RECOVERY--QSEU020138- Repair Airfield Electrical System (Aori)

Award Notice Posted

Solicitation number
02-0138
Agency
Awarded
to Cherokee Chainlink & Construction, Inc.
Set-aside
Competitive 8(a)

Opportunity facts

Contract number
FA4830-07-D-7007-6149 Federal contract award
NAICS code
238210 Electrical Contractors and Other Wiring Installation Contractors
PSC
Not on record
Place of performance
Bldgs 723 and 724 on Moody Afb Ga Moody, Georgia 31699, United States

Notice details come from SAM.gov. Updated .

Notice text

2 versions

Update #2 · Latest ·

Replace the airfield electrical system homeruns on the airfield lighting system from lighting vault at Building 723 to runway 36R/18L. Install new airfield lighting control system in lighting vault Building 723, Control Tower Building 1300, and 911 Center, Building 617. Insulate Lighting Vault Building 723. Install air conditioning to accommodate new airfield lighting control system on Moody AFB, GA.

Update #1 ·

RECOVERY: THIS NOTICE IS PROVIDED FOR INFORMATION PURPOSES ONLY. THIS OPPORTUNITY IS AVAILABLE TO THE SIMPLIFIED ACQUISITION BASE ENGINEERING REQUIREMENT (SABER) CONTRACTOR, MOODY AFB, GA.

DETAILED DISCRIPTION


The purpose of this project will be to replace 210,000 linear feet of existing homerun circuits feeding airfield lighting from Building 723 on Moody AFB, GA. All work must conform to Moody Air Force Base Electrical Standards. Work to be performed during non-flying hours and coordinated with Base Airfield Management. Contractor to provide 3 fully integrated touch screen controls for all airfield lighting at the Control Tower and Bldg 723 on Moody AFB, GA. The new control system will replace an antiquated toggle control system and provide Airfield Management, Base Civil Engineering, and Emergency 911 the ability to provide emergency landing and maintenance control capabilities. All work must comply with Moody AFB Electrical Standards. Contractor to will completely insulate and install a 15 Ton HVAC system to heat and cool Building 724 on Moody AFB, GA. Contractor shall provide all electrical and HVAC equipment to maintain ideal temperature to extend life of approximately 12 airfield lighting regulators. All work must comply with Moody Air Base Standards and building codes.