U.S. ARMY CORPS OF ENGINEERS


SAN FRANCISCO DISTRICT


1455 Market Street, 15th Floor


San Francisco, CA 94103


CESPN-ET-EW August 3, 2009



Scope of Services


for:



CONTRACT NO.: W912P7-06-D-0001

TASK ORDER: TBD

CONTRACTOR: Towill, Inc.

PROJECT: Comprehensive Evaluation of Project Datums (CEPD)

TITLE: ICW ARRA Funded Datums Evaluations

Page 2 of 79




1. General



The Comprehensive Evaluation of Project Datums (CEPD) is a USACE initiative that:


...describes specific procedural actions immediately required to evaluate the accuracy


and adequacy of existing flood protection elevations or controlling navigation depths


relative to federal datums established by the Department of Commerce and prescribed


for government-wide use by the Federal Geographic Data Committee (FGDC). This


guidance implements lessons learned from the Interagency Performance Evaluation


Task Force (IPET) study conducted after Hurricane Katrina, as identified in Volume


II (Geodetic Vertical and Water Level Datums) of the 1 June 2006 draft version of


the Final IPET Report-see https://ipet.wes.army.mil. It is specifically intended to


ensure that USACE project controlling elevations and datums are properly and


accurately referenced to nationwide spatial reference systems used by other Corps


Districts or Federal, state, and local agencies responsible for flood forecasting,


inundation modeling, flood insurance rate maps, bathymetric mapping, and


topographic mapping.


CEPD is a multi-step process involving 1) a Datums Evaluation Report, 2)


Implementation of Corrective Actions, and 3) updating the project design, if necessary.


Information on USACE requirements for CEPD can be found in EC 1110-2-6065,




Comprehensive Evaluation of Datums - Guidance for a Comprehensive Evaluation of


Vertical Datums on Flood Control, Shore Protection, Hurricane Protection, and


Navigation Projects


(2 April 2007) (http://140.194.76.129/publications/engcirculars/



ec1110-2-6065/toc.htm.) Additional guidance was recently provided in ER


1110-2-8160 Policies for Referencing Project Elevation Grades to Nationwide Vertical. http://140.194.76.129/publications/eng-regs/er1110-2-8160/toc.html.


Datums


This Scope of Work covers review of project documents and preparation of the Datums


Evaluation Report. Implementation of Corrective Actions and updating project design


are not included in this Task Order.



2. Obligation of Surveyor - Engineer (S-E)



The S-E will provide services and submittals as detailed in the following sections. It


shall be the S-E's responsibility to review all available USACE San Francisco District


documents to complete the Datums Evaluation Reports.


S-E shall notify TPOC as least 2 days prior to any site visit, so that appropriate building


security notifications can be made. S-E will have to follow standard building access


requirements during each visit (photo, badge, escort, etc).


S-E will need to visit both the USACE San Francisco District, San Francisco Office


(1455 Market St) and Sausalito Construction Office to review project files. It may also


be advantageous to visit Construction project field offices (xx). S-E may also wish to


contact project sponsors to obtain additional data, however USACE project manager must


be contacted and authorization to contact sponsors received on a project by project basis.


Page 3 of 79


S-E shall maintain a log of all contact with USACE personnel (other than TPOC) and


sponsors. If S-E does not receive a response from USACE personnel after 3 tries (at least


one of which should be in writing via email), TPOC shall be notified.


S-E shall not assume USACE copy machines are available. USACE copy machines are


not always operational or are in heavy use by USACE personnel, and S-E shall not claim


delays as a consequence. S-E may use USACE copy machines in Room 1585 as long as


no hardship is imposed on USACE personnel. Large format copier is also available in


Room 1551.


S-E shall catalog and identify physical location for all documents referenced and/or


removed from USACE offices and copy provided to TPOC after each visit. All reports,


maps, data and other information shall be returned to USACE office and replaced exactly


where borrowed from within one week of removal.



3. Obligation of the Government



Government TPOC will be available for guidance and comments on all work under this


contract. Any comments, advice and/or guidance given by the Government TPOC will


be to assist the S-E in performing the work and will not change this scope of services or


release the S-E from performing all work required unless written notification of such,


signed by the Contracting Officer or the CO's designated representative (COR).


For each project, TPOC shall provide the name and contact information for Project


Manager, Engineering Technical Lead (ETL) (if one exists) and Hydraulic Engineer (if


one exists). Many projects do not have an ETL or a Hydraulic Engineer. TPOC shall be


primary technical contact for projects where these do not exist. For GI-CG and O&M


projects - government will also provide information on project authorization,


appropriation and type of project. For FCCE projects, project authorization will need to


be identified by S-E, appropriation shall be identified as FCCE. See below for definitions


of project types.



4. Contractor Services



Tasks are defined based on groups of projects from various USACE programs. Project


groups have been setup almost solely for accounting (RFP) purposes. Once contract is


awarded priorities and S-E's preferred approach (geographic, etc) will be discussed at


kick-off meeting. Most likely the SPN priority shall be CG, GI, O&M, FCCE. But


District is also willing to be flexible if S-E considers an alternative approach to be more


efficient.


