RECOVERY Y--Recovery Act. Bldg # 1, Fire Sprinkler Life Safety System. Project: 654-09-408. Project Location: Sierra Nevada Health Care System (SNHCS). City of Reno, County of Washoe, State of Nevada.
Award Notice Posted
- Solicitation number
- VA-261-10-RA-0150
- Agency
-
Veterans Integrated Service Network 21
Veterans Health Administration, Department of Veterans Affairs
- Awarded
- to Patriot Construction Inc.
- Set-aside
- Service-Disabled Veteran-Owned Small Business
Opportunity facts
- Contract number
- VA261RA0844 Federal contract award
- NAICS code
- 236220 Commercial and Institutional Building Construction
- PSC
- Not on record
Notice details come from SAM.gov. Updated .
Notice text
AMERICAN RECOVERY AND REINVESTMENT ACT (ARRA)OF 2009 --- PUBLIC LAW 111 - 5
THIS SPECIAL NOTICE IS PROVIDED FOR INFORMATIONAL PURPOSES ONLY:
This procurement shall be solicited as a Total Service Disabled Veteran Owned Small Business (SDVOSB) Set-Aside ONLY, and it shall be competitively negotiated amongst
the existing VA Sierra Pacific Network (VISN 21) Indefinite Delivery Indefinite Quantity (IDIQ) Contractors ONLY.
SOLICITATION (RFP) VA-261-10-RA-0150
SECTION 00 11 21
REQUEST FOR PROPOSAL TO DESIGN BUILD
BLDG 1 SPRINKLER SYSTEM
PROJECT NUMBER 654-09-408
RENO VAMC
RENO, NEVADA
SCOPE OF WORK --- DESIGN-BUILD
A. PART I - General
A1. SCOPE OF CONTRACT
Provide all labor, materials, tools and equipment, and design-build services necessary
for design and construction of a fire suppression system and fire alarm system modifications to the VA Hospital in Reno, NV, as described in the following work description and phasing plan:
Phase 2 to include the following section of Bldg 1 and is to be coordinated with Phase 2
of the Bldg 1 HVAC Project. A complete set of "Reflective Ceiling Plan" drawings
for Bldg 1 HVAC Project is provided for clarification:
Fire sprinkler installation and alarm system mods in Section 1-1 (North Wing)
Fire sprinkler installation and alarm system mods in Section 1-2 (NorthEast Wing)
Fire sprinkler installation and alarm system mods in Section 1-3 (North Section of Center Core Wing)
Provide connection point for Phase 3 from center core.
Phasing requirements are included in this scope to allow coordination with a project recently awarded to replace the HVAC system in Bldg 1. If phased properly, adequate clearances will be provided for routing of the sprinkler system and demo or install
of ceilings will not be required under this scope.
836.204 Disclosure of the magnitude of construction projects.
The estimated price range for this project is between $250,000 and $500,000.
RFP issue date is approximately March 19, 2010.
Pre-Proposal Conference (PPC) / Site Walk (SW) date is approximately March 26, 2010.
Offer due date is approximately April 19, 2010.
Exact times, dates, and locations shall be provided in the RFP.
Files
| File | Type | Posted |
|---|---|---|
| VA-261-10-RA-0150-0002000.DOC | DOC document | |
| VA-261-10-RA-0150-0001000.DOC | DOC document | |
| VA-261-10-RA-0150-000.DOC | DOC document | |
| VA-261-10-RA-0150-008.PDF | ||
| VA-261-10-RA-0150-017.PDF | ||
| VA-261-10-RA-0150-013.PDF | ||
| VA-261-10-RA-0150-012.PDF | ||
| VA-261-10-RA-0150-006.PDF | ||
| VA-261-10-RA-0150-004.PDF | ||
| VA-261-10-RA-0150-011.PDF | ||
| VA-261-10-RA-0150-020.PDF | ||
| VA-261-10-RA-0150-005.PDF | ||
| VA-261-10-RA-0150-007.PDF | ||
| VA-261-10-RA-0150-001.PDF | ||
| VA-261-10-RA-0150-009.PDF | ||
| VA-261-10-RA-0150-016.PDF | ||
| VA-261-10-RA-0150-015.PDF | ||
| VA-261-10-RA-0150-018.PDF | ||
| VA-261-10-RA-0150-003.PDF | ||
| VA-261-10-RA-0150-002.PDF | ||
| VA-261-10-RA-0150-010.PDF | ||
| VA-261-10-RA-0150-014.PDF | ||
| VA-261-10-RA-0150-019.PDF |
Show all 23
On GovTribe
Work this opportunity
- Track it in your pipeline
- Find teaming partners
- Similar opportunities
- Ask GovTribe AI about this opportunity