RECOVERY--Z--RECOVERY-- USACE Little Rock District, 700 West Capitol, Little Rock, AR 72201; Bank Stabilization Structure Repairs & Channel Improvements, Arkansas River.

Award Notice Posted

Solicitation number
W9127S09R0030
Agency
Awarded
to Souter Construction Co., Inc.
Set-aside
No set-aside

Opportunity facts

Contract number
W9127S-09-D-0010--0014 Federal contract award
NAICS code
237990 Other Heavy and Civil Engineering Construction
PSC
Not on record

Notice details come from SAM.gov. Updated .

Notice text

4 versions

Update #4 · Latest ·

THIS NOTICE IS PROVIDED FOR INFORMATION PURPOSES ONLY. There was a Delivery Orders awarded to W9127S-09-D-0010, Indefinite Delivery Indefinite Contract. The work consists of repairing damaged bank stabilization structures by adding stone to stone-fill revetments and dikes, trench-fill revetments, and wood pile revetments; by extending and raising structures and constructing new structures to improve the channel and reduce dredging requirements; realigning existing revetments. Schedule A, NM 308.7 to 125.4, Schedule B, 125.4 to 0.

Update #3 ·

THIS NOTICE IS PROVIDED FOR INFORMATION PURPOSES ONLY. There was a Delivery Orders awarded to W9127S-09-D-0010, Indefinite Delivery Indefinite Contract. The work consists of repairing damaged bank stabilization structures by adding stone to stone-fill revetments and dikes, trench-fill revetments, and wood pile revetments; by extending and raising structures and constructing new structures to improve the channel and reduce dredging requirements; realigning existing revetments. Schedule A, NM 308.7 to 125.4, Schedule B, 125.4 to 0.

Update #2 ·

RECOVERY-- THIS NOTICE IS PROVIDED FOR INFORMATION PURPOSES ONLY. There was a Delivery Orders awarded to W9127S-09-D-0010, Indefinite Delivery Indefinite Contract. The work consists of repairing damaged bank stabilization structures by adding stone to stone-fill revetments and dikes, trench-fill revetments, and wood pile revetments; by extending and raising structures and constructing new structures to improve the channel and reduce dredging requirements; realigning existing revetments. Schedule A, NM 308.7 to 125.4, Schedule B, 125.4 to 0.

Update #1 ·

RECOVERY-- THIS NOTICE IS PROVIDED FOR INFORMATION PURPOSES ONLY. There was a Delivery Orders awarded to W9127S-09-D-0010, Indefinite Delivery Indefinite Contract. The work consists of repairing damaged bank stabilization structures by adding stone to stone-fill revetments and dikes, trench-fill revetments, and wood pile revetments; by extending and raising structures and constructing new structures to improve the channel and reduce dredging requirements; realigning existing revetments. Schedule A, NM 308.7 to 125.4, Schedule B, 125.4 to 0.

On GovTribe

Work this opportunity

  • Track it in your pipeline
  • Find teaming partners
  • Similar opportunities
  • Ask GovTribe AI about this opportunity

GovTribe for Federal Contractors