Projects are identified as either FCCE (Flood Control and Coastal Emergency), O&M


(Operation & Maintenance), GI (General Investigation), or CG (Construction General).


Projects designated here as Flood Control and Coastal Emergency (FCCE) are typically


Page 4 of 79


projects constructed by a non-federal sponsor, that have been found eligible to receive


federal assistance under Public Law 84-99, for disaster preparedness, emergency


operations and/or rehabilitation of flood control works. These projects must meet


specific federal requirements for maintenance and operation and are inspected biannually


by the USACE to verify continued eligibility. It is anticipated that S-E will


find very few supporting documents for FCCE projects.


GI and CG projects are part of the USACE Civil Works program. Typically GI projects


are in the study or design phase, while CG projects are in construction. However there


are also several CG projects at the San Francisco District that are in the study phase, but


because they are already constructed and in operation, they received CG funds and are


therefore referred to as CG projects even though, there is no currently on-going


construction. An example of this is the Sacramento Deep Water Ship Channel. It


currently has an operational depth of 30 feet MLLW, however there is an active study to


evaluate deepening the project to 35 feet MLLW or some intermediate increment.


O&M projects are projects where construction is complete and project is operated by the


USACE, such as many of our navigation projects.


The Contractor's services shall include the following items for all Tasks.


S-E will need to visit both the USACE San Francisco District, San Francisco Office


(1455 Market St., POC: Anne K Sturm) and Sausalito Construction Office to review


project files. It may also be advantageous to visit Construction project field offices. S-E


may also wish to contact project sponsors to obtain additional data, however USACE


project manager must be contacted and authorization to contact sponsors received on a


project by project basis. S-E shall maintain a log of all contact with USACE personnel


(other than TPOC) and sponsors. If S-E does not receive a response from USACE


personnel after 3 tries (at least one of which should be in writing via email), TPOC shall


be notified.


S-E shall notify TPOC as least 2 days prior to any visit to USACE offices, so that


appropriate building security notifications can be made. At 1455 Market St., S-E will


have to follow standard building access requirements during each visit (photo, badge,


escort, etc).


S-E shall catalog and identify physical location for all documents referenced and/or


removed from USACE offices and copy provided to TPOC after each visit. All reports,


maps, data and other information shall be returned to USACE office and replaced exactly


where borrowed from within one week of removal.


S-E shall complete the Comprehensive Evaluation of Project Datums (CEPD) Evaluation


Report for each project. Even when multiple projects appear to be part of the same


system, a separate report must be completed for each project. A template report and an


example of a completed report are included with this Scope of Work as Attachments 1


Page 5 of 79


and 2. All report sections shall be completed by S-E. The completed CEPD Evaluation


Report will be submitted to TPOC for review and approval.


Report shall assess the adequacy and accuracy of reference datums and survey control for


the subject project and meet the requirements of EC 1110-2-6065. The evaluation report


includes, but is not limited to, the following elements: identify and document all project


survey control monuments and benchmarks; document existing NSRS connections;


identify any legacy survey control (e.g. NAD27, NGVD29) and provide conversions


between legacy datums and NAVD88; and, document basis for all source hydraulic


elevations, including gages, and their survey control. If information is available, S-E


shall identify datums and elevation data used in hydrodynamic models. Project must


meet a relative and absolute vertical accuracy requirement of 0.25 feet. Though TPOC


may direct the use an alternate vertical accuracy on a project by project basis. Use of


Vertcon for datum conversions is not an acceptable option for either existing project


control or corrective action.


At a minimum, project must be referenced to the North American Datum 1983 (NAD83),


National Spatial Reference System (NSRS) 2007, epoch of 2007.00 or later, and the


North American Vertical Datum of 1988 ( NAVD88). Recommended geoid model shall


be GEOID09. GEOID09 release is expected by late September 2009. Any alternation of


this control shall be accompanied by an explanation from S-E.


Once a Draft Datums Evaluation Report is completed for a project, it shall be submitted


to TPOC for review. TPOC comments shall be provided to S-E within 2 weeks of receipt


of draft report. Teleconference may be held should the S-E have any questions regarding


comments. Final Datums Evaluation Report shall be submitted to TPOC two weeks after


receipt of comments.


This contract is being funded from the American Recovery and Reinvestment Act


(ARRA) (Stimulus) funds. Therefore Contractor must complete quarterly reporting


requirements as defined in Attachment 3. At the time with SOW is being issued,


reporting website is not yet active. TPOC will work with Contractor to fulfill reporting


requirements.



Task A: FCCE Group A



Task includes project review and completion of Datums Evaluation Report. See details


above. S-E shall assume 2 meetings - one kick-off meeting and one meeting following


completion of first few reports.


CAD and/or GIS files of the FCCE project alignments are available in various coordinate


systems. It should be noted that these are approximate alignments based on field


inspections. Any waypoints shown on figures are related to a specific inspection event


and not related to any project specific control.


