RECOVERY: Lochsa Powell Pavement Rehabilitation, Clearwater NF
Award Notice Posted
- Solicitation number
- AG-82B1-S-10-0440
- Agency
-
Operations Center Intermountain
Economic Recovery Operations, Department of Agriculture
- Awarded
- to K.c. Equipment, Inc.
- Set-aside
- No set-aside
Opportunity facts
- Contract number
- AG-82B1-C-10-0369 Federal contract award
- NAICS code
- 237310 Highway, Street, and Bridge Construction
- PSC
- Not on record
- Place of performance
- Powell and Lochsa Ranger Districts, Clearwater National Forest, United States
Notice details come from SAM.gov. Updated .
Notice text
3 versions
Update #3 · Latest ·
Amendment No 1, replace Wage Determination
Update #2 ·
Sealed Bids are due to Intermountain EROC, July 23, 2010, 1:00.
Update #1 ·
THIS IS AN AMERICAN RECOVERY AND REINVESTMENT ACT (ARRA) PROCUREMENT. The resulting contract will utilize funds provided by the AMERICAN RECOVERY AND REINVESTMENT ACT (ARRA) OF 2009. Interested parties are notified that the inclusion of unique provisions required in implementing the Act, including those for significant reporting and transparency, will be required of the successful bidder.
The purpose of this announcement is to make notice the Forest Service contemplates releasing an Invitation for Bid (IFB) on or about June 24, 2010. If the IFB is released, it will be released through this FedBizOpps website, and prospective vendors should visit this FedBizOpps website from time to time on or after June 24, 2010 to obtain a copy of the solicitation. This requirement is being solicited as an IFB under FAR Part 14. Bids are due at July 23, 2010; 12:00 P.M. (MT). A single firm-fixed price type contract will be awarded to the responsible bidder based upon price and price related factors.
ALL Sealed Bid SHOULD BE MAILED TO:
USDA/FOREST SERVICES
ATTN: PHYLLIS R. COBURN-HARRIEL
740 SIMMS ST GOLDEN, CO 80401
REF SOL#: AG-82B1-S-10-0424
PROJECT DESCRIPTION.
This project consists of asphalt repair with surface preparation and asphalt placement. Work includes skin patch, repair potholes and crack sealing with and without routing. Install corrugated metal pipe, including excavation, removal and disposal of unsuitable material. Chip seal, and asphalt pavement sealcoat.
The magnitude of this project IAW FAR 36.204 (c) is between $500,000 and $1,000,000.
There will not be a pre-bid meeting/site visit held on this project.
Projected start date is July 2010 with completion not later than October 30, 2010
Performance and Payments will be required per the Miller Act and Davis-Bacon wage rates will apply.
PROJECT LOCATION.
Project #1, Powell Ranger Station is located at MP 161.78 off US Highway 12. From Orofino, Idaho travel east on highway 12 to mile post 161.78 and junction of Powell Ranger station. Follow signs to ranger station (approximately 1 mile).
Project #2, Powell Access Road is Located at MP 161.78 off US Highway 12.
Project #3, Powell Campground is located off the Powell Ranger Station road.
Project #4, Wendover Campground is located at MP 158.22 on US Highway 12 on the right.
Project #5, Wilderness Gateway Campground is located at MP 122.63 on US Highway 12.
(Additive Item ) Whitehouse Campground is located at MP 158.50 on US Highway 12.
Files
| File | Type | Posted |
|---|---|---|
| Amend1_attachment_General Decision Number.docx | DOCX document | |
| Amend1_LochsaPowell.doc | DOC document | |
| Drawings_PowellLochsa.pdf | ||
| sol_pkg.doc | DOC document | |
| FSSS.docx | DOCX document | |
| WageDeterminationDB_ID100015.docx | DOCX document |
On GovTribe
Work this opportunity
- Track it in your pipeline
- Find teaming partners
- Similar opportunities
- Ask GovTribe AI about this opportunity