RECOVERY--C--Project Number 107070 St. Francis West Bank Seepage Study ross-sections and topographic survey

Award Notice Posted

Solicitation number
W912EQ-09-R-0018
Agency
Awarded
Set-aside
No set-aside

Opportunity facts

Contract number
W912EQ-10-D-0002-TASK ORDER 0007
NAICS code
541370 Surveying and Mapping (except Geophysical) Services
PSC
Not on record
More information

Notice details come from SAM.gov. Updated .

Notice text

4 versions

Update #4 · Latest ·

RECOVERY - PER FAR 5.7 THIS NOTICE IS PROVIDED FOR INFORMATION PURPOSES ONLY; THEREFORE FAR 5.203 DOES NOT APPLY. THIS OPPORTUNITY WAS AVAILABLE ONLY TO CONTRACTOR(S) UNDER THE CURRENT CONTRACT NUMBER(S): Contractor: EMC, Incorporated, Contract Number: W912EQ-10-D-0014

This contract action was accomplished using other than competitive procedures because this is a task/delivery order where an exception to fair opportunity requirements was approved as this is a follow-on order to a competitive initial order (FAR 8.405-6(b)(2) or 16.505(b)(2)(iii).

The AE shall develop cross-sections and general topographic data along 10 miles of St Francis River (west bank) levee in the vicinity of Clay County, AR and Greene County, AR.

Update #3 ·

RECOVERY - PER FAR 5.7 THIS NOTICE IS PROVIDED FOR INFORMATION PURPOSES ONLY; THEREFORE FAR 5.203 DOES NOT APPLY. THIS OPPORTUNITY WAS AVAILABLE ONLY TO CONTRACTOR(S) UNDER THE CURRENT CONTRACT NUMBER(S): Contractor: Johnson-McAdams Surveying and Mapping, L.L.C.. Contract Number: W912EQ-10-D-0002,

This contract action was accomplished using other than competitive procedures because this is a task/delivery order where an exception to fair opportunity requirements was approved as this is a follow-on order to a competitive initial order (FAR 8.405-6(b)(2) or 16.505(b)(2)(iii).

The Architect-Engineer (AE) shall develop cross-sections and general topographic data along 8 miles of St. Francis River (left bank) levee in the vicinity of Dunklin County, AR.

Update #2 ·

The AE shall develop cross-sections and general topographic data along 13 miles of proposed new canals from its beginning at the proposed reservoir at 2000 ft. west of County Road 85 to the proposed crossing at Baker Bayou approximately 1.1 mile west of Highway 31 in Lonoke County, AR, as shown on attached maps and attachments and as described below. In addition, the A-E shall develop digital terrain models at 2 ft. contour intervals at 19 designated sites (proposed bridges and other proposed structures and siphon locations) within the project area. New baselines and vertical control sufficient for future construction shall be established, and utilities, roadways, houses (including finish floor elevations), and other man-made features within the survey limits shall be located.

Update #1 ·

RECOVERY - PER FAR 5.7 THIS NOTICE IS PROVIDED FOR INFORMATION PURPOSES ONLY; THEREFORE FAR 5.203 DOES NOT APPLY. THIS OPPORTUNITY IS AVAILABLE ONLY TO CONTRACTOR(S) UNDER: W912EQ-10-D-0002

The Architect-Engineer(AE) shall Develop Cross-sections and general topographic data along 8 miles of St. Francis River (left Bank) levee in the vincinity of Dunklin County, AR.

Notice history

Notice Type Posted
This notice Latest Award Notice
A-Services Award Notice
Indefinite delivery type architect-engineer contract (S) for survey engineering, mapping, and related services within the boundaries or assignments of the mississippi valley division Original Award Notice