Page 6 of 79


All FCCE projects are flood control projects including either leveed channel, incised


channels, and/or incised channel. Task covers the following projects:


1. Reach 3: J-3, Martin Cr., Alameda Zone 7, Figure 1


2. Reach 4: J-1, Big Canyon Cr., Alameda Zone 7, Figure 1


3. Reach 5: J, S. San Ramon Cr., Alameda Zone 7, Figure 1


4. Reach 6: T, Dublin Cr., Alameda Zone 7, Figure 1


5. Reach 8: F; u/s, Alamo Creek, Alameda Zone 7, Figure 1


6. Reach 9: F; u/s, Alamo Canal, Alameda Zone 7, Figure 1


7. Reach 10: G-1; u/s, Chabot Canal, Alameda Zone 7, Figure 1


8. Reach 12: G-1-1; midway, Old Alamo Cr., Alameda Zone 7, Figure 1


9. Reach 13: F; d/s, Alamo Canal, Alameda Zone 7, Figure 1


10. Reach 14: F1; d/s, Tehan Creek, Alameda Zone 7, Figure 1


11. Reach 15: K, Tassajara Cr., Alameda Zone 7, Figure 1


12. Reach 16: G-3, Croak Cr., Alameda Zone 7, Figure 1


13. Reach 17: G; d/s, Arroyo Mocho, Alameda Zone 7, Figure 1


14. Reach 18: G; midway, Arroyo Mocho, Alameda Zone 7, Figure 1


15. Reach 19: B-5, d/s, Pleasanton Canal, Alameda Zone 7, Figure 1


16. Reach 22: E; 3rd reach, Arroyo Del Valle, Alameda Zone 7, Figure 1


17. Reach 23: E; d/s, Arroyo Del Valle, Alameda Zone 7, Figure 1


18. Reach 24: G; u/s, Arroyo Mocho, Alameda Zone 7, Figure 1


19. Reach 25: H; d/s, Arroyo Las Positas, Alameda Zone 7, Figure 1


20. Reach 26: M, Collier Cr., Alameda Zone 7, Figure 1


21. Reach 27: H; 3rd reach, Arroyo Las Positas, Alameda Zone 7, Figure 1


22. Reach 28: P; midway, Arroyo Seco, Alameda Zone 7, Figure 1


Page 7 of 79


23. Reach 29: P-1; d/s, Patterson Cr., Alameda Zone 7, Figure 1


24. Reach 30: H; 2nd reach, Arroyo Las Positas, Alameda Zone 7, Figure 1


25. Reach 31: H; u/s, Arroyo Las Positas, Alameda Zone 7, Figure 1


26. Reach 32: R; d/s, Altamont Cr., Alameda Zone 7, Figure 1


27. Reach 33: H; u/s, Arroyo Las Positas, Alameda Zone 7, Figure 1


28. Reach 34: R-1, Vasco Cr., Alameda Zone 7, Figure 1


29. Reach 35: B; u/s, Arroyo de la Laguna, Alameda Zone 7, Figure 1


30. Reach 36: B; d/s, Arroyo de la Laguna, Alameda Zone 7, Figure 1


31. Reach 38: B-2-2; midway, Pleasanton Cr., Alameda Zone 7, Figure 1


32. Calpella WTP, Russian R., w. br., Mendocino FC&WCD, Figure 2


33. Black, J. Prop. 3, Russian R., Sonoma WA, Figure 3


34. Allcoast Lumber, Russian R., Sonoma WA, Figure 4


35. Cloverdale City, Russian R., Sonoma WA, Figure 5


36. Soledad City, Salinas R., Monterey WA, Figure 6


37. Butte #1, Butte Cr., Siskiyou FC&WCD, Figure 7


38. Butte #3, Butte Cr., Siskiyou FC&WCD, Figure 8


39. Sam's Neck, Meiss Lake, Siskiyou FC&WCD, Figure 9



Option Task B through Task E will be awarded subject to the availability of funds and at


the discretion of the Contracting Officer.



Option Task B: FCCE Group B



Task includes project review and completion of Datums Evaluation Report. See details


above.


CAD and/or GIS files of the FCCE project alignments are available in various coordinate


systems. It should be noted that these are approximate alignments based on field


Page 8 of 79


inspections. Any waypoints shown on figures are related to a specific inspection event


and not related to any project specific control.


All FCCE projects are flood control projects including either leveed channel, incised


channels, and/or incised channel. Task covers the following projects:


