Purifier, centrifuga

Closed Solicitation Posted

Solicitation number
N0010426QTA63
Agency
Naval Supply Systems Command Department of the Navy, Department of Defense
Responses due
Set-aside
No set-aside

Opportunity facts

NAICS code
333998 All Other Miscellaneous General Purpose Machinery Manufacturing
PSC
4330 Centrifugals, Separators, And Pressure And Vacuum Filters
Points of contact

Notice details come from SAM.gov. Updated .

About this opportunity

The Department of the Navy Naval Supply Systems Command is seeking quotations for the repair and evaluation of four centrifugal purifiers (NSN 7HH 4330-01-425-4236). The primary objective is to obtain teardown, evaluation, repair, and/or modification services for these units with a target repair turnaround time (RTAT) of 150 days. Contractors must submit quotes that include unit price, total price, and their proposed RTAT, with Government Source Inspection (GSI) required as part of the evaluation process. The solicitation is issued under Emergency Acquisition Flexibilities with bilateral award procedures, meaning the contractor's written acceptance will be required prior to contract execution. The solicitation was posted on January 15, 2026, with a response deadline of January 16, 2026. Contractors unable to meet the government's required RTAT must provide detailed capacity constraints explaining their constraints, and price reductions may apply if the contractor fails to achieve the specified turnaround time.

This solicitation carries no set-aside designation and is classified under NAICS 333998 (All Other Miscellaneous General Purpose Machinery Manufacturing) and PSC 4330 (Centrifugals, Separators, and Pressure and Vacuum Filters). No incumbent contractor or specific award value is identified in the solicitation materials. The procurement involves four units of the specified centrifugal purifier with a 0-00 shelf life requiring complete teardown and evaluation. Freight will be managed by the Navy through the Commercial Asset Visibility (CAV) Statement of Work, eliminating logistics responsibility from the contractor. The place of performance is the United States, and contractors must verify nomenclature, part number, and NSN prior to submitting their response to ensure accuracy and compliance with government requirements.

Notice text

2 versions

Update #2 · Latest ·

ITEM UNIQUE IDENTIFICATION AND VALUATION (JAN 2023)|19||||||||||||||||||||

INSPECTION OF SUPPLIES--FIXED-PRICE (AUG 1996)|2|||

WIDE AREA WORKFLOW PAYMENT INSTRUCTIONS (JAN 2023)|16|Invoice & Receiving Report Combo||TBD|N00104|TBD|TBD|see sked|TBD|||TBD||||||

NAVY USE OF ABILITYONE SUPPORT CONTRACTOR - RELEASE OF OFFEROR INFORMATION (3-18))|1|WSS|

NOTICE OF CYBERSECURITY MATURITY MODEL CERTIFICATION LEVEL REQUIREMENTS (NOV 2025))|1||

LIMITATION OF LIABILITY--HIGH-VALUE ITEMS ($100K)(FEB 1997)|1||

ALTERNATE A, ANNUAL REPRESENTATIONS AND CERTIFICATIONS (OCT 2025)|13||||||||||||||

ANNUAL REPRESENTATIONS AND CERTIFICATIONS (MAR 2025)(DEVIATION 2025-O0003 AND2025-O0004))|13|333998|500||||||||||||

NOTICE OF PRIORITY RATING FOR NATIONAL DEFENSE, EMERGENCY PERPARDENESS, AND ENRGY PROGAM USE (APRIL 2008))|2||x|

Amendment issued becuase the solicitation did not post to SAM when it was issued. The solicitation is now on Contract Opportunities via SAM.gov.

This solicitation is issued pursuant to Emergency Acquisition Flexibilities (EAF).

The resultant award of this solicitation will be issued bilaterally, requiring the contractor's written acceptance prior to execution. Verify nomenclature, part number, and NSN prior to responding.

Please note freight is handled by the Navy as per the Commercial Asset Visibility (CAV) Statement of Work.

The Government is seeking a Repair Turnaround Time (RTAT) of: 150 Days

Government Source Inspection (GSI) is required.

Your quote should include the following information:

QUOTE AMOUNT AND RTAT

- Unit Price:__________

- Total Price:__________

- Repair Turnaround Time (RTAT): _______ days

If your company is not quoting the Government's Required Repair Turnaround Time (RTAT) or earlier, provide your company's capacity constraints.

_________________________________________________________________

_________________________________________________________________

_________________________________________________________________

Repair Turnaround Time (RTAT): the resultant contractual delivery requirement is measured from asset Return to the date of asset acceptance under the terms of the contract. For purposes of this section, Return is defined as physical receipt of the F-condition

asset at the contractor's facility as reflected in the Action Date entry in the Commercial Asset Visibility (CAV) system. In accordance with the CAV Statement of Work, the contractor is required to accurately report all transactions by the end of the fifth regular

business day after receipt and the Action Date entered in CAV must be dated to reflect the actual date of physical receipt. The Contractor must obtain final inspection and acceptance by the Government for all assets within the RTATs established in this contract.

