About this opportunity

The U.S. Army Corps of Engineers, Portland District, intends to issue an RFP for repair and refurbishment of two Generator Step-Up (GSU) power transformers (T9 and T10) with an option for a third (T11) at The Dalles Dam in The Dalles, Oregon, with a response deadline of August 13, 2026. The Government will award one Firm-Fixed-Price construction contract using Best Value Tradeoff source selection.

Work is performed at The Dalles Dam, Oregon. The Government seeks qualified contractors with demonstrated experience performing inspection, repair, refurbishment, oil processing, testing, and return-to-service activities for large Class II oil-filled power transformers rated at or above 230 kV and 100 MVA. Experience at hydroelectric generation facilities, utility substations, or comparable high-voltage industrial power facilities is highly desirable. The transformers are General Electric three-phase units manufactured in 1973 with 230 kV Grounded Wye / 13.2 kV Delta voltage rating, 208 MVA capacity, FOA cooling class, and approximately 14,600 gallons of insulating oil. The project addresses deterioration and failure of high-voltage neutral conductor components identified in prior forensic investigations. Scope includes internal inspection, detailed inspection and repair reports, engineering evaluation, repairs to restore reliability and extend operational life, oil processing, factory testing, and return-to-service activities.

Notice text

2 versions

Update #2 · Latest ·

The U.S. Army Corps of Engineers (USACE), Portland District, intends to issue a Request for Proposals (RFP) for the repair and refurbishment of two (2) Generator Step-Up (GSU) power transformers (T10 and T9), with an option for repair and refurbishment of a third transformer (T11), located at The Dalles Dam in The Dalles, Oregon.

The Government intends to award one Firm-Fixed-Price construction contract utilizing a Best Value Tradeoff source selection process.

The Government is seeking qualified contractors with demonstrated experience performing inspection, repair, refurbishment, oil processing, testing, and return-to-service activities for large Class II oil-filled power transformers rated at or above 230 kV and 100 MVA. Experience performing similar work at hydroelectric generation facilities, utility substations, or comparable high-voltage industrial power facilities is highly desirable.

The work generally consists of furnishing all labor, supervision, equipment, materials, transportation, testing, engineering support, and incidental services necessary to inspect, repair, refurbish, test, and return to reliable operational service existing Generator Step-Up (GSU) power transformers.

The transformers are General Electric three-phase GSU transformers manufactured in 1973 with the following characteristics:

  • Voltage Rating: 230 kV Grounded Wye / 13.2 kV Delta
  • Capacity Rating: 208 MVA
  • Cooling Class: FOA
  • Insulating Oil Quantity: Approximately 14,600 gallons
  • Transformer Type: Class II oil-filled power transformers

The project was developed following previous transformer failures and forensic investigations that identified deterioration and failure of high-voltage neutral conductor components. The repair effort is intended to restore transformer reliability and extend operational life.

The work includes, but is not limited to:

  • Internal inspection of existing transformers and preparation of detailed inspection and repair reports.
  • Engineering evaluation of transformer condition and recommended repair actions.
  • Repair and refurbishment of Class II oil-filled GSU transformers rated at or above 230 kV and 100 MVA.
  • Removal, inspection, repair, replacement, and reinstallation of high-voltage and low-voltage bushings.
  • Removal and reinstallation of transformer-mounted devices and accessories.
  • Replacement of gaskets and repair or replacement of internal transformer conductors as required.
  • Evaluation of transformer windings, connections, terminals, and insulation systems for evidence of overheating, deterioration, burns, discoloration, or deposits.
  • Transformer oil draining, temporary storage, containment, disposal, vacuum processing, hot-oil filling, and installation of new insulating oil.
  • Transformer electrical and oil testing before and after repair activities, including insulation resistance, power factor, winding resistance, turns ratio, bushing power factor, leakage reactance testing, and Sweep Frequency Response Analysis (SFRA).
  • Preparation of test reports and documentation required to demonstrate successful completion of repair activities.
  • Optional replacement of oil cooling pump isolation valves.
  • Optional repair and refurbishment of Generator Step-Up Transformer T11.