40. Zone 2, A, Estudillo Canal, Alameda FC&WCD, Figure 10


41. Zone 2, G, Chabot Cr., Alameda FC&WCD, Figure 11


42. Zone 2, K, Sulfur Cr., Alameda FC&WCD, Figure 12


43. Zone 3A, B, Ward Cr., Alameda FC&WCD, Figure 13


44. Zone 3A, D, Old Alameda Cr., Alameda FC&WCD, Figure 14


45. Zone 5, L, Dry Cr., Alameda FC&WCD, Figure 15


46. Zone 5, M, Masonic Home Cr., Alameda FC&WCD, Figure 16


47. Zone 6, E, Laguna Cr., Alameda FC&WCD, Figure 17


48. Zone 6, Alameda PWP, Coyote Cr., Alameda FC&WCD, Figure 18


49. Zone 12, A, Temescal Cr., Alameda FC&WCD, Figure 19


50. Zone 12, E, Sausal Cr., Alameda FC&WCD, Figure 20


51. Zone 12, I, Seminary Cr., Alameda FC&WCD, Figure 21


52. Zone 12, J, Lion Cr., Alameda FC&WCD, Figure 22


53. Zone 12, K, Arroyo Viejo, Alameda FC&WCD, Figure 23


54. Zone 12, M, Elmhurst Canal, Alameda FC&WCD, Figure 24


55. Zone 12, P, Up. San Leandro Cr., Alameda FC&WCD, Figure 25



Option Task C: GI_CG Group A



Task includes project review and completion of Datums Evaluation Report. See details


above.


56. Bay Farm Island Dike - Shore Protection (CG), Figure 26


Page 9 of 79


Shore Protection project located along the south side of San Leandro Channel and


San Leandro Bay between Bay Farm Island Bridge and the confluence of San


Leandro Channel and Airport Channel.


57. Corte Madera Creek - Flood Control Project, Figure 27


Corte Madera Creek and its tributaries drain an area of 28 square miles in Marin


County, California, and discharge into the west side of San Francisco Bay nine miles


north of the Golden Gate Bridge. The flood control project has been built in separate


units.


58. Estudillo Canal - Single Purpose Flood Risk Management, Figure 28


The study area is located within the City of San Leandro, California and about 15


miles southeast of San Francisco. The watershed drains into the San Francisco Bay,


with a drainage area of approximately 10 square miles. A substantial number of


properties within this densely populated area are designated as being in a Federal


Emergency Management Agency floodplain. The study will evaluate potential flood


damage reduction alternatives in a highly developed area.


59. Hamilton Airfield Wetland Restoration - Environmental Restoration (CG), Figure


29


The project site is located on San Pablo Bay, four miles east of the city of Novato, in


Marin County, California, and includes 988 acres of a former military airfield and


adjacent California State Lands Commission areas. The levee-protected site has


subsided below the elevation of surrounding properties, including the tidal wetlands


immediately adjacent to San Pablo Bay. This wetlands restoration project would


advance the beneficial reuse of dredge material from San Francisco Bay as part of the


Long Term Management Strategy (LTMS). The California State Coastal Conservancy


is the non-Federal sponsor.


60. Laguna de Santa Rosa - Environmental Restoration, Figure 30


The Laguna de Santa Rosa, a tributary of the Russian River, is located approximately


13 miles west of the city of Santa Rosa in Sonoma County, California. Historically,


this area has served as a naturally occurring 7,000-acre storm detention basin during


flooding of the Russian River, and is a valuable coastal fresh water wetland. The local


community believes that siltation has reduced the ability of the Laguna de Santa Rosa


to function as a major flood basin, and that thousands of acres of wetlands habitat


have been lost or degraded. Endangered species (steelhead trout and red-legged frogs)


are being negatively impacted due to this loss of habitat. The study will investigate


and evaluate solutions to the siltation problem in order to restore both the storm


detention function and wetland habitat of the area.


61. Larkspur Ferry Channel - Navigation (O&M) , Figure 31


This project consists of maintenance dredging of the main navigation channel to a


depth of -13 feet Mean Lower Low Water (MLLW) for a length of 13,560-feet and a


width of 232-feet wide, with a -15 feet MLLW Turning Basin at the channel


Page 10 of 79


terminal. The non-Federal sponsor, Golden Gate Bridge, Highway and Transportation


District, provides ferryboat transit service between Marin County and San Francisco.


62. Las Gallinas 205 - Flood Control (CG) , Figure 32


Las Gallinas Creek is located east of Highway 101 in the Santa Venetia area of Marin


County, about 10 miles north of San Francisco. Las Gallinas Creek is vulnerable to


extreme high tides and heavy storm runoff, and the existing levee system is


approaching the end of its useful life. A Section 205 flood damage reduction study


was initiated under the Continuing Authorities Program (CAP).


63. Napa River Salt Marsh - Environmental Restoration (CG) , Figure 33


This project is a shallow-draft channel, mainly light commercial and recreational


navigation. The operations and maintenance schedule provides for 6-year cycle


maintenance dredging for the Napa River Channel to -15 feet Mean Lower Low


Water (MLLW) from Mare Island Strait Causeway to Asylum Slough (down-stream


portion); thence -10 feet MLLW to head of navigation at the Third Street Bridge in


the City of Napa (up-stream portion). The project is approximately 16 miles long.


64. Ocean Beach - Shore Protection , Figure 34


Ocean Beach forms the western boundary of the City of San Francisco, California,


extending 3.3 miles along the Pacific Ocean coastline. The City of San Francisco, the


local sponsor, desires Corps assistance with developing and implementing a suitable


long-term coastal storm damage prevention plan. The beach itself is part of the larger


National Park Service Golden Gate National Recreation Area, and is recognized as a


uniquely valuable coastal resource within an urban environment. San Francisco


maintains municipal infrastructure on City property along the coastline, including the


Great Highway and the Lake Merced Sewage Transport Tunnel. The area falls within


the jurisdiction of the California Coastal Commission under the California Coastal


Act.


