3 versions

Update #3 · Latest ·

RECOVERY - PER FAR 5.7 THIS NOTICE IS PROVIDED FOR INFORMATION PURPOSES ONLY; THEREFORE FAR 5.203 DOES NOT APPLY. THIS OPPORTUNITY WAS AVAILABLE ONLY TO CONTRACTOR(S) UNDER THE CURRENT CONTRACT NUMBER(S): GREAT LAKES DOCK AND MATERIALS, LLC W911XK-09-C-0021

This change provides, under Contract Clause 52.236-2 'Differing Site Conditions' for the removal of the concrete cap and other obstructions to facilitate the installation of steel sheet piling for the FY09 Saugatuck Harbor Revetment Repairs.

Update #2 ·

RECOVERY - PER FAR 5.7 THIS NOTICE IS PROVIDED FOR INFORMATION PURPOSES ONLY; THEREFORE FAR 5.203 DOES NOT APPLY. THIS OPPORTUNITY WAS AVAILABLE ONLY TO CONTRACTOR(S) UNDER THE CURRENT CONTRACT NUMBER(S): GREAT LAKES DOCK AND MATERIALS, LLC

This change provides, under Contract Clause 52.211-5001 'VARIATIONS IN ESTIMATED QUANTITIES, SUBDIVIDED ITEMS', for revising the estimated stone quantities in the contract bid schedule to reflect the actual quantities used for construction for the FY09 Saugatuck Harbor Revetment Repairs.

Update #1 ·

This project consist of repairs to Section C, D, E and F of the North Revetment and Sections C, D, E, F1 and F of the South Revetment at Saugatuck Harbor, Michigan. The total length of repairs to the North and South Revetments is approximately 1500 and 1360 respectively.