2 versions
Update #2 · Latest ·
RECOVERY - PER FAR 5.7 THIS NOTICE IS PROVIDED FOR INFORMATION PURPOSES ONLY; THEREFORE FAR 5.203 DOES NOT APPLY. THIS OPPORTUNITY WAS AVAILABLE ONLY TO CONTRACTOR(S) UNDER THE CURRENT CONTRACT NUMBER(S): W9127N08D0003
The U.S. Army Corps of Engineers, Portland District (USACE - Portland) has issued Task Order 15 under Contract W9127N08D0003 for the preparation of a main unit powerhouse study for Philpott Powerhouse located north of Bassett, Virginia. The goal of the study is to identify design paramters for all pieces of equipment so that, when all equipment is rehabilitated or replaced, all pieces are compatible with each other. The final product shall be a study report identifying: design parameters (primarily power output), cost, procurement time, and installation outage time for the power train components.
Update #1 ·
RECOVERY - PER FAR 5.7 THIS NOTICE IS PROVIDED FOR INFORMATION PURPOSES ONLY; THEREFORE FAR 5.203 DOES NOT APPLY. THIS OPPORTUNITY IS AVAILABLE ONLY TO CONTRACTOR(S) UNDER THE CURRENT CONTRACT NUMBER(S): W9127N08D0003
The U.S. Army Corps of Engineers, Portland District (USACE - Portland) intends to issue Task Order 15 under Contract W9127N08D0003 for the preparation of a main unit powerhouse study for Philpott Powerhouse located north of Bassett, Virginia. The goal of the study is to identify design paramters for all pieces of equipment so that, when all equipment is rehabilitated or replaced, all pieces are compatible with each other. The final product shall be a study report identifying: design parameters (primarily power output), cost, procurement time, and installation outage time for the power train components.