RECOVERY--S--PROJECT NUMBER 14580, Proctor Lake, TX Construct and provide electrical system enhancements to Copperas Creek Park and Promontory Park, Proctor Lake, Comanche, TX.

Award Notice Posted

Solicitation number
W9126G-10-R-0052
Agency
Awarded
to Comanche County Electric Cooperative Association
Set-aside
No set-aside

Opportunity facts

Contract number
W9126G-10-C-0050 Federal contract award
NAICS code
238210 Electrical Contractors and Other Wiring Installation Contractors
PSC
Not on record

Notice details come from SAM.gov. Updated .

Notice text

This contract action was accomplished using other than competitive procedures because there is only one responsible source as this contract is for utilities, and no other supplies or services will satisfy agency requirements. (FAR 6.302-1). See posted J&A for further information.

FOR OTHER THAN FULL AND OPEN COMPETITION


1. CONTRACTING AGENCY - Department of Army
US Army Corps of Engineers
Fort Worth District
Contracting Division
Fort Worth, Texas 76102

2. DESCRIPTION OF ACTION The approval is being requested for electrical improvements due funding received by the American Recovery and Reinvestment Act to renovate campgrounds at Proctor Lake. Furnish all tools, labor, material and equipment to provide electrical system enhancements to Copperas Creek Park and Promontory Park. This improvement will include installation of two new metering points, replacing 11 pole transformers with ground mounted transformers, replacing two pole transformers and relocating two metering locations. It is estimated to be completed within 18 months. The schedule of this work will parallel the construction work to be initialized under the American Recovery and Reinvestment Act of 2009. Jim Lester, Staking and Mapping Engineer for the Comanche Electric Cooperative Association, is the POC on this project and his contact number is 1-800-915-2533. Value is not to exceed $80,000.

3. DESCRIPTION OF SERVICES - Comanche Electric Cooperative Association (CECA) will be removing eight -167KVA & a 25KVA existing overhead transformers and poles, removing four poles with lighting arresters and removing two service poles, downgrading eight demand meters and removing 140 LF of primary line at the group use area. CECA will be installing ten - 37.5KVA ground mounted transformers with concrete pads, two 25KVA ground mounted transformers with pads, four ground-mounted junction boxes with slabs, one steel pole with 37.5 KVA areal transformers and four steel posts around every pad transformer. CECA will also install an estimated 559LF of primary line in Government provided pipe and ditch. CECA will provide twelve 200-320 Amp meter bases and make all primary side connections and material for electrical service.

4. AUTHORITY CITED - 10 USC 2304(c)1, as implemented by FAR 6.302-1(b)(3); State and Federal agencies created franchise territory that dictate that one utility company will provide service and provide construction work on their system.

5. REASON FOR AUTHORITY CITED - Comanche Electric Cooperative Association is the owner of the power distributions lines in this area and has successfully operated and maintained hundreds of miles of electric power lines for decades. The Texas Utility Commission requires CECA to own and maintain the existing power lines in this area; therefore, when a customer requests power changes to the existing lines, that customer is responsible for paying for any upgrades associated with the requirement. All the work identified in this J&A will be preformed by CECA employees.

6. EFFORTS TO OBTAIN COMPETITION - Because of electrical deregulation, there are now many electric service providers for electricity (power), but only one owner of the power distribution lines in this area, which is CECA. Therefore, any power work must be performed via CECA, as CECA will not allow another companies to upgrade or perform work their power lines.

7. ACTIONS TO INCREASE COMPETITION - No other actions pursued to increase competition.
8. MARKET RESEARCH - The Government has contacted CECA and verified the information provided herein.
9. INTERESTED SOURCES - The authority at 10 U.S.C.2304(c)(1), only one source can perform this particular requirement, because the power line ownership was not deregulated, and therefore the owner has the authority to allow or, as in this case, disallow another party to perform upgrades on the utility lines. The notice will be published.

10. OTHER FACTS - CECA has the necessary prerequisite knowledge of the power grid, system design and load capacity to make changes or modifications on the power system. CECA has the only ROW easements for access to provide improvement to system upgrades.
a. Procurement history.
Contract No. Period of Performance Project Name Competitive Status Contract Value
DACW-63-79-C-0002 1979 to unknown Provide Electric Utility Service Sole Source Unknown
b. Acquisition data availability. NA
c. Unusual and compelling urgency. NA
d. Subcontracting competition. NA

11. TECHNICAL CERTIFICATION:

I certify that the supporting data under my cognizance which are included in the justification are accurate and complete to the best of my knowledge and belief.

NAME: _Ronnie Bruggman___________ DATE: ________________

TITLE: _Recreational BLM SIGNATURE: ___________________


12. REQUIREMENTS CERTIFICATION:

I certify that the supporting data under my cognizance which are included in the justification are accurate and complete to the best of my knowledge and belief.

NAME: ____Toni Rushing____________ DATE: _______________

TITLE: _ OPM SIGNATURE: ________________________


13. FAIR AND REASONABLE COST DETERMINATION:

I hereby determine that the anticipated cost or price to the Government for this contract action will be fair and reasonable. Determination was based upon historical pricing and negotiations. Certified cost or pricing data is not required as the action is below $80,000.

NAME: _June L. Wohlbach____________ DATE: ________________

TITLE: Contracting Officer SIGNATURE: ____________________


14. CONTRACTING OFFICER CERTIFICATION:

I certify that this J&A is accurate and complete to the best of my knowledge and belief.


NAME: _June L. Wohlbach___________ DATE: ________________

TITLE: Contracting Officer SIGNATURE: ___________________

APPROVAL

Based on the foregoing justification, I hereby approve the procurement of electrical improvement services with Comanche Electric Cooperative Association, on an other than full and open competition basis pursuant to the authority of 10 U.S.C. 2304(c)(1), subject to the availability of funds, and provided the services herein described have otherwise been authorized for acquisition. Authorized amount is not to exceed $80,000.00.


NAME: JUNE L. WOHLBACH DATE: _________________________

TITLE: _______________________ SIGNATURE: _____________________

Notice history

On GovTribe

Work this opportunity

  • Track it in your pipeline
  • Find teaming partners
  • Similar opportunities
  • Ask GovTribe AI about this opportunity

GovTribe for Federal Contractors