At the Contractor's discretion, transformers may be transported to an off-site repair facility for inspection and refurbishment. If the Contractor selects this approach, the Contractor shall be responsible for all transportation, rigging, logistics, environmental compliance, security, and restoration requirements associated with movement of the equipment.

Procurement Information

  • Acquisition Method: Competitive Negotiated Acquisition
  • Source Selection: Best Value Tradeoff
  • Contract Type: Firm-Fixed-Price
  • NAICS Code: 238210 – Electrical Contractors and Other Wiring Installation Contractors
    • SBA Size Standard: $19.0 Million
  • PSC Code: Z2MD – Repair or Alteration of Electric Power Generation Facilities – Hydroelectric
  • Set-Aside: None
  • Magnitude of Construction: $5,000,000.00 - $10,000,000.00

The anticipated period of performance will be identified in the solicitation.

Performance and Payment Bonds will be required as applicable in accordance with the solicitation requirements.

Applicable wage determinations and labor requirements will be incorporated into the solicitation, as applicable.

A site visit is anticipated following issuance of the solicitation. Site visit information, registration requirements, and access procedures will be provided in the solicitation.

This project will be performed within an operating federal hydroelectric facility. Contractor personnel shall comply with all applicable safety, security, environmental, and operational requirements identified in the solicitation documents.

The solicitation, specifications, drawings, and amendments will be made available electronically through SAM.gov. Interested parties are responsible for monitoring SAM.gov for solicitation updates.

This notice is issued solely for informational and planning purposes and does not constitute a solicitation. The Government reserves the right to cancel this requirement at any time. No reimbursement will be made for costs associated with responding to this notice or preparing for any future solicitation.

Update #1 ·

The U.S. Army Corps of Engineers (USACE), Portland District, intends to issue a Request for Proposals (RFP) for the repair and refurbishment of two (2) Generator Step-Up (GSU) power transformers (T10 and T9), with an option for repair and refurbishment of a third transformer (T11), located at The Dalles Dam in The Dalles, Oregon.

The Government intends to award one Firm-Fixed-Price construction contract utilizing a Best Value Tradeoff source selection process.

The Government is seeking qualified contractors with demonstrated experience performing inspection, repair, refurbishment, oil processing, testing, and return-to-service activities for large Class II oil-filled power transformers rated at or above 230 kV and 100 MVA. Experience performing similar work at hydroelectric generation facilities, utility substations, or comparable high-voltage industrial power facilities is highly desirable.

The work generally consists of furnishing all labor, supervision, equipment, materials, transportation, testing, engineering support, and incidental services necessary to inspect, repair, refurbish, test, and return to reliable operational service existing Generator Step-Up (GSU) power transformers.

The transformers are General Electric three-phase GSU transformers manufactured in 1973 with the following characteristics:

  • Voltage Rating: 230 kV Grounded Wye / 13.2 kV Delta
  • Capacity Rating: 208 MVA
  • Cooling Class: FOA
  • Insulating Oil Quantity: Approximately 14,600 gallons
  • Transformer Type: Class II oil-filled power transformers

The project was developed following previous transformer failures and forensic investigations that identified deterioration and failure of high-voltage neutral conductor components. The repair effort is intended to restore transformer reliability and extend operational life.

The work includes, but is not limited to:

  • Internal inspection of existing transformers and preparation of detailed inspection and repair reports.
  • Engineering evaluation of transformer condition and recommended repair actions.
  • Repair and refurbishment of Class II oil-filled GSU transformers rated at or above 230 kV and 100 MVA.
  • Removal, inspection, repair, replacement, and reinstallation of high-voltage and low-voltage bushings.
  • Removal and reinstallation of transformer-mounted devices and accessories.
  • Replacement of gaskets and repair or replacement of internal transformer conductors as required.
  • Evaluation of transformer windings, connections, terminals, and insulation systems for evidence of overheating, deterioration, burns, discoloration, or deposits.
  • Transformer oil draining, temporary storage, containment, disposal, vacuum processing, hot-oil filling, and installation of new insulating oil.
  • Transformer electrical and oil testing before and after repair activities, including insulation resistance, power factor, winding resistance, turns ratio, bushing power factor, leakage reactance testing, and Sweep Frequency Response Analysis (SFRA).
  • Preparation of test reports and documentation required to demonstrate successful completion of repair activities.
  • Optional replacement of oil cooling pump isolation valves.
  • Optional repair and refurbishment of Generator Step-Up Transformer T11.