Check one: Firm-fixed-Price ___ Estimated ___

Return Material Authorization # (RMA), if applicable:__________

Delivery Vehicle (if Delivery Order requested) (if your company has a current BOA/IDIQ, for example) :__________________

TESTING AND EVALUATION IF BEYOND REPAIR

T&E fee/price (if asset is determined BR/BER):

AWARDEE INFO & PERFORMANCE LOCATION

- Awardee CAGE: __________

Inspection & Acceptance CAGE, if not same as "awardee CAGE": __________

Facility/Subcontractor CAGE (where the asset should be shipped), if not same as "awardee CAGE":__________

IOT COMPARE REPAIR PRICE TO PRICE TO BUY NEW

New unit price:__________

New unit delivery lead-time:__________

IMPORTANT NOTE: Any asset for which the contractor does not meet the required RTAT will incur a price reduction per unit/per month the contractor is late - any delay determined to be excusable (e.g. Government Delay) will not result in a price reduction. If a

price reduction is required due to unexcusable contractor delay, the Contracting Officer will implement the aforementioned price reduction via a "reconciliation modification" at the end of the contract performance. Price reductions made pursuant to this section

shall not limit other remedies available to the Government for failure to meet required RTATs, including but not limited to the Government's right to terminate for default.

In reference to the above important note, the contractor provides the following price reduction amount per unit per month the contractor does not meet the RTAT: $__________, up to a maximum of: $_________.

\

1. SCOPE

1.1 This contract/purchase order contains the requirements for repair and the contract quality requirements for the PURIFIER,CENTRIFUGA .

2. APPLICABLE DOCUMENTS - NOT APPLICABLE

3. REQUIREMENTS

3.1 Cage Code/Reference Number Items - The PURIFIER,CENTRIFUGA repaired under this contract/purchase order shall meet the operational and functional requirements as represented by the Cage Code(s) and reference number(s) listed below. All repair work shall

be performed in accordance with the contractors repair/overhaul standard practices, manuals and directives including but not limited to drawings, technical orders, manufacturing operations, tooling instructions, approved repair standards and any other

contractor or government approved documents developed to provide technical repair procedures.

CAGE___Ref. No.

;6K044 55N03/A-2902;

3.2 Changes in Design, Material Servicing, or Part Number - Except for a Code 1 change, which shall be processed as provided in the code statement shown below, no substitution of items shall be made until the NAVICP-MECH Contracting Officer has notified and

approval has been given by issuance of a written change order. When any change in design, material, servicing or part number is made to replace or substitute any item to be furnished on this contract/purchase order, the Contractor shall furnish, for the

substituting/replacement item, a drawing and an explanation of the reason for the change, explaining the reason therefor. If finished detail drawings are not available, shop drawings in the form used by the manufacturer will be acceptable for Government

evaluation. When notifying the Procurement Contracting Officer of the reasons for making substitutions, the type of change shall be indicated by code number in accordance with one of the following statements:

Code 1: PART NUMBER CHANGE ONLY - If the Manufacturer's Part Number indicated thereon has changed, but the parts are identical in all respects, supply the item and advise NAVICP-MECH immediately of the new part number.

Code 2: Assembly (or set or kit) not furnished - Used following detail parts.

Code 3: Part not furnished separately - Use assembly.

Code 4: Part redesigned - Old and new parts are completely interchangeable.

Code 5: Part redesigned - New part replaces old. Old part cannot replace new.

Code 6: Part redesigned - Parts not interchangeable.

4. QUALITY ASSURANCE

4.1 Responsibility for Compliance - All items must meet all requirements of this contract/purchase order. The inspection set forth in this specification shall become a part of the Contractor's overall inspection system or quality program. The absence of any

inspection requirements shall not relieve the Contractor of the responsibility of assuring that all products or supplies submitted to the Government for acceptance comply with all requirements of the contract/purchase order. Sampling in quality conformance

does not authorize submission of known defective material, either indicated or actual, not does it commit the Government to acceptance of defective material.

4.2 Records - Records of all inspection work by the Contractor shall be kept complete and available to the Government during the performance of contract/purchase order and for a period of 365 calendar days after final delivery of supplies.

5. PACKAGING- MIL-STD 2073 PACKAGING APPLIES AS FOUND ELSEWHERE IN THE SCHEDULE

6. NOTES - NOT APPLICABLE

Update #1 ·

QTY four NSN 7HH 4330 014254236 PP, Centrifugal Purifier. 

Attachments

Files attached to this notice, newest first
File Type Posted
3.01_RFQ_N0010426QTA63_25136-0063.pdf PDF