The Department of the Air Force Materiel Command Air Force Sustainment Center is procuring remanufacturing services for KC-135 Flap Drive Angle Gearbox Assemblies through a 5-year Indefinite Delivery/Indefinite Quantity (IDIQ) contract. The contractor must completely disassemble, inspect, repair or replace components, reassemble, and test the gearbox assemblies to restore them to a like-new condition, including all necessary packing, preservation, and packaging. Key requirements include compliance with AS9100 or ISO 9001-2015 quality standards, adherence to technical orders and specifications, supply chain risk management, cybersecurity measures, and comprehensive reporting through the Commercial Asset Visibility (CAV) system. Award will be made to the lowest total evaluated price offeror who meets all solicitation requirements, with this being a price-only competition. Proposals are due by December 15, 2025, at 12:00 PM.
This solicitation is set aside 100% for Women-Owned Small Businesses (WOSB), with a NAICS code of 336413 and a size standard of 1,250 employees. The contract covers a minimum quantity of 40 units and maximum quantity of 350 units per ordering period, with each unit carrying a unit acquisition cost of $4,470. The contractor must perform a Pre-Award Survey and Initial Production Evaluation as detailed in the statement of work. Performance will take place at the contractor's facility, with surface transportation to the DLA Distribution Depot in Oklahoma at Tinker Air Force Base. The contractor must manage Government-Furnished Property, maintain monthly production reports, submit government property inventory reports, develop production surge plans, and report shipping and packaging discrepancies in accordance with multiple Contract Data Requirements Lists.
Notice text
A 5-YEAR INDEFINITE DELIVERY INDEFINITE QUANTITY (IDIQ) MIN-MAX TYPE CONTRACT IS CONTEMPLATED.
NOTE: It is anticipated that pricing of this action will be based on adequate price competition; therefore, offerors are not
required to submit certified cost or pricing data at the time of proposal. However, if after receipt of proposals, it is determined
that adequate price competition does not exist, a request for other than certified cost or pricing data may be required in
accordance with FAR 15.403-1(b)(1).
52.232-18 Availability of Funds. As prescribed in 32.706-1(a), insert the following clause: Availability of Funds (Apr 1984)
Funds are not presently available for this contract. The Government’s obligation under this contract is contingent
upon the availability of appropriated funds from which payment for contract purposes can be made. No legal
liability on the part of the Government for any payment may arise until funds are made available to the
Contracting Officer for this contract and until the Contractor receives notice of such availability, to be confirmed in
writing by the Contracting Officer. (End of clause)
(a) A Pre-Award Survey and/or Initial Production Evaluation (IPE) is required. Details are provided in Appendix A, paragraphs 1.2 and 1.3 respectively.
(b) The contractor shall furnish all material, plant facilities, labor, parts, equipment, and expertise necessary to perform the remanufacture required to restore the end item to a like-new condition. The contractor shall also accomplish ALL necessary packing and preservation and packaging. ALL work shall be completed in accordance with the requirements specified herein (including attachments hereto) and all costs associated with work specifications, technical orders, and/or cost associated with Over and Above request (excluding missing parts) shall be included in the unit price. The government shall only pay the contractor for missing components after review and approval of O&A request. No additional cost will be allowed (i.e.material handling, profit, direct or indirect costs).
(c) Qualification requirements apply. Interested vendors that have not been previously qualified for this acquisition must
submit a Source Approval Request (SAR) package to the Tinker AFB Small Business Office. For questions regarding the Tinker
SAR Process or related issues, these inquiries should be submitted to the TAFB Small Business Office at: AFSC/SB, 3001 Staff
Drive, Suite 1AG 85A, Tinker AFB, OK 73145-3009. Email: afsc.sb.workflow@us.af.mil Website:
https://www.afsc.af.mil/units/sbo/index.asp. The actual SAR package submission itself shall be submitted electronically through DoD SAFE at https://safe.apps.mil/. DoD SAFE is a safe and secure option for large file submissions. If you have a PKI Certificate, the SAR can be sent directly to the email address below via DoD SAFE. If you do not have a PKI Certificate, then you must send a standard email message to the email address below and ask that they “Request a Drop-Off” to your email via DoD SAFE, which will enable you to be able to upload the SAR Submission Package documents to DoD SAFE. 429SCMS.SASPO.Workflow@us.af.mil
For more information on the Strategic Alternate Sourcing Program, please visit: https://www.tinker.af.mil/Home/429SCMS-SASPO/
As prescribed in FAR 9.202(e), the contracting officer need not delay a proposed award in order to provide a potential offeror
with an opportunity to demonstrate its ability to meet the standards specified for qualification.
(d) In order to receive any technical data related to this acquisition, offerors must send an email request to Cliff Morgan at
clifford.morgan.8@us.af.mil or Amy Gil at amy.gil@us.af.mil. Release of any data is subject to applicable data rights. The request shall be on company letterhead and include the applicable solicitation number, the specific data needed (including TO(s)), and a copy of the current, approved DD Form 2345. The form, including instructions for completing the form, is Page 4 of 56 FA8118-26-R-0003 available at: http://www.dtic.mil/whs/directives/infomgt/forms/forminfo/forminfopage2220.html. The Government is not
responsible for incomplete, misdirected, or untimely requests.** In order to receive drawings contractors will need to request all needed drawings through the JEDMICS website: https://af-jedmics.navair.navy.mil/webjedmics/index.jsp. Contractors who need an account will need to complete the instructions at the above link.