65. Oyster Point Harbor - Navigation (CG) , Figure 35


The City of South San Francisco owns Oyster Point Marina/Park, a 600-berth


recreational/commercial marina located adjacent to a variety of business parks,


including the headquarters for Genentech, approximately ten miles south of San


Francisco and two miles north of San Francisco International Airport. The 46-acre


facility includes picnic areas, jogging trails, a recreational fishing pier, bait shop,


small boat marine service and sales center, existing and proposed hotels, restaurants


and offices. Since 1977, the San Mateo County Harbor District has operated Oyster


Point Marina/Park under a Joint Powers Agreement with the City. A concrete


breakwater protects the Marina; however, there is a need to modify the entrance of


the harbor to provide safe navigation for current tenants of the marina, as well as


dinner cruise boats and a commuter ferry expected to begin operations in 2008. The


ferry is expected to provide NED benefits and reduce traffic and pollution impacts in


the Bay Area.


66. Pajaro River Watsonville - Single Purpose Flood Risk Management, Figure 36


Page 11 of 79


The existing flood damage reduction project, located in Santa Cruz and Monterey


Counties, California, consists of levees and channel improvements on the Pajaro


River and Corralitos and Salsipuedes Creeks constructed in 1949 to provide 50-year


flood protection to the Watsonville area. While the project remains capable of


successfully passing the flow rate it was originally designed for, the current level of


flood protection is about 8-15 years. This study will develop a locally acceptable plan


for flood protection features along the Pajaro River and Corralitos and Salsipuedes


Creeks in order to increase the level of flood protection afforded by the project.


67. Petaluma River - Flood Damage Reduction (CG) , Figure 37


The Petaluma River is located in Sonoma and Marin Counties, California on San


Pablo Bay. Project operations and maintenance provides for maintenance dredging of


a channel 200 feet wide and -8 feet deep across the flats in San Pablo Bay to the


mouth of the river; thence 100 feet wide and -8 feet deep to Western Avenue in


Petaluma, including a turning basin 300 to 400 feet wide and -8 feet deep. The City of


Petaluma is the local sponsor and is responsible for providing a suitable upland


disposal site.


68. Sacramento DWSC - Navigation (CG) , Figure 38


The Sacramento River Deep Water Ship Channel Project is a Congressionally


authorized project being implemented by the U.S. Army Corps of Engineers (Corps)


and the Port of Sacramento. Currently, the Corps and the Port of Sacramento are


conducting a Limited Reevaluation Study to recommend navigation improvements


for Federal funding and preparing a joint Supplemental Environmental Impact


Statement and Subsequent Environmental Impact Report (SEIS/SEIR) to evaluate the


action of resuming construction of navigational improvements to the Sacramento


River Deep Water Ship Channel (SRDWSC).


The SRDWSC runs from the Contra Costa county line to the Port of Sacramento. The


SRDWSC is located in the Sacramento - San Joaquin Delta region of northern


California. The 46.5-mile long ship channel lies within Contra Costa, Solano,


Sacramento, and Yolo Counties and serves the marine terminal facilities at the Port of


Sacramento. The SRDWSC joins the existing 35-feet deep channel at New York


Slough, thereby affording the Port of Sacramento access to San Francisco Bay Area


harbors and the Pacific Ocean.


69. San Pedro Creek, Pacifica - Flood Risk Management (CG) , Figure 39


San Pedro Creek lies in the Linda Mar area of Pacifica, California, along the Pacific


coast just south of San Francisco. The area has been subjected to severe damaging


floods, with approximately 100 acres subject to flooding. During the most recent


flood event in 1982, 183 residential and 10 commercial units suffered damages


exceeding $4 million. The project will use a floodwall plan and diversion-wetlandbypass


plan developed by the local sponsor as their preferred plan.


70. San Rafael Creek - Navigation, Figure 40


Page 12 of 79


San Rafael Creek is located north of San Francisco Bay in Marin County. This project


is a shallow-draft, mainly light commercial and recreational, channel. The operations


and maintenance schedule provides for 7 and 4-year cycle maintenance dredging,


respectively, for the Across the Flats Channel to -8 feet Mean Lower Low Water


(MLLW) in San Francisco Bay to the mouth of San Rafael Creek; thence -6 feet


MLLW for the Inner Canal Channel to the head of navigation at the Grand Street


Bridge in the City of San Rafael. The Across the Flats portion has always been


authorized for unconfined in-Bay aquatic disposal at site SF-11 south of Alcatraz


Island.


71. San Ramon Valley Recycled Water Project - Section 219 Environmental


Infrastructure (CG) , Figure 41


The project is located in the San Ramon Valley, approximately 25 miles east of San


Francisco, in the California counties of Contra Costa and Alameda. The project area


runs from Danville south to Dublin. The project will facilitate the use of recycled


water to replace potable water for landscape irrigation. The Corps' portion of this


project will include the design of one pump station and 6,500 feet of pipeline.


