Operations Division Rock Supply
Awarded Award Notice Posted
- Solicitation number
- W912P821C0028
- Agency
- ENDIST New Orleans US Army Corps of Engineers, Department of Defense
- Awarded
- to Crowley Holdings LLC
- Set-aside
- No set-aside
Opportunity facts
- Contract number
- W912P821C0028 Federal contract award
- NAICS code
- 212319 Other Crushed and Broken Stone Mining and Quarrying
- PSC
- 9610 Ores
- Place of performance
- New Orleans, Louisiana 70118, United States
Notice details come from SAM.gov. Updated .
About this opportunity
This Award Notice from the Department of the Army Corps of Engineers Engineering District New Orleans awarded a contract to Crowley Holdings, LLC for $1,100,200 to supply a total of 11 loaded barges containing approximately 14,400 tons of Grade B stone to three locations - two barges to Schooner Bayou Control Structure, three barges to Freshwater Bayou Lock, and six barges to Catfish Point Control Structure - with each barge containing approximately 1,400 tons and delivery expected within 12 days of the initial barge delivery at each location.
Notice text
ITEM 001: The contractor will supply approximately 2 each loaded barges of B-size stone (or equivalent as approved by the government) to Schooner Bayou Control Structure located at Schooner Bayou, 3.1 miles west of Freshwater Bayou Mile 15.9. Each barge shall contain approximately 1,400 tons of Grade B stone (or equivalent as approved by the government). All delivered barges will start with a 5 day unloading period. All barges will be delivered at a coordinated period with the Government. The corps expects to receive 2 barges at the same time. When unloading is near completion on the barges, the government will coordinate the
pickup and return of the barge set.
ITEM 002: This item covers a demurrage 24 hour rental rate for each barge beyond the initial 5 days of barge delivery. This line will be activated only if the government holds any barge for longer than 5 days or 120 hours after its initial delivery.
ITEM 003: This item covers the delivery of loaded barges AND the pickup/return of unloaded barges associated with the rock supply to the Schooner Bayou Control Structure located at Schooner Bayou, 3.1 miles west of Freshwater Bayou Mile 15.9. The barge unloading time is expected to take up to 12 total days total starting at the initial delivery time of barges.
ITEM 004: The contractor will supply approximately 3 each loaded barges of B-size stone (or equivalent as approved by the government) to Freshwater Bayou Lock located at approximate Freshwater Bayou Channel Mile 1.5. Each barge shall contain approximately 1,400 tons of Grade B stone (or equivalent as approved by the government). All delivered barges will start with a 5 day unloading period. All barges will be delivered at a coordinated period with the Government. The corps expects to receive all 3 barges at the same time. When unloading is near completion on the set of barges, the government will coordinate the pickup
and return of the barge set. located at Schooner Bayou, 3.1 miles west of Freshwater Bayou Mile 15.9. Each barge shall contain approximately 1,400 tons of Grade B stone (or equivalent as approved by the government). All delivered barges will start with a 5 day unloading period. All barges will be delivered at a coordinated period with the Government.
ITEM 005: This item covers a demurrage 24 hour rental rate for each barge beyond the initial 5 days of barge delivery. This line will be activated only if the government holds any barge for longer than 5 days or 120 hours after its initial delivery.
ITEM 006: This item covers the delivery of loaded barges AND the pickup/return of unloaded barges associated with the rock supply to Freshwater Bayou Lock located at approximate Freshwater Bayou Channel Mile 1.5. The barge unloading time is expected to take up to 12 total days total starting at the initial delivery time of barges.
ITEM 007: The contractor will supply approximately 6 each loaded barges of B-size stone (or equivalent as approved by the government) to Catfish Point Control Structure located at Mile 24 of the Mermentau River, slightly west of Mermentau River/Grand Lake intersection. Each barge shall contain approximately 1,400 tons of Grade B stone (or equivalent as approved by the government). All delivered barges will start with a 5 day unloading period. All barges will be delivered at a coordinated period with the Government. The corps expects to receive 3 barges at the same time. When unloading is near completion on the barges, the government will coordinate the pickup and return of the barge set.
ITEM 008: This item covers a demurrage 24 hour rental rate for each barge beyond the initial 5 days of barge delivery. This line will be activated only if the government holds any barge for longer than 5 days or 120 hours after its initial delivery.
ITEM 009: This item covers the delivery of loaded barges AND the pickup/return of unloaded barges associated with the rock supply to the Catfish Point Control Structure located at Mile 24 of the Mermentau River, slightly west of Mermentau River/Grand Lake intersection. The barge unloading time is expected to take up to 12 total days total starting at the initial delivery time of barges.
Awarded contract W912P821C0028 to Crowley Holdings, LLC for 1100200.00 on 2021-06-15.
Notice history
| Notice | Type | Posted |
|---|---|---|
| Operations Division Rock Supply | Award Notice | |
| Operations Division Rock Supply | Solicitation | |
| Operations Division Rock Supply | Pre-Solicitation |