Recovery--F--recovery-santa ANA land mitigation (SARM), riverside county, california, project no. 075354

Award Notice Posted

Solicitation number
W912PL-09-R-0014
Agency
Awarded
to ACS Habitat Management, Inc.
Set-aside
No set-aside

Opportunity facts

Contract number
W912PL-09-C-0039 Federal contract award
NAICS code
541620 Environmental Consulting Services
PSC
Not on record

Notice details come from SAM.gov. Updated .

Notice text

3 versions

Update #3 · Latest ·

The project consists of removal of arundo and other non-native vegetation species, habitat restoration, endangered species management and cowbird trapping and maintenance for a base year plus four option years.

Update #2 ·

RECOVERY--
RECOVERY--The project will consist of Removal of arundo and other non-native vegetation species, habitat restoration, endangered species management and cowbird trapping with five years of maintenance, to mitigate for Santa Ana River Mainstem (SARM) construction project.

The estimated cost of this project is $5,000,000 to $10,000,000.

NOTE: This project was authorized for construction under the American Recovery and Reinvestment Act (ARRA of 2009).

NOTE: This procurement is issued under full and open competition without exclusion of sources. When applicable, FAR 52.219-4, Notice of Price Evaluation Preference for HUBZone Small Business Concerns will be applied to this action.

ALL OFFERORS/BIDDERS ARE ADVISED THAT THIS PROJECT MAY BE DELAYED, CANCELED OR REVISED AT ANY TIME DURING THE SOLICITATION, SELECTION, EVALUATION, NEGOTIATION AND/OR FINAL AWARD PROCESS.

ORDERING SOLICITATION: The solicitation will be available on or about 18 August 2009. The solicitation will not be provided in hard paper copy. The solicitation and all amendments for this Request for Proposal will be posted on www.fbo.gov Viewing/downloading documents from fbo.go will require prior registration in Central Contractor Registration (www.ccr.gov). Please note that ALL firms who want to access the solicitation, both prospective primes and subcontractors, must be CCR-registered, have a MPIN, and either a DUNS number or CAGE code.

Sub-contracting plans are required for all construction contracts awarded to a large business when the award amount exceeds $1,000,000.00. If the offeror/bidder is a large business, the firm will be required to submit a sub-contracting plan. The plan shall be prepared in accordance with FAR 52.219-9. Failure to submit an acceptable sub-contracting plan may make the offeror/bidder ineligible for award of the contact. To be acceptable, the plan must adequately address the six required statutory elements and provide sufficient information to enable the Contracting Officer to answer affirmatively questions A through H of appendix DD, Part 2, AFARS 19.705. The Los Angeles District subcontracting goals are specific percentages of the contractors total planned subcontract amount. The goals are as follows: 70% with small business; 6.2% with small disadvantaged business; 7.0% with woman owned small business; .9% with service disabled veteran owned small business; 3.0% with veteran-owned small business and 9.8% with hub zone small business. All interested contractors are reminded that the successful contractor will be expected to place subcontracts to the maximum practicable extent with small and disadvantaged firms in accordance with the provisions of Public Law 95-507.

IT IS THE RESPONSIBILITY OF THE CONTRACTOR TO CHECK WWW.FBO.GOV FREQUENTLY FOR ANY AMENDMENTS OR CHANGES TO THE SOLICITATION. THE GOVERNMENT IS NOT RESPONSIBLE FOR ANY LOSS OF INTERNET CONNECTIVITY OR FOR AN OFFERORS INABILITY TO ACCESS THE DOCUMENTS POSTED AT THE REFERENCED WEBSITE. NO CDs OR HARD COPIES WILL BE MADE AVAILABLE.

If you would like to list your firm so that others can see you are an interested vendor, you must click the Add Me to Interested Vendors button in the listing for this solicitation on www.fbo.gov.

Update #1 ·

RECOVERY--
RECOVERY--The project will consist of Removal of arundo and other non-native vegetation species, habitat restoration, endangered species management and cowbird trapping with five years of maintenance, to mitigate for Santa Ana River Mainstem (SARM) construction project.

The estimated cost of this project is $5,000,000 to $10,000,000.

NOTE: This project was authorized for construction under the American Recovery and Reinvestment Act (ARRA of 2009).

NOTE: This procurement is issued under full and open competition without exclusion of sources. When applicable, FAR 52.219-4, Notice of Price Evaluation Preference for HUBZone Small Business Concerns will be applied to this action.

ALL OFFERORS/BIDDERS ARE ADVISED THAT THIS PROJECT MAY BE DELAYED, CANCELED OR REVISED AT ANY TIME DURING THE SOLICITATION, SELECTION, EVALUATION, NEGOTIATION AND/OR FINAL AWARD PROCESS.

ORDERING SOLICITATION: The solicitation will be available on or about 18 August 2009. The solicitation will not be provided in hard paper copy. The solicitation and all amendments for this Request for Proposal will be posted on www.fbo.gov Viewing/downloading documents from fbo.go will require prior registration in Central Contractor Registration (www.ccr.gov). Please note that ALL firms who want to access the solicitation, both prospective primes and subcontractors, must be CCR-registered, have a MPIN, and either a DUNS number or CAGE code.

Sub-contracting plans are required for all construction contracts awarded to a large business when the award amount exceeds $1,000,000.00. If the offeror/bidder is a large business, the firm will be required to submit a sub-contracting plan. The plan shall be prepared in accordance with FAR 52.219-9. Failure to submit an acceptable sub-contracting plan may make the offeror/bidder ineligible for award of the contact. To be acceptable, the plan must adequately address the six required statutory elements and provide sufficient information to enable the Contracting Officer to answer affirmatively questions A through H of appendix DD, Part 2, AFARS 19.705. The Los Angeles District subcontracting goals are specific percentages of the contractors total planned subcontract amount. The goals are as follows: 70% with small business; 6.2% with small disadvantaged business; 7.0% with woman owned small business; .9% with service disabled veteran owned small business; 3.0% with veteran-owned small business and 9.8% with hub zone small business. All interested contractors are reminded that the successful contractor will be expected to place subcontracts to the maximum practicable extent with small and disadvantaged firms in accordance with the provisions of Public Law 95-507.

IT IS THE RESPONSIBILITY OF THE CONTRACTOR TO CHECK WWW.FBO.GOV FREQUENTLY FOR ANY AMENDMENTS OR CHANGES TO THE SOLICITATION. THE GOVERNMENT IS NOT RESPONSIBLE FOR ANY LOSS OF INTERNET CONNECTIVITY OR FOR AN OFFERORS INABILITY TO ACCESS THE DOCUMENTS POSTED AT THE REFERENCED WEBSITE. NO CDs OR HARD COPIES WILL BE MADE AVAILABLE.

If you would like to list your firm so that others can see you are an interested vendor, you must click the Add Me to Interested Vendors button in the listing for this solicitation on www.fbo.gov.

Files

File Type Posted
Am1.pdf PDF
W912PL-09-R-0014 final.pdf PDF

On GovTribe