At the Contractor's discretion, transformers may be transported to an off-site repair facility for inspection and refurbishment. If the Contractor selects this approach, the Contractor shall be responsible for all transportation, rigging, logistics, environmental compliance, security, and restoration requirements associated with movement of the equipment.

Procurement Information

  • Acquisition Method: Competitive Negotiated Acquisition
  • Source Selection: Best Value Tradeoff
  • Contract Type: Firm-Fixed-Price
  • NAICS Code: 238210 – Electrical Contractors and Other Wiring Installation Contractors
    • SBA Size Standard: $19.0 Million
  • PSC Code: Z2MD – Repair or Alteration of Electric Power Generation Facilities – Hydroelectric
  • Set-Aside: None

The anticipated period of performance will be identified in the solicitation.

Performance and Payment Bonds will be required as applicable in accordance with the solicitation requirements.

Applicable wage determinations and labor requirements will be incorporated into the solicitation, as applicable.

A site visit is anticipated following issuance of the solicitation. Site visit information, registration requirements, and access procedures will be provided in the solicitation.

This project will be performed within an operating federal hydroelectric facility. Contractor personnel shall comply with all applicable safety, security, environmental, and operational requirements identified in the solicitation documents.

The solicitation, specifications, drawings, and amendments will be made available electronically through SAM.gov. Interested parties are responsible for monitoring SAM.gov for solicitation updates.

This notice is issued solely for informational and planning purposes and does not constitute a solicitation. The Government reserves the right to cancel this requirement at any time. No reimbursement will be made for costs associated with responding to this notice or preparing for any future solicitation.

Notice history

Notice Type Posted
This notice Latest pre-solicitation Pre-Solicitation
Sources Sought - TDA Transformer 9-11 Interim Repair Pre-Solicitation
TDA Transformer 9-11 Interim Repair Solicitation
TDA Transformer 9-11 Interim Repair Pre-Solicitation
TDA Transformer 9-11 Interim Repair Original Pre-Solicitation

Similar open opportunities

Opportunity Agency Set-aside Responses due
Navigation lock tainter valve (TV) repair, TV1 The Dalles Dam (Washington side), Lyle, WA 98635. 98635 · NAICS 237990 ENDIST Portland No set-aside
John day DAM navigation lock tainter valve (TV) repairs TV3 and TV4 Location and Access Details. Oregon Side Physical Access, Near Rufus, OR 97050 accessible via I-84, Exit 109. Washington Side (Closest Town), Goldendale, WA 98620 approximately 20 miles north across the river. River Location, Mile 216.6 on the Columbia River, joining Sherman County, Oregon, and Klickitat County, Washington. 98628 · NAICS 237990 ENDIST Portland No set-aside
TDA Isolated Phase Bus and Duct Inspection The Dalles Dam in The Dalles, Oregon. Access to The Dalles Dam is from I-84 Exit 88 97058 · NAICS 541380 ENDIST Portland No set-aside
Bonneville Powerhouse II Unwatering Pump Replacement United States · NAICS 237990 ENDIST Portland Total Small Business
John Day Below-the-Hook Lifting Devices Repair and Recertification Rufus, Oregon 97050, United States · NAICS 811310 ENDIST Portland No set-aside

On GovTribe

Work this opportunity

  • Track it in your pipeline
  • Find teaming partners
  • Similar opportunities
  • Ask GovTribe AI about this opportunity

GovTribe for Federal Contractors