72. Santa Rosa Creek Ecosystem Restoration - Environmental Restoration, Figure 42


The Santa Rosa Creek watershed encompasses approximately 80 square miles,


including the City of Santa Rosa, in Sonoma County, California. Santa Rosa Creek, a


tributary to the Russian River, was channelized by the Soil Conservation Service in


the 1960s to provide flood control protection to the surrounding City of Santa Rosa.


The existing flood control structures have resulted in habitat loss. The sponsor


initiated this study in 1999 to restore the degraded areas and re-establish parts of the


creek as an area to restore salmonid spawning habitat. A draft hydrologic study,


completed in August 2002, concluded that the predicted one percent flows on the


Santa Rosa Creek significantly exceeds the current capacity of the existing flood


control structures. The sponsor has reviewed the Corps' Hydrologic study and has


requested that flood damage reduction measures be incorporated as a purpose of this


study.


73. SF Bay to Stockton - Navigation (CG) , Figure 43


The project consists of deep draft navigation channels, extending from the San


Francisco Bay entrance to the Port of Stockton, through San Francisco, Marin, Contra


Costa, Solano, Sacramento, and San Joaquin Counties. The Corps is assessing the


feasibility of deepening the existing 35-foot channel. The Port of Stockton is the non-


Federal sponsor for the study and Contra Costa County is a project partner.


74. Sonoma Creek & Tributaries - Environmental Restoration, Figure 44


The study area is located in Sonoma County, California. The Sonoma Creek


watershed drains a 170-square mile area into the northern reaches of the San


Francisco Bay estuary. This study was originally funded as part of the overall San


Pablo Bay Watershed Management Study as provided in the Energy & Water


Appropriations Act of 1998. The findings of this study indicate a Federal interest in


Page 13 of 79


providing solutions for environmental restoration and flood protection to Sonoma


Creek and its tributaries.


75. Upper Guadalupe River - Flood Damage Reduction (CG) , Figure 45


The Upper Guadalupe River study area is located in the City of San Jose, Santa Clara


County, California. The river reach proposed for this project begins at Interstate


Highway 280, at the edge of downtown San Jose, and extends south for


approximately 5.5 miles. The proposed project utilizes a combination of bypass


channels, floodwalls, and some channel widening to achieve flood damage reduction,


and is expected to aid the long term recovery of riparian forest habitat and salmonoid


migration.



Option Task D: GI_CG Group B



Task includes project review and completion of Datums Evaluation Report. See details


above.


76. Arroyo de la Laguna - Flood Damage Reduction & Environmental Restoration,


Figure 46


Arroyo de la Laguna is located in Alameda County, about 25 miles southeast of San


Francisco. Arroyo de la Laguna collects and drains runoff from Livermore, Dublin


and Pleasanton into Alameda Creek; a number of tributaries extend into Contra Costa


and Santa Clara Counties. The upper basin is approximately 15 miles wide, 45 miles


long and covers about 398,000 acres. The current Reconnaissance Study would


evaluate Federal interest in solutions to potential flooding and associated damage to


surrounding riparian habitat.


77. Bolinas Lagoon Restoration - Ecosystem Restoration, Figure 47


Bolinas Lagoon is a tidal embayment located 15 miles northwest of San Francisco, on


the Marin County coastline between the towns of Stinson Beach and Bolinas. The


lagoon is part of the Gulf of the Farallones National Marine Sanctuary managed by


the National Oceanic and Atmospheric Administration. Sedimentation in the lagoon


is causing a continuous loss of important subtidal and intertidal aquatic habitat,


resulting in a reduction of the diversity and abundance of aquatic life. The goal of the


environmental restoration effort is to ameliorate the adverse human impacts to


Bolinas Lagoon, thereby promoting the natural, dynamic processes of this


internationally-recognized estuarine environment. Although, over the long term,


sediment deposition will continue to fill the lagoon, the restoration project is intended


to significantly slow the present rate of intertidal and subtidal habitat loss.


78. FPMS San Mateo Co Levee Survey - Survey, Support to Others, Figure 48


Project would involve implementation of a USACE survey.


79. Pier 36 Removal - unknown (CG) , Figure 49


USACE support leading to plans and specifications for removal of Pier 36.


Page 14 of 79


80. Salt River Restoration - Ecosystem Restoration, CAP 206 (CG) , Figure 50


The Salt River is a tributary of the Eel River located near the town of Ferndale, in


Humboldt County, California. It originates in the Wildcat Mountains above Ferndale,


flows across the Eel River delta, and enters the Eel River within one mile of the


Pacific Ocean. This area lies in the 4th largest estuary in California and provides


habitat for two federally and state listed endangered species: the Brown Pelican and


Peregrine Falcon. The proposed Salt River Restoration Project is expected to restore


approximately two miles of riparian and wetland habitats along the Salt River, which


has been experiencing major ecosystem degradation due to sedimentation and


drainage problems. Project solutions under consideration include tide gate removal


and dredging to control excess sedimentation, and riparian restoration. The proposed


project is also expected to incidentally reduce future flooding and infrastructure


disasters. The non-Federal sponsor is the Humboldt County Resource Conservation


District (RCD).


