Procurement Opportunity Document (POD) for Medium Explorer Concept Spacecraft and On-Orbit Support

Closed Pre-Solicitation Posted

Solicitation number
2024_Helio_MIDEX_Concept_1_POD
Agency
Responses due
Set-aside
No set-aside

Opportunity facts

Notice details come from SAM.gov. Updated .

About this opportunity

NASA Goddard Space Flight Center (GSFC) is seeking teaming partners to serve as the satellite (spacecraft) integrator for a Heliophysics Medium Explorer (MIDEX) mission. The selected partner will be responsible for providing a spacecraft bus, instrument to spacecraft integration and environmental testing support, integration support for the observatory to launch vehicle, and optional mission operations support. The proposed mission is currently in pre-Phase A, and the next steps include a mission concept study and Concept Study Report, followed by a down-select in July 2027. NASA will evaluate responses based on technical approach, relevant experience, and cost/schedule factors, with a target Announcement of Opportunity release in July 2025 and a target launch readiness date of January 2032. The cost cap for this AO is $300M (FY25$), excluding launch vehicle, and NASA will provide partial funding for the Phase A concept study.

This pre-solicitation notice does not indicate any set-aside designations, and no potential incumbents or current contractors are named. The exact award value or budget range is not specified, but the cost cap for the AO is $300M (FY25$), excluding launch vehicle. The key numerical details include the target Announcement of Opportunity release in July 2025 and the target launch readiness date of January 2032.

Notice text

The partnership opportunity is being issued to select teaming partners to serve as the satellite (spacecraft) integrator for this MIDEX mission, which includes providing a spacecraft bus consistent with a Class C mission per NPR 8705.4 Risk Classification for NASA Payloads, instrument to spacecraft integration and environmental testing support (at the vendors facility), integration support for the observatory to launch vehicle, and support for mission operations. Also, as an option, the selected partner to provide a mission operations center.

NOTE: Upon selection, GSFC may discuss, and further tailor the roles proposed by respondents in the best interests of the proposal.

The proposed mission is currently in pre-Phase A. If the proposal is down selected, the next step in the proposal process is a mission concept study culminating in a Concept Study Report (CSR), followed by a Site Visit.

The following schedule should be used as a basis for responses to this opportunity:

Helio MIDEX Draft AO Released: April 2025 (target)

Helio MIDEX AO Released: July 2025 (target)

Pre-proposal conference: ~3 weeks after final AO release

Step-1 proposal due: 90 days after AO release

Selection for competitive Phase A studies: April 2026 (target)

Concept Study Reports (CSRs) due: 9 months after selection

Step-2 down select: July 2027 (target)

AO required Launch Readiness Date: January 2032 (TBR)

Files

File Type Posted
Helio MIDEX POD - Concept 1.pdf PDF

On GovTribe

Work this opportunity

  • Track it in your pipeline
  • Find teaming partners
  • Similar opportunities
  • Ask GovTribe AI about this opportunity