Department of Defense (DoD) and Department of Defense Education Activity (DoDEA) principles for high performance and sustainable building requirements will be included in the design and construction of the project in accordance with federal laws and Executive Orders. Low Impact Development will be included in the design and construction of this project as appropriate. Anti-Terrorism/Force Protection (AT/FP) features will comply with AT/FP regulations, and physical security mitigation in accordance with DoD Minimum Anti-Terrorism Standards for Buildings and any Theater-specific requirements. Facilities will be designed to provide cyber security engineering and validation as specified in DoD Unified Facilities Criteria. Please read the entire solicitation and attachments for details.
Update #4 ·
The Request for Information (RFI) due date has changed from 7 July 2022, Japan Standard Time (JST), to 21 July 2022. 11:59 (midnight), JST. Please refer the attached PDF file for details. Solicitation and all attachments shall be downloaded from Procurement Integrated Enterprise Environment (PIEE) Solicitation Module https://piee.eb.mil/Construct a District Superintendent?s Office (DSO) facility with functional areas containing staff private offices, staff open offices, conference rooms, storage, Secure Internet Protocol Router (SIPR) room, training room, training room kitchenette, logistics warehouse, production suite, information technology workbench, staff lounge, telecommunications rooms, restrooms, an entrance/reception area, and other required areas for a fully functional administrative office. Typical construction is anticipated to consist of shallow foundation systems, reinforced concrete and structural steel framing, and reinforced concrete bearing and shear-walls. Interior construction will consist of reinforced concrete interior bearing and shear-walls, gypsum wallboard partitions, and operable/movable partition walls. Construction also includes a stand-alone water pump facility for fire protection.Department of Defense (DoD) and Department of Defense Education Activity (DoDEA) principles for high performance and sustainable building requirements will be included in the design and construction of the project in accordance with federal laws and Executive Orders. Low Impact Development will be included in the design and construction of this project as appropriate.Anti-Terrorism/Force Protection (AT/FP) features will comply with AT/FP regulations, and physical security mitigation in accordance with DoD Minimum Anti-Terrorism Standards for Buildings and any Theater-specific requirements.Facilities will be designed to provide cyber security engineering and validation as specified in DoD Unified Facilities Criteria.Please read the entire solicitation and attachments for details. *Visit 'https://piee.eb.mil/sol/xhtml/unauth/search/oppMgmtLink.xhtml?solNo=W912HV22B0011' to obtain more details.*
Update #3 ·
Solicitation and all attachments shall be downloaded from Procurement Integrated Enterprise Environment (PIEE) Solicitation Module https://piee.eb.mil/
*Visit 'https://piee.eb.mil/sol/xhtml/unauth/search/oppMgmtLink.xhtml?solNo=W912HV22B0011' to obtain more details.*
22 June 2022 update: The site visit attendees’ list has posted on PIEE.
21 June 2022 update: The pre-bid conference slides and attendees’ list have posted on PIEE.
Construct a District Superintendent's Office (DSO) facility with functional areas containing staff private offices, staff open offices, conference rooms, storage, Secure Internet Protocol Router (SIPR) room, training room, training room kitchenette, logistics warehouse, production suite, information technology workbench, staff lounge, telecommunications rooms, restrooms, an entrance/reception area, and other required areas for a fully functional administrative office. Typical construction is anticipated to consist of shallow foundation systems, reinforced concrete and structural steel framing, and reinforced concrete bearing and shear-walls. Interior construction will consist of reinforced concrete interior bearing and shear-walls, gypsum wallboard partitions, and operable/movable partition walls. Construction also includes a stand-alone water pump facility for fire protection.Department of Defense (DoD) and Department of Defense Education Activity (DoDEA) principles for high performance and sustainable building requirements will be included in the design and construction of the project in accordance with federal laws and Executive Orders. Low Impact Development will be included in the design and construction of this project as appropriate.Anti-Terrorism/Force Protection (AT/FP) features will comply with AT/FP regulations, and physical security mitigation in accordance with DoD Minimum Anti-Terrorism Standards for Buildings and any Theater-specific requirements.Facilities will be designed to provide cyber security engineering and validation as specified in DoD Unified Facilities Criteria.
Please read the entire solicitation and attachments for details.
