NV FLAP 400(1), Logandale Trails Access Road
Closed Pre-Solicitation Posted
This opportunity was awarded. See its 2 award notices in the notice history.
- Solicitation number
- 6982AF24B000020
- Agency
- Federal Highway Administration Department of Transportation
- Responses due
- Set-aside
- No set-aside
Opportunity facts
- NAICS code
- 237310 Highway, Street, and Bridge Construction
- Place of performance
- Logandale, Nevada 89021, United States
- Points of contact
-
- Denise Martinez cflacquisitions@dot.gov (202) 366-4000
Notice details come from SAM.gov. Updated .
About this opportunity
The Department of Transportation Federal Highway Administration is seeking contractors for the NV FLAP 400(1), Logandale Trails Access Road project in Logandale, Nevada. The project consists of approximately 3 miles of roadway construction, including excavation, aggregate base, asphalt concrete paving, concrete curb, barrier, and minor concrete pavement. Key requirements include the use of a desert tortoise biologist during construction. The project is expected to be advertised in August 2024, with construction starting in February 2025 and finishing in October 2025. The estimated cost range for the project is between $10,000,000 and $20,000,000.
This opportunity is not set-aside for any specific business size or type. The agency has not provided information about any incumbent contractors or the project's budget breakdown. The principal work items include 45,000 cubic yards of roadway excavation, 20,000 cubic yards of waste, 16,000 tons of aggregate base, 10,000 tons of asphalt concrete pavement, 4,500 linear feet of concrete curb, 1,200 linear feet of concrete barrier, and 1,100 square yards of minor concrete pavement.
Notice text
2 versions
Update #2 · Latest ·
THIS IS NOT AN INVITIATION FOR BID, PLAN AND SPEFICIATIONS ARE NOT AVAILBLE
THIS WILL BE ADERVTISED AS FULL AND OPEN COMPETITION.
PROJECT NUMBER and NAME: NV FLAP 400(1), LOGANDALE TRAILS ACCESS ROAD
PROJECT DESCRIPTION:
The project is in Logandale, Nevada in Clark County located 58 miles north east of Las Vegas, Nevada. The project begins on the west side of town and ends at the parking area for Logandale Trails, which is part of Nevada State Parks. The terrain is mostly rolling with elevation varying from 1,400 to 1,830 feet. The project consists of 4R work.
The project consists of roadway construction of approximately 3 miles with some large cuts and fills. The roadway will then get aggregate base and paved. Other elements of work include construction on low water crossings protected by concrete barrier and riprap then topped with concrete pavement. A desert tortoise biologist will be required at different stages of construction.
PRINCIPAL WORK ITEMS: Major items of work for the project include the following:
- Roadway Excavation – 45,000 CUYD
- Waste – 20,000 CUYD
- Aggregate Base – 16,000 TON
- Asphalt Concrete Pavement – 10,000 TON
- Curb, Concrete – 4,500 LNFT
- Concrete barrier – 1,200 LNFT
- Minor Concrete Pavement – 1,100 SQYD
ANTICIPATED SCHEDULE:
Advertise: August 2024
It is anticipated construction will start approximately February 2025 and finish approximately October 2025.
ESTIMATED COST RANGE: The anticipated cost range is between $10,000,000 and $20,000,000.
This will be advertised as full and open competition.
Update #1 ·
THIS IS NOT AN INVITIATION FOR BID, PLAN AND SPEFICIATIONS ARE NOT AVAILBLE
PROJECT NUMBER and NAME: NV FLAP 400(1), LOGANDALE TRAILS ACCESS ROAD
PROJECT DESCRIPTION:
The project is in Logandale, Nevada in Clark County located 58 miles north east of Las Vegas, Nevada. The project begins on the west side of town and ends at the parking area for Logandale Trails, which is part of Nevada State Parks. The terrain is mostly rolling with elevation varying from 1,400 to 1,830 feet. The project consists of 4R work.
The project consists of roadway construction of approximately 3 miles with some large cuts and fills. The roadway will then get aggregate base and paved. Other elements of work include construction on low water crossings protected by concrete barrier and riprap then topped with concrete pavement. A desert tortoise biologist will be required at different stages of construction.
PRINCIPAL WORK ITEMS: Major items of work for the project include the following:
- Roadway Excavation – 45,000 CUYD
- Waste – 20,000 CUYD
- Aggregate Base – 16,000 TON
- Asphalt Concrete Pavement – 10,000 TON
- Curb, Concrete – 4,500 LNFT
- Concrete barrier – 1,200 LNFT
- Minor Concrete Pavement – 1,100 SQYD
ANTICIPATED SCHEDULE:
Advertise: August 2024
It is anticipated construction will start approximately February 2025 and finish approximately October 2025.
ESTIMATED COST RANGE: The anticipated cost range is between $10,000,000 and $20,000,000.
Notice history
| Notice | Type | Posted |
|---|---|---|
| ND FLAP SDN 7NE(1) Hoffer Lake Access | Award Notice | |
| NV FLAP 400(1), Logandale Trails Access Road | Award Notice | |
| NV FLAP 400(1), Logandale Trails Access Road | Solicitation | |
| NV FLAP 400(1), Logandale Trails Access Road | Pre-Solicitation | |
| NV FLAP 400(1), Logandale Trails Access Road | Pre-Solicitation |