The U.S. Army Corps of Engineers, Little Rock District (SWL) has published a Special Notice announcing its intent to sole source the procurement of a three-phase gas-insulated 120,000 kVA transformer for a construction contract at the Bull Shoals Powerhouse. The statutory authority cited is 10 U.S.C. 3204(a)(5) as implemented by FAR 6.302-1(c)(1), which allows for sole sourcing when there is only one responsible source and no other supplies or services will satisfy the agency's requirements.

The purpose of this Special Notice is to solicit information from interested parties who believe they can meet the requirement for the specified transformer. The agency will not be purchasing the transformer directly from Toshiba, but it will be a brand name specification in the Design Bid Build (DBB) solicitation leading to the Firm-Fixed Price (FFP) construction contract. All responsible sources may submit a capability statement by 12:00 PM CDT on April 17, 2024, and the agency will consider these submissions in its determination.

Notice text

NOTICE OF INTENT TO SOLE SOURCE – Equipment: One (1) Three-Phase Gas-Insulated Generator-Step-Up (GSU) 120,000 kVA Transformer

This notice is being published in accordance with DFARS PGI 206-302-1, which states, “when utilizing the authority at FAR 6.302-1, the contracting officer shall post a request for information or a sources sought notice, and shall include the results of this inquiry in the justification required by FAR 6.303.” The statutory authority for this notice of intent to sole source brand name requirement is 10 U.S.C. 3204(a)(5) as implemented by FAR 6.302-1(c)(1) – Only one Responsible Source and No Other Supplies or Services Will Satisfy Agency Requirements.

The U.S. Army Corps of Engineers, Little Rock District (SWL), has a requirement for a Firm-Fixed Price (FFP) construction contract at Bull Shoals Powerhouse to remove and replace the “T3” bank of transformers with one three-phase gas-insulated GSU 120,000 kVA transformer. FAR Part 6.302-1(c)(1) is not intended to be used for the entire contract; rather, only the item listed below unless the results of this notice indicate otherwise.

Three-phase gas-insulated GSU 120,000 kVA transformer – Toshiba

The Government will not purchase transformer from Toshiba directly, but it will be a brand name specification requirement in the Design Bid Build (DBB) solicitation that will lead to the FFP construction contract.

*This is not a solicitation for competitive proposals; however, if any interested party believes that they can meet the above requirement, they may submit a capability statement to the point of contact listed in this Special Notice. All information furnished must be in writing and must contain sufficient detail to allow SWL to be able to determine if the interested party provide the requirement described herein.

All responsible sources may submit a capability statement which shall be considered by the agency. The submission must be received no later than 12:00 PM CDT on April 17, 2024.

Similar open opportunities

Opportunity Agency Set-aside Responses due
USACE Kansas City District - Stockton Dam and Powerhouse Procurement - Resin Impregnated Synthetic (RIS) Bushings Stockton, Missouri, United States · NAICS 335311 ENDIST Kansas City No set-aside

On GovTribe

Work this opportunity

  • Track it in your pipeline
  • Find teaming partners
  • Similar opportunities
  • Ask GovTribe AI about this opportunity

GovTribe for Federal Contractors