Remove a pedestrian bridge at Caesar Creek Lake

Closed Solicitation Posted

This opportunity was awarded. See the award notice from .

Solicitation number
W912QR25QA072
Agency
ENDIST Louisville US Army Corps of Engineers, Department of Defense
Responses due
Set-aside
Total Small Business

Opportunity facts

NAICS code
238910 Site Preparation Contractors
PSC
Y1LB Construction Of Highways, Roads, Streets, Bridges, And Railways
Place of performance
Caesar Creek Lake4020 N. Clarksville RoadWaynesville, Ohio 45068 45068
Points of contact
More information

Notice details come from SAM.gov. Updated .

About this opportunity

The U.S. Army Corps of Engineers Engineering District Louisville is seeking quotes for the removal of a pedestrian bridge and its embankments at Caesar Creek Lake, along with re-establishing the streambank in the tail water area. The contractor must provide all necessary management, personnel, materials, supplies, tools, equipment, fuel, and vehicles to complete the work in accordance with federal, state, and local regulations. The solicitation has been amended twice, with Amendment 0001 updating wage determinations and Amendment 0002 removing signage requirements from the scope of work. All contractors must resubmit their quotes incorporating both amendments to be considered for award. The current quote submission deadline is September 16, 2025, at 10:00 AM ET, with solicitation documents accessible through the PIEE Solicitation Module Link.

This opportunity is designated as a Total Small Business set-aside under NAICS code 238910 for Site Preparation Contractors. The work will be performed at Caesar Creek Lake located at 4020 N Clarksville Rd, Waynesville, OH 45068. A site visit attendance sheet indicates interest from three contractors: FCS Const, RDES Demo, and KT Holden Const, suggesting competitive interest in the project. The solicitation does not specify award values, contract duration, or detailed quantities, requiring review of the attached Statement of Work for comprehensive project specifications. The project falls under PSC category Y1LB for Construction of Highways, Roads, Streets, Bridges, and Railways, reflecting the infrastructure nature of the bridge removal work.

Notice text

5 versions

Update #5 · Latest ·

****Amendment 0002 START****

Solicitation W912QR25QA072 is hereby amended as follows on 15 September 2025:

Due to errors discovered in the Scope of Work, the follow changes have been made.

- The signage requirement (item number 3 in Line Item 0001) have been removed from the scope

*NOTE: The due date for quotes is updated to 16 September 2025 at 10:00 AM ET.**NOTE: All amendments shall be signed and submitted with the quote.* (Amendment 0001 and 0002)

*NOTE: ALL contractors must resubmit their quote by the stated deadline in order to be considered

*****Amendment 0002 END********

Amendment 0001 START****Solicitation W912QR25QA072 is hereby amended as follows on 08 September 2025:The Wage Determination have been updated form Wage Rates_OH20250001_15AUG2025 to Wage Rates_OH20250001_05SEPT2025. *NOTE: The due date for quotes remains 11 September 2025 at 10:00 AM ET.**NOTE: All amendments shall be signed and submitted with the quote.*****Amendment 0001 END****This Request for Quote (RFQ) is to remove a pedestrian bridge and its embankments, as well as re-establish the streambank in the tail water area of Caesar Creek Lake. Please see the SOW that is attached for more information. The contractor will provide all necessary management, personnel, materials, supplies, tools, equipment, fuel, and vehicles, except as otherwise provided herein, required to perform the work as specified and in strict accordance with all Terms, Conditions, General, Specific and Technical Provisions, Drawings, Attachments, Exhibits, etc., contained herein or incorporated by reference. The performance and responsibility of the contractor shall include all planning, programming, administration, management, supervision, communications, and inspection necessary to assure that all services are conducted in accordance with the contract requirements and all applicable Federal, State, and local laws and regulations.

