Amendment 0001 - Due to conflicting dates contained in the document the proposals are now due 1 June 2015

Update #1 ·

Rehab Maintenance Facility Driveway and Parking lot

Ft Randall Project SD


Description:

The work includes removal of approximately 2,870 square yards of road asphalt that averages 4"-5" thick along the Maintenance Facility driveway and 3"-3.5" along the parking lot. The asphalt material will be either hauled about one mile away to the Fort Randall Bone Yard and stockpiled; or milled and stockpiled near the job site. The new design of the Maintenance Facility driveway and parking lot sub-base will consist of work to cut and/or fill to the elevations indicated on the drawings and compacted, while new sub-base areas will need to be excavated then filled with 6" of compacted gravel. Cut sub-base material (approximately 2" deep) from the driveway sections is to be used as sub-base fill on the parking lot extensions. Other work will include: 1) Removal of three (3) street light poles to be retained by the Government and respective footings estimated at 24"x24"x96" deep (cut conduit & abandon) to be disposed of by the contractor; 2) Removal and disposal of three (3) electrical pedestal (with bollard) footings approximately 24"x36"x48" deep; 3) Remove, dispose and replace a sidewalk approximately 98' long by 6' wide; 4) Excavating a 120' long electrical conduit trench to 6" deep by 3" wide along the sidewalk sub-base and extend approximately 20' north to a designated electrical junction box location; 5) Backfill and compact electrical conduit trench after COE personnel install the PVC electrical conduit; 6) Earthwork for removal of 40' of 18" round culvert to be retained by the Government; and 7) Ditch grading and shaping. Optional work will include placing landscaping rock at designated locations.

Files

Notice history

Notice Type Posted
Rehab Maint parking and driveway Fort Randall SD Latest Award Notice
This notice Original Award Notice

On GovTribe

Work this opportunity

  • Track it in your pipeline
  • Find teaming partners
  • Similar opportunities
  • Ask GovTribe AI about this opportunity

GovTribe for Federal Contractors