North Gunnison Substation 115kV Switch Install
Closed Solicitation Posted
This opportunity was awarded. See the award notice from .
- Solicitation number
- 89503226BWA000078
- Agency
-
Western Area Power Administration
Department of Energy
- Responses due
- Set-aside
- Total Small Business
Opportunity facts
- NAICS code
- 237130 Power and Communication Line and Related Structures Construction
- Points of contact
- More information
Notice details come from SAM.gov. Updated .
About this opportunity
The Western Area Power Administration seeks installation of a 115kV disconnect switch at the North Gunnison Substation, with proposals due July 9, 2026. The procurement is a total small business set-aside, restricting competition to firms meeting SBA small business size standards.
Work includes demolition and site development; removal and disposal of existing pedestals, rigid bus, insulators, and concrete foundations; and furnishing and installation of the 115kV disconnect switch, structural steel, foundations, and associated equipment. The switch installation will provide flexible operation to feed North Gunnison loads and enable WAPA to maintain all electrical substation equipment. NAICS code 237130 applies (Power and Communication Line and Related Structures Construction), as does PSC Y1PZ (Construction Of Other Non-Building Facilities). Amendment 0004 updated specification changes, the solicitation close date, and post-Q&A timing; Amendment 0003 corrected the bid opening date.
Notice text
3 versions
Update #3 · Latest ·
Amendment (0004) to update Specification change, Change Solicitation Close, and Post Q/A.
Update #2 ·
Amendment (0003) to correct Bid Opening Date.
North Gunnison 115-kV Switch Installation to add a 115kV Disconnect Switch to the bus work to provide flexible operation to feed the North Gunnison loads and allow WAPA to maintain all the electrical substation equipment.
a. Provide demolition and site development.
b. Remove and dispose of existing pedestals, rigid bus, insulators, and concrete foundations.
c. Furnish and install 115kV disconnect switch, structural steel, foundations, and associated equipment.
Update #1 ·
North Gunnison 115-kV Switch Installation to add a 115kV Disconnect Switch to the bus work to provide flexible operation to feed the North Gunnison loads and allow WAPA to maintain all the electrical substation equipment.
a. Provide demolition and site development.
b. Remove and dispose of existing pedestals, rigid bus, insulators, and concrete foundations.
c. Furnish and install 115kV disconnect switch, structural steel, foundations, and associated equipment.
Notice history
| Notice | Type | Posted |
|---|---|---|
| North Gunnison Substation 115kV Switch Installation | Award Notice | |
| This notice | Solicitation | |
| North Gunnison Substation 115kV Switch Installation | Pre-Solicitation |
On GovTribe
Work this opportunity
- Track it in your pipeline
- Find teaming partners
- Similar opportunities
- Ask GovTribe AI about this opportunity