Update #4 ·

****Amendment 0002 START****Solicitation W912QR25QA072 is hereby amended as follows on 15 September 2025:Due to errors discovered in the Scope of Work, the follow changes have been made. - The signage requirement (item number 3 in Line Item 0001) have been removed from the scope *NOTE: The due date for quotes is updated to 16 September 2025 at 10:00 AM ET.**NOTE: All amendments shall be signed and submitted with the quote.* (Amendment 0001 and 0002)*NOTE: ALL contractors must resubmit their quote by the stated deadline in order to be considered*****Amendment 0002 END********Amendment 0001 START****Solicitation W912QR25QA072 is hereby amended as follows on 08 September 2025:The Wage Determination have been updated form Wage Rates_OH20250001_15AUG2025 to Wage Rates_OH20250001_05SEPT2025. *NOTE: The due date for quotes remains 11 September 2025 at 10:00 AM ET.**NOTE: All amendments shall be signed and submitted with the quote.*****Amendment 0001 END****This Request for Quote (RFQ) is to remove a pedestrian bridge and its embankments, as well as re-establish the streambank in the tail water area of Caesar Creek Lake. Please see the SOW that is attached for more information. The contractor will provide all necessary management, personnel, materials, supplies, tools, equipment, fuel, and vehicles, except as otherwise provided herein, required to perform the work as specified and in strict accordance with all Terms, Conditions, General, Specific and Technical Provisions, Drawings, Attachments, Exhibits, etc., contained herein or incorporated by reference. The performance and responsibility of the contractor shall include all planning, programming, administration, management, supervision, communications, and inspection necessary to assure that all services are conducted in accordance with the contract requirements and all applicable Federal, State, and local laws and regulations.

Update #3 ·

****Amendment 0001 START****Solicitation W912QR25QA072 is hereby amended as follows on 08 September 2025:The Wage Determination have been updated form Wage Rates_OH20250001_15AUG2025 to Wage Rates_OH20250001_05SEPT2025. *NOTE: The due date for quotes remains 11 September 2025 at 10:00 AM ET.**NOTE: All amendments shall be signed and submitted with the quote.*****Amendment 0001 END****This Request for Quote (RFQ) is to remove a pedestrian bridge and its embankments, as well as re-establish the streambank in the tail water area of Caesar Creek Lake. Please see the SOW that is attached for more information. The contractor will provide all necessary management, personnel, materials, supplies, tools, equipment, fuel, and vehicles, except as otherwise provided herein, required to perform the work as specified and in strict accordance with all Terms, Conditions, General, Specific and Technical Provisions, Drawings, Attachments, Exhibits, etc., contained herein or incorporated by reference. The performance and responsibility of the contractor shall include all planning, programming, administration, management, supervision, communications, and inspection necessary to assure that all services are conducted in accordance with the contract requirements and all applicable Federal, State, and local laws and regulations.

Update #2 ·

This Request for Quote (RFQ) is to remove a pedestrian bridge and its embankments, as well as re-establish the streambank in the tail water area of Caesar Creek Lake. Please see the SOW that is attached for more information. The contractor will provide all necessary management, personnel, materials, supplies, tools, equipment, fuel, and vehicles, except as otherwise provided herein, required to perform the work as specified and in strict accordance with all Terms, Conditions, General, Specific and Technical Provisions, Drawings, Attachments, Exhibits, etc., contained herein or incorporated by reference. The performance and responsibility of the contractor shall include all planning, programming, administration, management, supervision, communications, and inspection necessary to assure that all services are conducted in accordance with the contract requirements and all applicable Federal, State, and local laws and regulations.

NOTE: For solicitation documents please see the attachments/links section and select "PIEE Solicitation Module Link for W912QR25QA072" for access to the solicitation. 

Update #1 ·

This Request for Quote (RFQ) is to remove a pedestrian bridge and its embankments, as well as re-establish the streambank in the tail water area of Caesar Creek Lake. Please see the SOW that is attached for more information. The contractor will provide all necessary management, personnel, materials, supplies, tools, equipment, fuel, and vehicles, except as otherwise provided herein, required to perform the work as specified and in strict accordance with all Terms, Conditions, General, Specific and Technical Provisions, Drawings, Attachments, Exhibits, etc., contained herein or incorporated by reference. The performance and responsibility of the contractor shall include all planning, programming, administration, management, supervision, communications, and inspection necessary to assure that all services are conducted in accordance with the contract requirements and all applicable Federal, State, and local laws and regulations.

Attachments

Files attached to this notice, newest first
File Type Posted
Site Visit Attendance Sheet.pdf PDF

Notice history

Notices posted for this opportunity, newest first
Notice Type Posted
Caesar Creek Pedestrian Bridge Removal Award Award Notice
Remove a pedestrian bridge at Caesar Creek Lake This notice · Latest solicitation Solicitation

On GovTribe

Work this opportunity on GovTribe

  • Track it in your pipeline
  • Find teaming partners
  • Similar opportunities
  • Ask GovTribe AI about this opportunity