Recovery -- project number KNMD081036 - repair aircraft arresting systems, (runways 4R and 8R), hickam AFB, hawaii

Award Notice Posted

Solicitation number
FY09-15CONS-008
Agency
Awarded
to Allied Pacific Builders Inc.
Set-aside
No set-aside

Opportunity facts

Contract number
W912J6-08-D-0002-TN01 Federal contract award
NAICS code
237310 Highway, Street, and Bridge Construction
PSC
Not on record
Place of performance
Runway 4R AND 8R Hickam Afb, Hawaii Honolulu, Hawaii 96853, United States

Notice details come from SAM.gov. Updated .

Notice text

5 versions

Update #5 · Latest ·

TAS::57 3404::TAS RECOVERYPROJECT#KNMD081036::RP# ENTITLED REPAIR AIRCRAFT ARRESTING SYSTEMS,RUNWAY 4R AND 8R, HICKAM AFB, HAWAII::YES::ARRA

This modification to this task order is to extend the performance period for 320 calendar days, with a competion date of 11 Jan 2011, awaiting delivery of Government-Furnished Equipment (Arresting System Engine) due to be delivered on Nov 2011.


It is in the best interest of the government to wait for the new arresting system engine, and determine the actual engine bolt pattern to secure the engines. This will eliminate the possibility of bolt reinstallation cost if the bolt pattern is inaccurate.


"NOTICE: Pursuant to Federal Acquisition Regulation paragraph 4.1501, the contractor is hereby informed that all products and services provided by this contract/order are funded by and subject to the terms and conditions of the American Recovery and Reinvestment Act of 2009."

Update #4 ·

TAS::57 3404::TAS RECOVERYPROJECT#KNMD081036::RP# ENTITLED REPAIR AIRCRAFT ARRESTING SYSTEMS,RUNWAY 4R AND 8R, HICKAM AFB, HAWAII::YES::ARRA

This modification is issued to incorporate the contractor's 100 percent design submittals, including drawings dated 15 Mar 2010. Also, extends performance period to an additional 175 days, completion date 1 Mar 2011, awaiting delivery of Government-Furnished Equipment (Arresting Systems) due 1 Nov 2010.

Update #3 ·

This Admin Modification was issued to add ARRA Statement in accordance with FAR 4.1501.

Update #2 ·

RECOVERY - PER FAR 5.7 THIS NOTICE IS PROVIDED FOR INFORMATION PURPOSES ONLY; THEREFORE FAR 5.203 DOES NOT APPLY.  THIS OPPORTUNITY WAS AVAILABLE ONLY TO CONTRACTOR(S) UNDER THE IDIQ MATOC COMPETITIVE CONTRACTS WITH THE HAWAII NATIONAL GUARD, HICKAM AFB, HAWAII FOR REPAIR AIRCRAFT ARRESTING SYSTEMS, RUNWAY 4R AND 8R, KNMD 08-1036 AT HICKAM AFB, HAWAII

Update #1 ·

RECOVERY: REPAIR AIRCRAFT ARRESTING SYSTEMS (RUNWAY 4R AND 8R) AT HICKAM AFB, HAWAII. THIS NOTICE IS PROVIDED FOR INFORMATION PURPOSES ONLY.  THIS OPPORTUNITY IS ONLY AVAILABLE TO BE COMPETED WITH HAWAII AIR NATIONAL GUARD MATOC DESIGN BUILD CONTRACTORS.  WORK ON THIS PROJECT FOR DESIGN/BUILD SERVICES THAT INCLUDES REPLACE THE TWO-ROLLER DECK SHEAVES OF THE TWO BAK-12 BARRIER SYSTEMS ON THE 4R AND 8R RUNWAYS WITH THREE-ROLLER DECK SHEAVES.  WORK INCLUDES THE REMOVAL OF THE EXISTING DECK SHEAVES, REPLACEMENT OF DECK SHEAVE FOUNDATIONS TO SUIT NEW 3-ROLLER DECK SHEAVES, AND INSTALLATION OF THE NEW 3-ROLLER DECK SHEAVES.  REPAIR DETERIORATED CONCRETE FOOTINGS AND PIT FLOORS.  REPAIR/REPLACE EXISTING DRAINAGE SUMP AND PUMPS, EXHAUST SYSTEM, AND EXPLOSION PROOF LIGHTING.

On GovTribe

Work this opportunity

  • Track it in your pipeline
  • Find teaming partners
  • Similar opportunities
  • Ask GovTribe AI about this opportunity