81. San Francisco Bay Delta Model & Base Yard - Existing Infrastructure, Figure 51


San Francisco Bay Delta Model Regional Visitor Center is located in Sausalito,


California. The Center currently serves over 150,000 visitors annually, 60% of them


school children, fulfilling the Corps Strategic Communication goals, providing public


and curriculum-based school tours, special events, workshops, and seminars on the


Corps' modern missions within the context of the environmental, cultural, and


historical issues of the Bay Area. The center piece is a hydraulic scale model covering


one and one-half acres that was once used to reproduce existing and proposed


conditions of the San Francisco Bay and Estuary. Exhibits and programs explain


technical aspects of the model and the role of the Corps in water resource


developments in the Bay Area and throughout the Nation. The Regional Bay Model


Visitors Center works in cooperation with the Bay Model Association, which is a


non-profit organization. One of their main programs is the JASON project, which


provides school children scientific exploration of environments around the world


through video hookups at the Bay Model. Sponsors for this program include National


Geographic, NASA, and NOAA.


82. St Helena - Flood Risk Management and Environmental Restoration, Figure 52


The project is located approximately 60 miles north of San Francisco, in the City of


St. Helena, Napa County, California. The proposed project would provide rearing,


resident, and migratory habitats for Federally listed threatened and endangered


species and remove barriers to fish migration. The project would reconnect the Napa


River with restored aquatic, riparian and upstream habitat along the Napa River. The


City of St. Helena is the non-Federal Sponsor.


83. Upper Penitencia Creek - Single Purpose Flood Risk Management, Figure 53


Upper Penitencia Creek is located in the City of San Jose, in Santa Clara County,


California. The project is intended to reduce flood damages in San Jose and Milpitas.


Alternatives under consideration for this 3.6-mile reach include a combination of


flood-proofing at the upstream limit, levees, floodwalls and bypass channels.


Page 15 of 79



Option Task E: GI_CG Group C



Task includes project review and completion of Datums Evaluation Report. See details


above.


Watershed studies are very general in nature and eventually lead to specific projects


within the watershed. The datums evaluation in this case must also be general,


identifying existing resources in the region and any shortcomings.


84. Arana Gulch Watershed - Watershed Study , Figure 54


This Ecosystem Restoration study was authorized by the House Transportation and


Infrastructure Committee Resolution dated June 25, 1999. The study area is located in


Santa Cruz County, California, adjacent to the Port of Santa Cruz. The study area


includes 2,200 acres of coastal watershed and seven miles of stream. The study will


involve a collaborative watershed planning effort to restore passage for endangered


anadromous fish, restore native riparian vegetation, improve water quality, improve


connectivity of the upper habitat, and reduce erosion and sedimentation throughout


the watershed. Additionally, the


beneficial use of sediment from the stream and harbor is being considered as part of a


Regional Sediment Management initiative.


85. Corte Madera Creek 209 - Watershed Study, Figure 55


The project study area is located in Marin County, California. Corte Madera Creek


and its tributaries drain an area of 28 square miles into the west side of San Francisco


Bay, nine miles north of the Golden Gate Bridge. This study will examine


improvements to stream function and flood damage reduction by exploring potential


physical and management measures including storm water management,


development, and sedimentation measures, as well as creek and habitat improvements


and maintenance. Local groups have requested a watershed study to examine


potential constructed and management improvements to the function of the


watershed, both to improve migration of the threatened Steelhead (et al) and reduce


flood damages.


86. Laguna Creek Watershed - Watershed Study, Figure 56


The study area is located within the City of Fremont, California about 28 miles


southeast of San Francisco. The watershed drains into the San Francisco Bay, with a


drainage area of approximately 25 square miles. This study will evaluate potential


flood damage reduction alternatives in a highly developed area.


87. Napa Valley Watershed Mgmt - Watershed Study, Figure 57


The Napa Valley Watershed is located within the northern portion of the San Pablo


Bay drainage basin in Napa County, California. The purpose of this study is to


complete a watershed analysis of the Napa River Watershed in order to address


watershed problems and opportunities through water and related land resource


management.


Page 16 of 79


88. Pajaro River Basin Study - Watershed Study, Figure 58


This project is a watershed study centering on the Pajaro River, and includes the


California counties of Santa Clara, Santa Cruz, Monterey and San Benito. The study


will focus on flood protection, ecosystem restoration solutions and other purposes


such as recreation and water supply for the entire 12,000-square-mile watershed.