Update #2 ·
Solicitation and all attachments shall be downloaded from Procurement Integrated Enterprise Environment (PIEE) Solicitation Module https://piee.eb.mil/
*Visit 'https://piee.eb.mil/sol/xhtml/unauth/search/oppMgmtLink.xhtml?solNo=W912HV22B0011' to obtain more details.*
21 June 2022 update: The pre-bid conference slides and attendees’ list have posted on PIEE.
Construct a District Superintendent's Office (DSO) facility with functional areas containing staff private offices, staff open offices, conference rooms, storage, Secure Internet Protocol Router (SIPR) room, training room, training room kitchenette, logistics warehouse, production suite, information technology workbench, staff lounge, telecommunications rooms, restrooms, an entrance/reception area, and other required areas for a fully functional administrative office. Typical construction is anticipated to consist of shallow foundation systems, reinforced concrete and structural steel framing, and reinforced concrete bearing and shear-walls. Interior construction will consist of reinforced concrete interior bearing and shear-walls, gypsum wallboard partitions, and operable/movable partition walls. Construction also includes a stand-alone water pump facility for fire protection.Department of Defense (DoD) and Department of Defense Education Activity (DoDEA) principles for high performance and sustainable building requirements will be included in the design and construction of the project in accordance with federal laws and Executive Orders. Low Impact Development will be included in the design and construction of this project as appropriate.Anti-Terrorism/Force Protection (AT/FP) features will comply with AT/FP regulations, and physical security mitigation in accordance with DoD Minimum Anti-Terrorism Standards for Buildings and any Theater-specific requirements.Facilities will be designed to provide cyber security engineering and validation as specified in DoD Unified Facilities Criteria.
Please read the entire solicitation and attachments for details.
Update #1 ·
Solicitation and all attachments shall be downloaded from Procurement Integrated Enterprise Environment (PIEE) Solicitation Module https://piee.eb.mil/
*Visit 'https://piee.eb.mil/sol/xhtml/unauth/search/oppMgmtLink.xhtml?solNo=W912HV22B0011' to obtain more details.*
Construct a District Superintendent's Office (DSO) facility with functional areas containing staff private offices, staff open offices, conference rooms, storage, Secure Internet Protocol Router (SIPR) room, training room, training room kitchenette, logistics warehouse, production suite, information technology workbench, staff lounge, telecommunications rooms, restrooms, an entrance/reception area, and other required areas for a fully functional administrative office. Typical construction is anticipated to consist of shallow foundation systems, reinforced concrete and structural steel framing, and reinforced concrete bearing and shear-walls. Interior construction will consist of reinforced concrete interior bearing and shear-walls, gypsum wallboard partitions, and operable/movable partition walls. Construction also includes a stand-alone water pump facility for fire protection.Department of Defense (DoD) and Department of Defense Education Activity (DoDEA) principles for high performance and sustainable building requirements will be included in the design and construction of the project in accordance with federal laws and Executive Orders. Low Impact Development will be included in the design and construction of this project as appropriate.Anti-Terrorism/Force Protection (AT/FP) features will comply with AT/FP regulations, and physical security mitigation in accordance with DoD Minimum Anti-Terrorism Standards for Buildings and any Theater-specific requirements.Facilities will be designed to provide cyber security engineering and validation as specified in DoD Unified Facilities Criteria.
Please read the entire solicitation and attachments for details.
Files
| File | Type | Posted |
|---|---|---|
| Abstract of Bids W912HV22B0011-signed.pdf |
Notice history
| Notice | Type | Posted |
|---|---|---|
| Replace Pacific East District Superintendent's Office, Yokota AB, Japan | Award Notice | |
| This notice | Solicitation | |
| Construct District Superintendent’s Office facility | Pre-Solicitation |
Similar open opportunities
| Opportunity | Agency | Set-aside | Responses due |
|---|---|---|---|
| FY26 ZNRE224305P3 Improve Military Family Housing PAIP 9 Phase 3, Yokota Air Base, Japan | ENDIST Japan | No set-aside | |
| FY26 MCN P309, School Age Care Centers Replacement, Camp Foster and McTureous, Okinawa, Japan | ENDIST Japan | No set-aside | |
| Vehicle Maintenance Shop, Kadena Air Base, Okinawa, Japan | ENDIST Japan | No set-aside | |
| Renovate military family housing tower 4511, camp courtney | ENDIST Japan | No set-aside | |
| AFHC Repair Quarters 82 and 86, Camp Zama, Japan | ENDIST Japan | No set-aside |
On GovTribe
Work this opportunity
- Track it in your pipeline
- Find teaming partners
- Similar opportunities
- Ask GovTribe AI about this opportunity