RECOVERY--R--PROJECT NUMBER 138889, Alabama River Lakes, AL Sedimentation and Erosion Analysis Report

Award Notice Posted

Solicitation number
W91278-10-156-ARRA
Agency
Awarded
to Bowhead Science And Technology, LLC
Set-aside
No set-aside

Opportunity facts

Contract number
W91278-10-156-ARRA Federal contract award
NAICS code
541990 All Other Professional, Scientific, and Technical Services
PSC
Not on record

Notice details come from SAM.gov. Updated .

Notice text

4 versions

Update #4 · Latest ·

RECOVERY - PER FAR 5.7 THIS NOTICE IS PROVIDED FOR INFORMATION PURPOSES ONLY; THEREFORE FAR 5.203 DOES NOT APPLY. THIS OPPORTUNITY WAS AVAILABLE ONLY TO CONTRACTOR(S) UNDER THE CURRENT CONTRACT NUMBER(S): Bowhead Scienhce and Technology, LLC W91278-10-D-0001, Scientific and Technology Support for Mobile District

This contract action was accomplished using other than competitive procedures because this is an order under an existing contract that was awarded using non-competitive procedures.

Correction to previous award notice. The award number is corrected to read W91278-10-D-0001, 0007 in lieu of W91278-10-156-ARRA as previously stated. All other information provided remains unchanged.

Update #3 ·

RECOVERY - PER FAR 5.7 THIS NOTICE IS PROVIDED FOR INFORMATION PURPOSES ONLY; THEREFORE FAR 5.203 DOES NOT APPLY. THIS OPPORTUNITY WAS AVAILABLE ONLY TO CONTRACTOR(S) UNDER THE CURRENT CONTRACT NUMBER(S): Bowhead Science and Technology, LLC W91278-10-D-0001, Scientific and Technology Support for Mobile District

This contract action was accomplished using other than competitive procedures because this is an order under an existing contract that was awarded using non-competitive procedures.

The US Army Corps of Engineers awarded Task Order 0007 against their sole source 8(a) fixed price Indefinite Delivery Indefinite Quantity Contract W91278-10-D-0001. The scope of work for Task Order 0007 covers Sedimentation Survey Analysis for Alabama River Lakes projects. This award includes American Recovery and Reinvestment Act funding and all applicable clauses apply.

Update #2 ·

RECOVERY - PER FAR 5.7 THIS NOTICE IS PROVIDED FOR INFORMATION PURPOSES ONLY; THEREFORE FAR 5.203 DOES NOT APPLY. THIS OPPORTUNITY IS AVAILABLE ONLY TO CONTRACTOR(S) UNDER THE CURRENT CONTRACT NUMBER(S): Bowhead Science and Technology, LLC, W91278-10-D-0001, Scientific & Technology Support for Mobile District

Special Notice W91278-10-156-ARRA is amendment to add Project Number 138889 - Alabama River Lakes, AL for Sedimentation and Erosion Analysis Report.

Update #1 ·

RECOVERY - PER FAR 5.7 THIS NOTICE IS PROVIDED FOR INFORMATION PURPOSES ONLY; THEREFORE FAR 5.203 DOES NOT APPLY. THIS OPPORTUNITY IS AVAILABLE ONLY TO CONTRACTOR(S) UNDER THE CURRENT CONTRACT NUMBER(S): Bowhead Science and Technology, LLC, W91278-10-D-0001, Scientific & Technology Support for Mobile District

Using recovery Act funding, the Mobile District Corps of Engineers intends to issue a Task Order against Contract number W91278-10-D-0001, a Sole Sourced 8(a) awarded as a Fixed Price Indefinite Delivery Indefinite Quantity Contract for Scientific and Technology Support for the Mobile District Corps of Engineers awarded to Bowhead Science and Technology, LLC, 7851 Dolleys Court, King George, VA 22485. North American Industry Classification System (NAICS) code 541990 applies to this contract award. Description of Work: This effort is in support of a Sedimentation Survey Analysis for USACE Mobile District projects. The contractor will process hydrographic and lidar data along with aerial photography in support of efforts to perform a sedimentation and erosion analysis for Alabama River Lakes projects (Lake Claiborne, Millers Ferry Lock and Dam, Robert F. Henry Lock and Dam). The existing contract must be used for the following reason: 1) The work to be performed is within scope of the original contract. 2) The incumbent contract has the management, technical and administrative skills to efficiently and effectively accomplish this work. 3) This contract enables the work to begin immediately. Contract clauses required for project involving Recovery Act funds have been incorporated into the existing contract. The American Recovery and Reinvestment Act (ARRA) contain specific acquisition requirements that must be met when using Recovery Act funds, including compliance with the Federal Acquisition Regulation.