NM FTBL 2004(1) Wild Rivers Road

Closed Pre-Solicitation Posted

This opportunity was awarded. See the award notice from , or the latest solicitation from .

Solicitation number
6982AF20SS0034
Agency
Federal Highway Administration Department of Transportation
Responses due
Set-aside
No set-aside

Opportunity facts

NAICS code
237310 Highway, Street, and Bridge Construction
PSC
Y1LB Construction Of Highways, Roads, Streets, Bridges, And Railways
Place of performance
Taos Nm Usa

Notice details come from SAM.gov. Updated .

About this opportunity

This pre-solicitation notice is seeking information from small businesses regarding their ability to complete roadway improvements on 4.75 miles of the Wild Rivers Back Country Byway located within the Rio Grande del Norte National Monument in New Mexico. The Department of Transportation Federal Highway Administration intends to procure construction services to rehabilitate, restore and resurface the roads and parking areas which includes embankment construction, roadway aggregate, full depth reclamation and asphalt concrete placement. Contractors must submit statements of intent, certifications, bonding capacity and past project experience by August 13, 2020 in order for the contracting officer to determine if a set-aside is possible for small businesses, HUBZone, women-owned, 8(a), or service-disabled veteran owned small businesses.

There is no set-aside designated at this time. The work involves significant quantities of 15,119 cubic yards of embankment construction, 5,055 cubic yards of roadway aggregate, 5 miles of full depth reclamation and 11,557 tons of asphalt concrete pavement. The proposed construction period is from April 2021 through November 2021 at an estimated value between $3.5 million and $7 million. The primary NAICS code is 237110 and PSC code D301.

Notice text

THIS IS NOT A REQUEST FOR BID – PLANS AND SPECIFICATIONS ARE NOT AVAILABLE

THIS NOTICE IS BEING ISSUED TO DETERMINE IF THERE IS SUFFICIENT INTEREST FROM QUALIFIED PRIME CONTRACTORS who are Small Businesses, HUBZone small businesses, Woman owned small business concerns, 8(a) small businesses, or Service disabled veteran owned small businesses and who intend to submit a bid for this solicitation to allow for a set-aside in one of these programs. Contractors MUST submit the following by e-mail to CFLAcquisitions@dot.gov for receipt by close of business (2 p.m. local Denver time) on August 13, 2020:

(1) A positive statement of your intention to submit a bid for this solicitation as a Prime Contractor;

(2) A copy of the letter from SBA stating date of HUBZone small business certification or acceptance to the 8(a) small business program. In the case of a Service Disabled Veteran Owned Small Business Concern, you must provide proof of eligibility (DD form 214 or a letter of adjudication from the Veterans Administration). This information must be provided in order to determine eligibility - DO NOT SEND COPIES OF YOUR SAM PROFILE.

(3) Letter from bonding agent stating your firm's capability to bond for a single project of $7 million, and your firm's aggregate bonding capacity; and

(4) Provide a list of road construction projects of equal or greater value and scope to the NM FTBL 2004(1) Wild Rivers Road project in which you performed (as the prime contractor) embankment construction, roadway aggregate, full depth reclamation, and asphalt concrete placement. Experience with guardrail installation, installation of sleeves for waterline repairs, and traffic control items is also necessary. State whether your firm was the prime contractor or subcontractor on the project. DO NOT SEND INFORMATION ON PROJECTS THAT DO NOT INCLUDE THE ABOVE WORK.

The size of a small business firm includes all parents, subsidiaries, affiliates, etc. Refer to the Code of Federal Regulations 13 CFR 121.103 for information on how the SBA determines affiliation and 13 CFR 121.108 regarding the penalties for misrepresentation of size status. All firms should be certified in the System for Award Management (SAM) located at https://www.sam.gov/

A Qualified HUBZone SBC receiving a HUBZone contract for general construction must spend at least 50% of the cost of the contract incurred for personnel on its own employees or employees of other qualified HUBZone SBCs. This requirement may be met by expending at least 50% of the cost of the contract incurred for personnel on its employees or it may subcontract at least 35% of the cost of the contract performance incurred for personnel to one or more qualified HUBZone SBCs. A qualified HUBZone SBC prime contractor may not, however, subcontract more than 50% of the cost of the

contract incurred for personnel to non-qualified HUBZone SBCs.

PROJECT DETAILS: NM FTBL 2004(1) Wild Rivers Road

PROJECT DESCRIPTION: The Wild Rivers Back Country Byway (BCB) is located within the Wild Rivers Recreation Area, a portion of the Rio Grande del Norte National Monument. It begins about 26 miles north of Taos, NM near the town of Cerro, NM, where NM state highway 378 dead-ends into the Byway. The Wild Rivers BCB is a 12.5-mile two-lane paved road that offers access points for recreational biking and mountain biking on 3 designated trails, sightseeing, camping / picnicking, fishing, and hiking on 10 designated trails. The access road is used for school visitations, architectural surveys, geology education services, horseback riding, and fishing tour guides.

The purpose of this project is to enhance overall public access to the Wild Rivers area with surfacing improvements of 4.75 miles of Loop Road to rehabilitate, restore, and resurface (3R) the roads and parking areas.  While a 1-mile section of the road remains for two-way traffic, the remaining 3.75 miles of the loop will be repaved as a one-way road and restriped to encourage non-vehicular traffic and enhanced livability by improving facilities for bicycle traffic.

  1. Change Loop Road traffic pattern. Two-way traffic will remain for 1 mile from the Entrance Road connection to the Visitor Center. The remainder of the 3.75 miles of Loop Road will be changed to one-way traffic (clockwise).
  2. Widen paved surface of the 3.75 miles to 34 feet to provide wider shoulders for bicycles. Proposed pavement typical section is two 11-foot lanes and two 6-foot shoulders with safety edge and proper shouldering material.
  3. Reconstruct pavement on the aprons where aggregate approach roads (from campgrounds, overlooks, employee parking, and the admin and host entries near the Visitor Center) intersect the paved loop road.  Recondition roadway aggregate along access roads to each area.
  4. Install sleeves for future waterline repairs.
  5. Install guardrail to proper elevations.
  6. Replace signing, pavement markings, and delineators per new traffic pattern.
     
    Items worth noting:
  • The peak construction season is estimated to April through end-October.  However, work can be performed depending on the weather.
  • Revegetation will be limited to seeding and mulching on disturbed slopes along the roadway and disturbed surfaces from construction activities.
  • Traffic control plans will need to consider methods to prevent parking within active work zones.

SIGNIFICANT QUANTITIES:

  • 15,119 cubic yards of Embankment construction.
  • 5,055 cubic yards of roadway aggregate.
  • 5 miles of full depth reclamation.
  • 11,557 tons of Asphalt concrete pavement.

It is anticipated that this project will be advertised in September, 2020. Construction is anticipated from April, 2021 – November, 2021.

The proposed project is estimated at a cost between $3,500,000 and $7,000,000.

Notice history

Notices posted for this opportunity, newest first
Notice Type Posted
NM FTBL 2004(1) Wild Rivers Road Award Award Notice
NM FTBL 2004(1) Wild Rivers Road Latest solicitation Solicitation
NM FTBL 2004(1) Wild Rivers Road Pre-Solicitation
NM FTBL 2004(1) Wild Rivers Road This notice · Original Pre-Solicitation

On GovTribe

Work this opportunity on GovTribe

  • Track it in your pipeline
  • Find teaming partners
  • Similar opportunities
  • Ask GovTribe AI about this opportunity