RECOVERY--Z--PROJECT NUMBER 111134 Facilities Repair/Renewal Project, Closure Structure Reconstruction, Wood River Drainage and Levee District, Madison County, IL. -Z
Award Notice Posted
- Solicitation number
- W912DY-10-N-61
- Agency
-
Engineering Support Center Huntsville
US Army Corps of Engineers, Department of Defense
- Awarded
- to Lime Energy Services CO.
- Set-aside
- No set-aside
Opportunity facts
- Contract number
- W912DY-08-D-0033-0004 Federal contract award
- NAICS code
- 236220 Commercial and Institutional Building Construction
- PSC
- Not on record
Notice details come from SAM.gov. Updated .
Notice text
2 versions
Update #2 · Latest ·
RECOVERY - PER FAR 5.7 THIS NOTICE IS PROVIDED FOR INFORMATION PURPOSES ONLY; THEREFORE FAR 5.203 DOES NOT APPLY. THIS OPPORTUNITY WAS AVAILABLE ONLY TO CONTRACTOR(S) UNDER THE CURRENT CONTRACT NUMBER(S): ITSI-W912DY-08-D-0032, AEM-W912DY-08-D-0033, and JJKSP-W912DY-08-D-0034,
RECOVERY -- THIS AWARD NOTICE IS PROVIDED FOR INFORMATION PURPOSES ONLY. The purpose of this project is for the replacement and reconstruction of three closure structures within the Wood River Levee System located in Madison County, Illinois. This levee system is located along the east bank of the Mississippi River, between river miles 195 and 203, above the Ohio River and is maintained by the Wood River Levee and Drainage District. The three reconstructed closure structures are in close proximity to Powder Mill Road and are adjacent to the East Fork of Wood River. Two of the structures are for closure of a common railroad track through the lines of protection along each bank of the East Fork (closure structures CS-10 on the north bank and CS-11 on the south bank). The other structure (CS-12) is a two lane roadway closure across Powder Mill Road on the south bank of the East Fork. The closure structures are within a publicly accessible area of the Olin-Winchester Corporation manufacturing facility in East Alton, IL. In accordance with Section 803 Evaluation Requirements, the evaluation consensus board (using the evaluation criteria identified in the RFP), determined Applied Energy Management as the best value contractor to perform the services.
Update #1 ·
RECOVERY - PER FAR 5.7 THIS NOTICE IS PROVIDED FOR INFORMATION PURPOSES ONLY; THEREFORE FAR 5.203 DOES NOT APPLY. THIS OPPORTUNITY IS AVAILABLE ONLY TO CONTRACTOR(S) UNDER THE CURRENT CONTRACT NUMBER(S): ITSI (W912DY-08-D-0032); AEM (W912DY-08-D-0033); and JJKSP (W912DY-08-D-0034)
The intent of this task order is for the replacement and reconstruction of three closure structures within the Wood River Levee System in Madison County, Illinois.
On GovTribe
Work this opportunity
- Track it in your pipeline
- Find teaming partners
- Similar opportunities
- Ask GovTribe AI about this opportunity