About this opportunity

This notice is for repair work along Beck Avenue and Flagler Street at Rock Island Arsenal. The Department of the Army Materiel Command Joint Munitions Command will solicit proposals to remove existing pavement, realign roads, install storm sewer and place new concrete pavement. Proposers must furnish all labor, equipment, and materials. Performance and payment bonds are required. Evaluation will consider technical qualifications and price. Questions are due by July 8, 2022.

This opportunity is set aside for total small business participation. Repairs include removing a retaining wall and relocating security fences and gates. Sidewalks will be replaced along with all storm drainage. Work must follow the 2022 Iowa SUDAS specifications and is estimated between $1 million to $5 million. The NAICS code is 237110 and PSC code is R499.

Notice text

This is a notice that a solicitation is anticipated to be forth coming and will have all the necessary documents, including a scope of work.

IAW FAR 36.204(d), the magnitude of this project is between $1,000,000.00 and $5,000,000.00.

Performance and Payment Bonds are required.

The Scope of this project consists of furnishing labor, equipment and material to realign, fully repave and update the Beck Avenue corridor and Flagler Street.  The premise for this project is to remove the existing pavement, realign Beck Avenue and Flagler Street, re-grade, install new storm sewer and place new pavement. Beck Avenue and Flagler Street along with all side street entrance connections shall be 9 inch Portland Cement Concrete with reinforcement at the joints with a 6 inch curb and gutter at 30 inch width, place on a 12 inch modified subbase. The project includes the removal of an existing retaining wall and
wing walls without disturbing an adjacent underground tunnel. Removal, relocation and
replacement of the existing security fence. Remove and relocate the existing turnstile
door and controls including electrical connections, simplex access programming and
installing a heated concrete pad. Remove and relocate the existing security gate that
includes operating controls, simplex access programming controls, card reader, electrical
connections and bollards with controls for the gate. 6 inch subdrain tile shall be installed
along the gutter line and tied into new storm intakes. Sidewalks shall be 6 feet in width,
P.C.C., placed on 6 inch modified subbase with 6 inch by 6 inch welded wire fabric.
Existing storm drainage shall be removed and replaced. The finish grade shall be receive
4” of topsoil and hydro seed and mulched. The project shall be constructed using the
Iowa State Urban Design and Specifications Program (SUDAS) 2022.

Notice history

Notice Type Posted
Repair Beck Avenue Rock Island Arsenal Latest solicitation Solicitation
This notice Original Pre-Solicitation

Similar open opportunities

Opportunity Agency Set-aside Responses due
W912EK27BA003 - Detroit Project Office Detroit, MI Wayne County Roads, Parking, and Grounds Renovation NAICS 237310 ENDIST Rock Island Competitive 8(a)
Gear shaper repair Rock Island, Illinois 61299, United States · NAICS 811310 ACC Rock Island Total Small Business