RECOVERY--Z--PROJECT NUMBER 13818, Illinois River Basin Restoration , IL
Award Notice Posted
- Solicitation number
- W912EK-10-R-0063
- Agency
-
ENDIST Rock Island
US Army Corps of Engineers, Department of Defense
- Awarded
- to Frontier - Arrowhead
- Set-aside
- No set-aside
Opportunity facts
- Contract number
- W912EK-10-C-0112 Federal contract award
- NAICS code
- 237990 Other Heavy and Civil Engineering Construction
- PSC
- Not on record
Notice details come from SAM.gov. Updated .
Notice text
2 versions
Update #2 · Latest ·
Contract Award Amount equals $378,162.11 Recovery Funds, and $145,788.69 Non-Recovery Funds.
This contract action was accomplished using other than competitive procedures because a statute exists that expressly authorizes or requires that the acquisition be made from a specific source or through another agency (FAR 6.302-5); specifically, Sole source awards under the 8(a) Program. Per FAR 6.302-5 a J&A is not required for this award.
THIS NOTICE IS PROVIDED FOR INFORMATION PURPOSES ONLY. THIS PROJECT WAS SOLE SOURCED TO AN 8(A) CONTRACTOR.
This notice is being posted in compliance with the transparency and accountability requirements associated with the American Recovery and Reinvestment Act.
Solicitation W912EK-10-R-0063 was awarded under contract W912EK-10-C-0112, Waubonsie Creek, Section 519, Illinois River Basin, Oswego, Kendall County, IL.
The work includes, but is not limited to grading, shaping, and placing erosion protection for stream banks; placing field stone, riprap, and boulders to construct rock ramps riffles and bank slop protection; clearing and grubbing; modification of existing spillway and dam from within stream; debris removal and disposal; and seeding.
Update #1 ·
RECOVERY - THIS NOTICE IS PROVIDED FOR INFORMATION PURPOSES ONLY. THIS OPPORTUNITY IS AVAILABLE ONLY TO A SOLE SOURCE 8(A) SET ASIDE CONTRACTOR. THIS IS NOT A REQUEST FOR PROPOSAL.
This notice is being posted in compliance with the transparency and accountability requirements associated with the American Recovery and Reinvestment Act.
The work includes, but is not limited to grading, shaping, and placing erosion protection for stream banks; placing field stone, riprap, and boulders to construct rock ramps riffles and bank slop protection; clearing and grubbing; modification of existing spillway and dam from within stream; debris removal and disposal; and seeding.
Notice history
| Notice | Type | Posted |
|---|---|---|
| RECOVERY--Z--PROJECT NUMBER 13818, Illinois River Basin Restoration , IL | Award Notice | |
| This notice | Award Notice |
On GovTribe
Work this opportunity
- Track it in your pipeline
- Find teaming partners
- Similar opportunities
- Ask GovTribe AI about this opportunity