(e) GOVERNMENT PROPERTY FURNISHED FOR REPAIR (FAR 16.503(c))
Failure of the Government to furnish such items in the amounts or quantities described in the Schedule as “estimated” or
“maximum” will not entitle the contractor to any equitable adjustment in price under the Government Property clause of the contract.
(f) END ITEMS BEYOND REMANUFACTURE
"Reparable End Items" are defined as end items which can be restored to a serviceable condition, in accordance with applicable
requirements. Some units of items listed in Section B may, upon disassembly and/or inspection, be determined to be beyond
the overhaul limits specified in the Work Specification and/or Technical Orders. Any cost for work performed by the Contractor
prior to determination that such equipment is beyond these limits, shall be included in the unit price(s) of the listed item(s).
(g) If the contractor estimates that any item is not reparable (i.e. beyond overhaul), the Contractor shall promptly notify the
administrative contracting officer in writing and shall not perform further overhaul on any such items except at the direction of
the administrative contracting officer (ACO). Upon written confirmation from the ACO that a particular item is not reparable,
the contractor shall dispose of the unit in the manner directed by the ACO. Contractors are cautioned that until a contract is executed, any effort performed in support of the anticipated effort is performed strictly at their own risk and expense. There is no authorization to begin performance until the contractor has received a duly authorized contract signed by the Contracting Officer. Also, this request for proposal is not to be construed to mean that the award of a contract is assured, as the availability of funds, timely submission of all requested documents, and acceptance by both parties are prerequisite to any contract award.
(h) Condemned units shall not be counted as production.
(i) In the event there are component part(s) with long lead times, the awardee is responsible for securing necessary parts to
meet the Government’s required delivery schedule.
(j) In the event that DFARS clause 252.217-7001, Surge Option, is invoked, quantities and prices will be negotiated at that time.
The fill-in data in Clause 252.217-7001 will be TBD until a surge is known and negotiations are necessary.
(k) Item Unique Identification (IUID) marking is required in accordance with DFARS 252.211-7003. Contractor determined
location and method of marking is acceptable.
(l) All quantities specified herein represent the total contract quantities for all five years combined. The ordering period for
each line item shall extend from the contractual effective data to five years thereafter or until the maximum quantity for each
line item is reached, whichever comes first. The minimum and maximum quantities for each line item are as follows:
Line Item 0001 NSN: 1680-00-335-6816 Minimum Quantity: 40each Maximum Quantity: 350 each
Line Item 0002 Over & Above
Line Item 0003 Data
(m) This Solicitation contemplates award of a five-year Indefinite Delivery Indefinite Quantity (IDIQ) Type Contract. Reference
Clauses 52.216-19 – Delivery-Order Limitations, 52.216-22 – Indefinite Quantity and 252.216-7006 – Ordering.
(n) Some units of items listed in Section B may, upon disassembly and/or inspection, be determined to be beyond the remanufacture limits specified in the Work Specification and/or Technical Orders. Any cost for work performed by the Contractor prior to determination that such equipment is beyond these limits, shall be included in the unit price(s) of the
listed item(s).
(o) In accordance with the attached CAV AF Reporting Requirements (see the document listed in Section J), the contractor must
include a DD1348-1when assets are shipped. DCMA Quality Assurance Representatives (QARs) will not approve or sign the
Page 5 of 56 FA8118-26-R-0003 DD1348-1, but will ensure DD1348-1 is included with each returned asset. If a DD1348-1 is not included with each returned asset, DCMA will not sign the DD250.
(p) In accordance with DAFFARS 5309.105-1 the Supplier Performance Risk System (SPRS) is checked for supplier risk
assessments when determining responsibility. DFARS 252.204.7303(b) states that the contracting officer shall verify that the
summary level score of a current NIST SP 800-171 DoD Assessment (i.e., not more than 3 years old, unless a lesser time is
specified in the solicitation) for each covered contractor information system that is relevant to an offer, contract, task order, or
delivery order are posted in Supplier Performance Risk System (SPRS). Offerors are required to represent they will implement
National Institute of Standards and Technology (NIST) Special Publication (SP) 800-171 SP 800-171 (reference the provision
DFARS 252.204-7008). A score of 110 must be in SPRS, if assessment score is less than 110, contractors must submit a plan
with their proposal to become compliant.
Files
| File | Type | Posted |
|---|---|---|
| IUID REDACTED.pdf | ||
| DID_80969.pdf | ||
| SOW.pdf | ||
| ITEM DESCRIPTION_REDACTED.pdf | ||
| CDRLs.pdf | ||
| DID_81995A.pdf | ||
| JQRR.pdf | ||
| Transportation Data.pdf | ||
| DID_80441D.pdf | ||
| DID_81838.pdf | ||
| GFP.pdf | ||
| CAV AF Reporting Requirements.pdf | ||
| Quality Assurance Report.pdf | ||
| Packaging Requirements.pdf | ||
| DID_80503.pdf | ||
| FA8118-26-R-0003.pdf |
Show all 16
Similar open opportunities
| Opportunity | Agency | Set-aside | Responses due |
|---|---|---|---|
| FA811826R0057 - reman E-3 AI gearbox assembly | Air Force Sustainment Center | No set-aside | |
| T-38 Accessory Drive Gearbox Remanufacture | Air Force Sustainment Center | No set-aside | |
| GearboxAssy_End_Item_F100_NSN_2840015493031NZ_PN_4087025-801 | Aviation | No set-aside | |
| Gearbox, Assembly, AI | Aviation | No set-aside | |
| N0038326PR0R653 | Naval Supply Systems Command | No set-aside |
On GovTribe
Work this opportunity
- Track it in your pipeline
- Find teaming partners
- Similar opportunities
- Ask GovTribe AI about this opportunity