89. Russian River Watershed - Watershed Study, Figure 59


The Russian River Watershed encompasses 1,485 square miles (approx. 950,000


acres) within Sonoma and Mendocino Counties, California. This watershed study will


look at opportunities to prevent or reduce flood damages, to restore riverine


ecosystem values and the wise use of floodplains, to restore watershed functions


through restorative land-use practices, and to conserve remaining hydrologic and


ecological resources. The result of Phase I was the formation of the Russian River


Watershed Council, with the mission to protect, restore, and enhance the biological


health of the Russian River and its watershed through a community-based process,


facilitating communication and collaboration among all interested parties. The Plan of


Action for Phase II (POA) was also completed in Phase I. The POA articulates


critical issues and potential actions, and can be found at website




http://www.rrwc.net.


Phase II will include the completion of a Russian River



Watershed Adaptive Management Plan (WAMP).


90. San Pablo Bay Watershed, CA - Watershed Study, Figure 60


The San Pablo Bay Watershed Project addresses near, mid, and long-term restoration


and flood protection in the San Pablo Bay Watershed. The non-Federal sponsor for


the project is the State Coastal Conservancy. The San Pablo Bay Watershed is in the


northern reach of the San Francisco Estuary, an area whose population is projected to


increase by two million people during the next three decades. Innovative planning


and construction approaches can minimize the environmental impacts caused by this


growth and corresponding changes in land uses, including directing population and


land use changes away from critical resources such as wetland and riparian habitats.


The San Pablo Bay Watershed Restoration Program (Program) provides technical,


planning, and design assistance for restoration and flood protection in order to clarify


restoration parameters, goals, and objectives, and to identify and prioritize future


restoration opportunities. The technical, planning, and design assistance provided to


the Program supports resources protection for the construction of replacement


wetlands, protection from additional pollution, and creation of habitats to increase the


biodiversity and habitat values in the watershed.


91. Upper York Creek Dam - Aquatic Ecosystem Restoration, Figure 61


The project is located approximately 60 miles north of San Francisco, in the City of


St. Helena, Napa County, California. Upper York Creek Dam is an earthen dam built


around the turn of the 20th century. Its reservoir served as a water supply for the City


of St. Helena. The proposed project would create and restore approximately two acres


of channel, riparian, and upland habitat near the dam. It would also reconnect


approximately two miles of stream corridor habitat and associated upland habitat,


improving water quality and rearing, resident, and migratory habitats for Federally


Page 17 of 79


listed threatened and endangered species. The non-Federal project sponsor is the City


of St. Helena.



5. Submittals


I. Monthly Safety Exposure Report



The S-E shall submit the "USACE Summary of Contractor Work-Related Injuries and


Illnesses" and "USACE PRIME CONTRACTOR, Monthly Record of Work-Related


Injuries/Illnesses & Exposure in electronic spreadsheet format and signed hard copy


reports through e-mail and by mail.


It is required that contractors to submit the two forms in excel format and these two forms


in excel formats can be downloaded from the link below:


http://www.hnd.usace.army.mil/safety/Safety_Pol_Reg_Docs.aspx


Under "General Safety and Occupational Health" Table, pick the first row from the table


"29 CFR 1904", right column from the 20 CFR 1904, "USACE Prime Contractor


Monthly Record of Accidents and Exposure Hours".



II. Draft Submittal



1. Draft Datums Evaluation Report


2. Electronic copy of any key documentation (do not require full document, cover page


and key pages acceptable). Location of original document should be identified.



III. Final Submittal



1.Final Datums Evaluation Report


Page 18 of 79



6. Schedule



First draft datums evaluation report is due 6 weeks after NTP. Periodic submittals shall


be made no less than every 2 weeks thereafter. All draft datums evaluation reports are


due 6 months after NTP.


TPOC comments shall be provided to S-E within 2 weeks of receipt of draft report.


Final Datums Evaluation Report shall be submitted to TPOC two weeks after receipt of


comments.


Contractor may recommend alternative schedule with justification.


7. Applicable Standards

Surveyor-Engineer shall be responsible for notifying the Contracting Officer of any


missing criteria needed for his work.


The following technical references (or most recent version) shall be used for the work


and services and are available online at http://www.usace.army.mil/inet/usace-docs/engmanuals/


cecw.htm. unless listed otherwise:


1. Comprehensive Evaluation of Project Datums, EC 1110-2-6065, 1 July 2007, USACE.


2. Hydrographic Surveying, EM 1110-2-1003, 1 June 2002, change 1 April 2004,


USACE.


3. Topographic Surveying, EM 1110-1-1005, 31 August 1994, USACE.


4. Photogrammetric Mapping, EM 1110-1-1000, 31 July 2002, USACE.


5. Federal Geographic Data Committee. Geospatial Accuracy Standards, Part 3:


National Standard for Spatial Accuracy (1998), which is an update of Office of


Management.


6. American Society for Photogrammetry and Remote Sensing (ASPRS) Accuracy


Standards for Large-Scale Maps (31 March 1993) The ASPRS, as it is applied to


USACE projects, is explained in EM 1110-1-1000.


7. EM 1110-1-1002, Survey Markers and Monumentation dated 14 September 1990.


8. EM 1110-1-1003, NAVSTAR Global Positioning System Surveying dated 1 July 2003.


9. EM 1110-1-1004, Engineering and Design - Geodetic and Control Surveying, dated 01


June 2002.




 



 