Naval Submarine Base Kings Bay Maintenance Dredging, Camden County, Georgia

Award Notice Posted

Solicitation number
W912EP25CA001
Agency
Awarded
to Cottrell Contracting Corporation
Set-aside
Total Small Business

Opportunity facts

Contract number
W912EP25CA001 Federal contract award
Place of performance
Kings Bay, Georgia, United States

Notice details come from SAM.gov. Updated .

About this opportunity

The Department of the Army Corps of Engineers Engineering District Jacksonville has awarded contract W912EP25CA001 to Cottrell Contracting Corporation for maintenance dredging at Naval Submarine Base Kings Bay in Camden County, Georgia. The contract, valued at $9,110,750, involves dredging multiple submarine base locations to specific depth requirements ranging from 39 to 47 feet, with dredged materials to be placed at Disposal Area Crab Island. The awarded contract includes a base work package, three optional work components (additional weir riser boards, secondary maintenance dredging, and mobilization/demobilization), and ancillary services such as bird monitoring and standby time. The contract was awarded on April 24, 2025, and is designated as a total small business set-aside opportunity.

Notice text

BASE:

Work consists of maintenance dredging the locations to required depths indicated in the table below and on the drawings. The placement of the dredged material will be at Disposal Area Crab Island (D/A-C) as indicated on the drawings and as directed by the Contracting Officer. Additional Base work also includes bird monitoring and standby time.

LOCATION

REQUIRED DEPTH

Range H to I and Upper Turning Basin (UTB)

45-foot UTB,

45-foot and 47-foot Channel

Range G to H and Explosive

Handling Basin (EHB)

44-foot and 47-foot

Range E to G and Magnetic Silencing Facility (MSF) North

44-foot

Site Six North (SS-N)

39-foot

Site Six South (SS-S) and Medium Auxiliary Repair Dock (ARDM) Yoke

45-foot

Explosive Handling Wharves (EHW)

47-foot

Refit Wharves

47-foot

Dry Dock Caisson Gate Sill and Dry Dock Caisson Gate Mooring Facility

46-foot

Option A:

Work consists of supplying additional field cut weir riser boards as requested by the Contracting Officer.

Option B:

Work consists of secondary maintenance dredging. The locations and required depths are indicated in the table below and on the drawings. The placement of the dredged material will be at Disposal Area Crab Island (D/A-C) as indicated on the drawings and as directed by the Contracting Officer. Option B work also includes bird monitoring and standby time.

LOCATION

REQUIRED DEPTH

Site Six South (SS-S) and Medium Auxiliary Repair Dock (ARDM) Yoke

45-foot

Site Six North (SS-N)

39-foot

Explosive Handling Wharves (EHW)

47-foot

Refit Wharves

47-foot

Dry Dock Caisson Gate Sill and Dry Dock Caisson Gate Mooring Facility

46-foot

Option C:

Work consists of Mobilization/Demobilization for secondary maintenance dredging if demobilization from the site occurs after completing all the Base work.

Awarded contract W912EP25CA001 to COTTRELL CONTRACTING CORPORATION for 9110750.00 on 2025-04-24.

Notice history

Notice Type Posted
This notice Award Award Notice
Naval Submarine Base Kings Bay Maintenance Dredging, Camden County, Georgia Latest solicitation Solicitation
Naval Submarine Base Kings Bay Maintenance Dredging, Camden County, Georgia Original Pre-Solicitation