RECOVERY--Z--RECOVERY INFORMATIONAL ONLY RECOVERY Resurface Chaffee & Entrance Road

Award Notice Posted

Solicitation number
W9124E08D0005
Agency
Awarded
to WB Construction & Sons, Inc.
Set-aside
No set-aside

Opportunity facts

Contract number
W9124E-08-D-0005-0009 Federal contract award
NAICS code
237310 Highway, Street, and Bridge Construction
PSC
Not on record
Place of performance
ACA, Fort Polk Directorate of Contracting, 6661 Warrior Trail Fort Polk LA 71459 US
More information

Notice details come from SAM.gov. Updated .

Notice text

3 versions

Update #3 · Latest ·

RECOVERY--THIS NOTICE IS PROVIDED FOR INFORMATION PURPOSES ONLY. THIS OPPORTUNITY IS AVAILABLE ONLY TO CONTRACTORS UNDER W9124E08D0005.

RECOVERY INFORMATIONAL ONLY RECOVERY Resurface Chaffee & Entrance Road, Fort Polk,La THIS NOTICE IS PROVIDED FOR INFORMATION PURPOSES ONLY. THIS OPPORTUNITY IS AVAILABLE ONLY TO CONTRACTORS UNDER W9124E-08-D-0005-0013

Update #2 ·

This work is available only to previous competed solicitation resulting in contract W9124E-08-D-0005 awarded to W.B Construction & Sons, LLC. WORK TO BE DONE: Perform all work as necessary for the Chaffee & Entrance Road construction project. Work shall be done in accordance with the appropriate building codes and requirements specifications unless otherwise indicated.
SITE CLEARING AND PREPARATION: Prepare site for the placement of fill material and stone base.
Site demolition cold plane 1.5 of asphaltic concrete.
Patch any base failures to contract specifications.
Apply surface treatment and overlay 2 of asphaltic wearing course.
Restripe with plastic pavement marking.
SITE MAINTENANCE: The contractor shall take necessary measures to control erosion of existing disturbed areas. When construction is complete, the contractor shall make sure any disturbed areas are returned to before construction quality.
Paving Roadway: Contractor shall furnish and pave one or more courses of asphaltic concrete in conformity with lines, grades and thickness as directed by PM.
UTILITIES: Locate all existing utilities and protect during construction. (includes Gas, sewer, electrical, water, and communications)
Note: All patterns and colors shall follow the Fort Polk Installation Design Guide and will be submitted to the government for selection prior to install. The contractor will submit color samples to project manager for approval.

Update #1 ·

RECOVERY - INFORMATIONAL ONLY - This project available only to awardee of previously competed contract - Perform all work as necessary for the overlay of Louisiana Avenue for DPW. Work shall be done in accordance with the appropriate building codes and requirements specifications unless otherwise indicated. SITE CLEARING AND PREPARATION: Prepare site for the placement of fill material and stone base. Site demolition cold plane 1.5 of asphaltic concrete. Patch any base failures to contract specifications. Apply surface treatment and overlay 1.5 of asphaltic wearing course. Restripe with plastic pavement marking. SITE MAINTENANCE: The contractor shall take necessary measures to control erosion of existing disturbed areas. When construction is complete, the contractor shall make sure any disturbed areas are returned to before construction quality. Paving Roadway: Contractor shall furnish and pave one or more courses of asphaltic concrete in conformity with lines, grades and thickness as directed by PM. UTILITIES: Locate all existing utilities and protect during construction. (includes Gas, sewer, electrical, water, and communications)- INFORMATIONAL ONLY - RECOVERY