RECOVERY--Z--PROJECT NUMBER WWYK050315A, Repair East Jet Engine Power Check Pad, Facility 51170

Award Notice Posted

Solicitation number
W912BV-08-R-2011
Agency
Awarded
Set-aside
No set-aside

Opportunity facts

Contract number
W912BV-08-D-2045, Task Order 0011, 001102
NAICS code
236210 Industrial Building Construction
PSC
Not on record

Notice details come from SAM.gov. Updated .

Notice text

3 versions

Update #3 · Latest ·

RECOVERY - PER FAR 5.7 THIS NOTICE IS PROVIDED FOR INFORMATION PURPOSES ONLY; THEREFORE FAR 5.203 DOES NOT APPLY. THIS OPPORTUNITY WAS AVAILABLE ONLY TO CONTRACTOR(S) UNDER THE CURRENT CONTRACT NUMBER(S): Asset Group, Inc., W912BV-08-D-2050, Task Order 0003, Operations & Mainteance, Air Force

As part of Operations and Maintenance, Air Force, Recovery Act, this modification has been issued to Asset Group, Inc., to perform the following work: (1) Delete the following from the Statement of Work: 2.1.10 Contractor shall replace existing thrust blocks in-kind. (2) Delete the following from the Statement of Work: 2.1.10 Contractor shall replace existing thrust blocks in-kind. (3) Install 100,000 lb capacity thrust anchor on east power check pad according to Air Force ETL 01-10. Anchor to be located 67.5 feet from the east edge of the concrete pavement, and centered in the concrete panel as noted in "blue" on the attached drawing. The north panel is the preferred location. (4) Delete from Statement of Work: 4.1.1.1.6 East Pad Blast Deflector Metal. Repair or replace angle iron bracing as needed. Replace corroded corrugated metal panels to match existing where necessary. (5) Delete from the Statement of Work: 1.1.4.1 The Government shall retain occupancy of one power check pad while the other power check pad is under construction. 1.1.4.2 Contractor shall phase the project. Phase 1 shall be to repair the east power check pad: phast 2 shall be to repair the west power check pad. (6) Delete from the Statement of Work: 1.1.4.1 The Government shall retain occupancy of one power check pad while the other power check pad is under construction. 1.1.4.2 Contractor shall phase the project. Phase 1 shall be to repair the east power check pad: phast 2 shall be to repair the west power check pad. (7) The Contracting Officer suspended the Contractor from work due to a customer request because an Air Show was taking place in the vicinity of the work zone. The Contractor has requested time and compensation due to the suspension. (8) Contractor shall remove approximately 750 linear feet of airfield fence east of runway 17/35, west of 3108 & 3117 and 400 linear feet of airfield fence west of runway 17/35 on the east side of where building 101/95. All ground surfaces where support posts have been removed shall be restored to the surrounding ground condition. Attached "Sketch A" shows location of fencing to be removed. Execution of this work shall occur with-in the current project performance period. (9) Contractor shall mill and overlay approximately 1,865 linear feet by 8 foot wide asphalt shoulder at the TMF as shown on attached "Sketch B". Existing asphalt shall be milled down 1-1/2 inches and overlaid back to existing surfaces. Asphalt mix shall be the same as what is required for the shoulders at the check pad. Asphalt millings shall be stock piled for the bases use at a location on the south side of patrol road. Execution of this work shall occur with-in the current project performance period.

Update #2 ·

RECOVERY - PER FAR 5.7 THIS NOTICE IS PROVIDED FOR INFORMATION PURPOSES ONLY; THEREFORE FAR 5.203 DOES NOT APPLY. THIS OPPORTUNITY WAS AVAILABLE ONLY TO CONTRACTOR(S) UNDER THE CURRENT CONTRACT NUMBER(S): HGL Construction, Inc., W912BV-08-D-2045, Task Order 0011, Operations & Maintenance, Air Force

As part of Operations and Maintenance, Air Force, Recovery Act, this modification has been issued to HGL Construction, Inc., to perform the following work: Change the domestic water tie-in point from the location shown in the approved drawings to 100 linear feet further north making the tie-in to the ddmestic water line within the grass area north of the building 230 security fence and just south of 1st Street.

Update #1 ·

RECOVERY - PER FAR 5.7 THIS NOTICE IS PROVIDED FOR INFORMATION PURPOSES ONLY; THEREFORE FAR 5.203 DOES NOT APPLY. THIS OPPORTUNITY WAS AVAILABLE ONLY TO CONTRACTOR(S) UNDER THE CURRENT CONTRACT NUMBER(S): Asset Group, Inc., W912BV-08-D-2050, Task Order 0003, Operation & Maintenance, Air Force

As part of Operations and Maintenance, Air Force, Recovery Act, this modification has been issued to Asset Group, Inc., to extend he contract as follows: Extend project performance period 42 calandar days due to Government caused delays. Delay was due to the contractor not being able to access the construction site due to an aircraft being damaged upon landing and the subsequent investigation.

Notice history

4 of 7 notices listed here. See the rest on GovTribe.